WorksheetsSG20 Baseline 2
Total questions: 180
Worksheet time: 3hrs 0mins
Examine if there is an alternate solution.
Escalate the issue to the technical infrastructure team.
Check the lessons learned database.
Consult the project sponsor about the issue.
While closing a project, the client finds some defects in the deliverable. What should the project manager do next?
Review the output against the acceptance criteria.
Extend the project until all deliverables are accepted.
Persuade the client to accept the output as is.
Pay the penalty for the defective item.
While reviewing progress, in the middle of an iteration, the Scrum Master points out a major risk due to a user story dependency. What should the project manager do next?
Update the product backlog to include the dependency.
Update the impacted plans and monitor the risk.
Enter the risk in the iteration’s risk register.
Involve the team to complete risk analysis.
A company is implementing Agile. Which action should the project manager take to ensure they are acting as a servant leader?
Keep strict control of the team and their activities.
Serve as a backup in case a team member becomes ill.
Ensure the team follows all processes as defined without questioning them.
Understand the bottlenecks and support the team to remove them.
A project manager notices that a critical team member has lost interest in the project. How should the project manager address this issue?
Escalate this issue to the human resources (HR) manager.
Replace the team member with a more interested team member.
Schedule a meeting with the team member to identify the cause.
Increase the team member's salary.
The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details. What should be the priority order in the product backlog?
Requirement 3, Requirement 1, Requirement 2
Risk 3,
Risk 1, Risk 2,
Requirement 3, Requirement 1, Requirement 2
Requirement 3, Risk 3, Requirement 1,
Requirement 2,
Risk 2
Requirement 3,
Requirement 1,
Risk 3,
Requirement 2,
Risk 1, Risk 2
A project manager is working on a project charter and discovers that some of the key stakeholders in this project are moving to other departments and their replacements have not been identified yet.
What should the project manager do next?
Put the project on hold until the replacements are identified.
Obtain support from the project sponsor to continue the project.
Perform an impact analysis of the possible delays.
Involve senior management to resolve the challenge.
A project manager has developed a schedule for a project involving various departments. The project manager met with each team member to develop a work breakdown structure (WBS). However, after the WBS was finalized, the project manager discovers that some tasks are redundant. What should the project manager have done to avoid this issue?
Enlisted the help of subject matter experts (SMEs) to provide scheduling guidance.
Organized group sessions for all team members to review the WBS together.
Improved the communication channels with all team members.
Prepared a task assignment matrix to represent the WBS.
A member of a development project team informs the project manager that the operating system is not going to be installed on time due to a late upgrade by the supplier. What should the project manager do first?
Determine the impact of the situation.
Modify the schedule to reflect the situation.
Inform the stakeholders about the problem.
Have the project team brainstorm a solution.
At the beginning of a project, the project manager meets the product owner and the business analyst to work on a requirements gathering process to create the list of requirements, features, and product backlog. Which elements should be considered to assure all user stories are well-written and sized correctly to allow a smooth agile project delivery? (Choose two)
Independent, negotiable, and estimable
Unique, applicable, and replicable
Subdivisible, suitable, and considerable
Concise, detailed, and executable
Valuable, small, and testable
A project manager realizes that some newly hired team members have not been as productive as hoped, which is putting the project at risk. What should the project manager do to resolve this issue?
Provide additional training to the new team members.
Conduct job shadowing within the project team.
Institute project milestone completion incentives.
Tell the team that productivity must improve.
A company has decided to utilize an international virtual team due to a lack of locally skilled resources. What can the project manager do to build an effective project communications management plan?
Study the impact of cultural differences on communication.
Adopt an Email "push" communication approach with the team.
Set up a project folder in the cloud and endorse a pull communication approach for the team.
Assign a communications manager to the project.
An external stakeholder has the potential to have a major impact on a project. What approach should the project manager take with this stakeholder?
Communicate with the stakeholder according to the stakeholder engagement and communications management plans.
Request feedback from the stakeholder so that the project meets the stakeholder's expectations and can be delivered as planned.
Add the stakeholder to the risk register and quantify the level of impact that the stakeholder could have.
Inform the stakeholder of the key project benefits and keep them updated on the project's milestone achievements.
You are leading a large and complex project. Due to the size and complexity of the project, you have decided that a project management team will perform most of the planning, and the remainder of the project team will be brought on when the initial planning is complete. In this scenario, when is the best time to conduct the project kick-off meeting?
As project execution begins
Shortly after project initiation X
As part of pre-project work
During initial project planning
A scrum team is midway into a sprint when the project sponsor approaches the scrum master and requests that a new, urgent, and potentially complex mandatory compliance-related requirement should be developed immediately in the current sprint. The sponsor stresses that if the requirement is not implemented, the entire project may be canceled.
What is the scrum master's best response?
Add the requirement to the product backlog and request the product owner to review the requirement after the sprint is over
Discuss the requirement with the product owner, and let them make a decision, including sprint cancellation
Submit a change request to update the scope baseline and add the requirement to the requirement traceability matrix
Add the requirement to the current sprint backlog and direct the team to start working on it immediately
An agile project is being carried out by a small startup company. Everybody is located in the same office space. The sponsor likes to come by to the team space every day to see how the project progresses. Due to personal circumstances, the sponsor will be away for several weeks, and requests the project manager for a weekly project status update. What is the best way for the project manager to accommodate the sponsor's request?
Speak to the sponsor over the phone to communicate the project status
Email a slideshow presentation and a spreadsheet report to the sponsor
Take pictures of the information radiators and email them to the sponsor
Wait until the sponsor is back and provide them with the latest project status
A project to develop a new software application for a custome way into i cution. According to t oje management plan, the quality assurance team should start testing the product after all work packages are completed. Suddenly, the customer's competitor launches a similar product, and the customer goes out of business. The project is terminated. What could the project manager have done differently to bring value to the business and customer?
Accelerated product development using schedule compression techniques such as crashing, fast-tracking, resource leveling, resource smoothing, and leads and lags
Replaced the project team members by generalizing specialists experienced in software development, product testing, and interpretation of customer business requirements
Requested additional contingency and management reserves during project planning to cover the costs of project termination in case the customer goes out of business
Applied an adaptive development approach in which the product is developed incrementaly via short iterations with continuous feedback from the customer and stakeholders
A project manager has been experiencing unnecessary delays during project execution in obtaining signatures from senior management due to an inadequate notification process when a signature is required. Addressing the issue only requires a minor update to the communications management plan. What should the project manager do next?
Update the cost baseline
Update the communications management plan
Submit a change request
Implement the proposed solution