WorksheetsRVTI Review PDI DC Electrical Systems
Total questions: 11
Worksheet time: 10mins
During the first step in performing PDI on electrical systems, safe work practices include which of the following? (Choose all that apply.)
safety glasses
footwear
gloves
no loose jewelry
Place the steps for the simple series battery bank in the correct order.
configure batteries on test bench
interconnect batteries
connect distribution system to the battery bank
record voltage
record amperage
Place the steps for the series/parallel battery bank in the correct order.
configure batteries on test bench
connect two sets of 6V batteries in a series
connect each set of 6V batteries in parallel
connect distribution system to the battery bank
record voltage, then amperage
Place the steps for a parallel battery bank in the correct order.
configure batteries on test bench
connect two 12V batteries in parallel
connect distribution system to the battery bank
record voltage
record amperage
When connecting the distribution system to the battery bank, connect the batteries...
positive to positive, negative to negative
positive to negative, negative to positive
in parallel
in series
Match the following requirements for creating battery banks.
simple series
no requirement
series/parallel
two sets of 6V batteries
parallel
two 12V batteries
When constructing a battery bank, the first step is always...
tightening connections
to configure batteries on a test bench
checking the connections
to configure batteries on a test bench, with batteries oriented positive and negative
The first step for Power Converter PDI is to...
plug the coach into AC power source
plug the coach into DC power source
verify there is a power source
measure DC voltage
After measuring DC voltage at the converter and at the battery, you notice there is a voltage drop. Your next step is...
contacting a Level 2 technician
Documenting
Unplugging the coach from the power source
Rechecking
When completing the Alternator PDI, measure DC voltage at the...
coach battery bank
chassis battery bank
converter
charge controller output
After assembling documentation for the Solar PDI, you should...
inspect mounting brackets for rust
measure output voltage at charge controller output
inspect mounting brackets for proper installation
measure output voltage at the battery bank