Part 3 - DSN new

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

This is the shortest possible time in which the activity can be finished. It assumes that everything goes well.

a)

Optimistic

b)

Pessimistic

c)

Most Likely

d)

Accurate

2.
  • The longest possible time required to perform an activity under extremely bad conditions

a)

Optimistic

b)

Pessimistic

c)

Most Likely

d)

Accurate

3.

Critical path is the

a)

shortest time path in a network 

b)

longest time path in a network 

c)

efficient time path in a network 

d)

optimal time path in a network 

4.

Activities with zero slack lie on a

a)

Non-Critical path

b)

Critical path

c)

Normal path

d)

Crash path

5.

A ______ is a graphical representation of arrows and nodes for showing logical sequence of activities performed to achieve a project objectives.

a)

Bar

b)

Network

c)

Chart

d)

Diagram

6.

If duration of each activity in a project scheduling is not known with certainty then ____ network model is used

a)

CPM

b)

PERT

c)

PEST

d)

Deterministic

7.

________ analysis is used for planning, scheduling and controlling large complex projects.

a)

Transportation

b)

LPP

c)

Network

d)

Assignment

8.

_________ is developed to handle uncertain activity time

a)

CPM

b)

PERT

c)

Transportation

d)

LPP Problem

9.

_________ is developed for industrial projects for which activity times generally were known

a)

CPM

b)

PERT

c)

Transportation

d)

LPP Problem

10.

The ___________ is the length of time in which a non-critical activity or event can be delayed or extended without delaying the total project completion time.

a)

Float

b)

Slack

c)

Freetime

d)

Dummy