PRM final (FIT HANU)

Total questions: 100

Worksheet time: 50mins

Name
Class
Date
1.

To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?


a)

Critical path method

b)

Flowchart

c)
  1. Precedence diagramming

d)

Work breakdown structure

2.

All of the following are factors in the assessment of project risk EXCEPT:


a)

Risk event

b)
  1. Risk probability

c)

Amount at stake

d)

Insurance premiums

3.

A project manager is being considered for a particular project that will deal exclusively with global virtual teams. He only has experience with local teams. What should he do when discussing the opportunity with the sponsor?

a)
  1. Since he has led projects and teams, it does not make any difference that these are all global virtual teams, so he does not need to bring it up.

b)

He should avoid any conversation regarding the types of teams involved so the sponsor does not know he lacks experience in this area

c)

The project manager should point out to the sponsor that he has not had experience with global virtual teams but discuss why he thinks he is a good fit for the project anyway

d)
  1. The project manager should point out to the sponsor that he has not had experience with global virtual teams and therefore must decline the assignment.

4.

A project has three critical paths. Which of the following BEST describes how this affects the project?

a)

It makes it easier to manage

b)

It increases the project risk.

c)

It increases the project risk.

d)
  1. It makes it more expensive

5.

Risk tolerances are determined in order to help:

a)
  1. The team rank the project risks

b)

The project manager estimate the project.

c)

The team schedule the project.

d)
  1. Management know how other manager will act on the project.

6.

A major negotiation with a potential subcontractor is scheduled for tomorrow when you discover there is a good chance the project will be cancelled. What should you do?


a)
  1. Do not spend too much time preparing for the negotiations

b)
  1. Cut the negotiations short

c)
  1. Only negotiate major items.

d)
  1. Postpone the negotiations.


7.

If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?

a)

Perform a Monte Carlo analysis.

b)
  1. Fast track the project

c)
  1. Fast track the project

d)

Analyze the life cycle costs

8.

All of the following are common results of risk management EXCEPT:


a)
  1. Contract terms and conditions are created.

b)
  1. The project management plan is changed

c)
  1. The communications management plan is changed.

d)

The project charter is changed

9.

You've been assigned to take over managing a project that should be half complete according to the schedule. After an extensive evaluation, you discover that the project is running far behind schedule and that the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action?


a)
  1. Try to restructure the schedule to meet the project deadline.

b)
  1. Report your assessment to the sponsor.

c)
  1. Turn the project back to the previous project manager.

d)
  1. Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.

10.

When would a milestone chart be used instead of a bar chart?


a)
  1. Project planning.

b)
  1. Reporting to team members.

c)
  1. Reporting to management.

d)
  1. Risk analysis

11.

Purchasing insurance is BEST considered an example of risk:

a)

Mitigation

b)
  1. Transfer

c)
  1. Acceptance

d)
  1. Avoidance

12.

You are halfway through a major network rollout. There are 300 locations in the US with another 20 in England. A software seller has just released a major software upgrade for some of the equipment being installed. The upgrade would provide the customer with functionality they requested that was not available at the time the project began. What is the BEST course of action under these circumstances?

a)
  1. Continue as planned, your customer has not requested a change.

b)
  1. Inform the customer of the upgrade and the impacts to the project's timeline and functionality if the upgrade is implemented.

c)
  1. Implement the change and adjust the schedule as necessary because this supports the customer's original request.

d)
  1. Implement the change to the remaining sites and continue with the schedule.

13.

Your project management plan results in a project schedule that is too long. If the project network diagram can not change but you have extra personnel resources, what is the BEST thing to do?

a)

Fast track the project

b)

Level the resources

c)

Crash the project

d)

Monte Carlo analysis

14.

You are finding it difficult to evaluate the exact cost impact of risks. You should evaluate on ano

a)
  1. Quantitative basis

b)
  1. Numerical basis

c)
  1. Qualitative basis

d)
  1. Econometric basis

15.

You are a project manager for one of many projects in a large and important program. At a high level status meeting, you note that another project manager has reported her project on schedule. Looking back on your project over the last few weeks, you remember many deliverables from the other project that arrived late. What should you do?


a)

Meet with the program manager.

b)
  1. Develop a risk control plan.

c)
  1. Discuss the issue with your boss.

d)

Meet with the other project manager.

16.

Which of the following is the BEST thing to do to try to complete a project two days earlier?


a)

Tell senior management that the project's critical path does not allow the project to be finished earlier.

b)

Tell your boss.

c)
  1. Meet with the team and look for options for crashing or fast tracking the critical path.

d)
  1. Work hard and see what the project status is next month.

17.

Output of the Plan Risk Responses process includes:

a)

Residual risks, fallback plans, and contingency reserves

b)

Risk triggers, contracts, and a risk list.

c)

Secondary risks, process updates and risk owners.

d)

Contingency plans, project management plan updates and change requests.

18.

You have always been asked by your management to cut your project estimate by 10% after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25% reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation?

a)
  1. Replan to achieve a 35% improvement in downtime.

b)
  1. Reduce the estimates and note the changes in the risk response plan.

c)
  1. Provide an accurate estimate of the actual costs and be able to support it.

d)
  1. Meet with the team to identify where you can find 10% savings.

19.

. In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:


a)

Risk impact of crashing each activity.saas

b)

Customer's opinion of which activities to crash.

c)

Boss's opinion of which activities to crash and in which order.

d)
  1. Project life cycle phase in which the activity is due to occur.

20.

Workarounds are determined during which risk management process?

a)

Identify Risks

b)

Perform Quantitative Risk Analysis

c)

Plan Risk Responses

d)

Monitor and Control Risks

21.

You are in the middle of a project when you discover that a software seller for your project is having major difficulty keeping employees due to a labor dispute.Many other projects in your company are also using the company's services. What should you do?


a)

Attempt to keep the required people on your project.

b)

Tell the other project managers in your company about the labor problem.

c)

Contact the company and advise it that you will cancel its work on the project unless it settles its labor dispute.

d)
  1. Cease doing business with the company.

22.

Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity?

a)

Sequence Activities

b)

Develop Schedule

c)

Define Scope

d)
  1. Develop Project Charter

23.

During which risk management process is a determination to transfer a risk made?

a)

Identify Risks

b)

Perform Quantitative Risk Analysis

c)

Plan Risk Responses

d)

Monitor and Control Risks.

24.

All of the following are the responsibility of a project manager EXCEPT:

a)


  1. Maintain the confidentiality of customer confidential information.

b)
  1. Determine the legality of company procedures.

c)
  1. Ensure that a conflict of interest does not compromise the legitimate interest of the customer.

d)
  1. Provide accurate and truthful representations in cost estimates.

25.

A project manager is in the middle of the executing process of a very large construction project when he discovers that the time needed to complete the project is longer than the time available. What is the BEST thing to do?

a)
  1. Cut product scope

b)
  1. Meet with management and tell them that the required date can not be met

c)
  1. Work overtime

d)
  1. Determine options for schedule compression and present management with his recommended option

26.

A project management has just finished the risk response plan for a US$387,000 engineering project. Which of the following should he probably do NEXT?


a)
  1. Determine the overall risk rating of the project.

b)
  1. Begin to analyze the risks that show up in the project drawings.

c)
  1. Add work packages to the project work breakdown structure.

d)
  1. Hold a project risk reassessment.

27.

In order to complete work on your projects, you have been provided confidential information from all of your clients. A university contacts you to help it in its research. Such assistance world require you to provide the university with some of the client data from your files. What should you do?

a)
  1. Release the information but remove all references to the client's names.

b)
  1. Provide high level information only.

c)
  1. Contact to your clients and seek permission to disclose the information.

d)
  1. Disclose the information.

28.

During project planning, you estimate the time needed for each activity and then add the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?


a)

The team did not create the estimate, and estimating takes too long using that method.

b)
  1. The team did not create the estimate, and a network diagram was not used.

c)
  1. The estimate is too long and should be created by management.

d)
  1. The project estimate should be the same as the customer's required completion date

29.

A project manager asked various stakeholders to determine the probability and impact of a number of risks. He then analyzed the assumption. He is about to move to the next step of risk management. Based on this information, what has the project manager forgotten to do?

a)

Evaluate trends in risk analysis.

b)

Identify triggers.

c)

Provide a standardized risk rating matrix.

d)

Create a fallback plan.

30.

Management has promised you part of the incentive fee from the customer if you complete the project early. While finalizing a major deliverables, your team informs you that the deliverables meets the requirements in the contract but will not provide the functionality the customer needs. If the deliverable is late, the project will not be completed early. What action should you take?

a)

Provide the deliverable as it is.

b)

Inform the customer of the situation and work out a mutually agreeable solution.

c)

Start to compile a list of delays caused by the customer to prepare for negotiations.

d)

Cut out other activities in a way that will be unnoticed to provide more time to fix the deliverable.

31.

You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?

a)

Precedence diagramming method.

b)

Arrow diagramming method.

c)

Critical path method.

d)

Operational diagramming method.

32.

A project manager has assembled the project team, identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions, and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?

a)

Simulation

b)

Risk mitigation.

c)

Overall risk ranking for the project.

d)
  1. Involvement of other stakeholders.

33.

You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do is:

a)
  1. Develop options to meet the milestone date.

b)
  1. Change the milestone date.

c)
  1. Remove any discussion about due dates in the project status report.

d)
  1. Educate the team about the need to meet milestone dates.

34.

A dependency requiring that design be completed before manufacturing can start is an example of a:


a)
  1. Discretionary dependency.

b)
  1. External dependency.

c)
  1. Mandatory dependency.

d)
  1. Scope dependency.


35.

If a project has a 60% chance of a US$100,000 profit and a 40% chance of a US$100.000 loss, the expected monetary value for the project is:

a)
  1. $100.000 profit

b)
  1. $60.000 loss

c)
  1. $20.000 profit

d)
  1. $40.000 loss

36.

A project manager gathered data to perform earned value calculations on his project. He used the results to report to management that the project is under budget and on schedule. After reporting this information, he discovered that the base figures he used in the calculations were incorrect, as they came from an old copy of the project file which had not been updated. What should he do now?

a)

He should contact management to make them aware of the error, give the correct information, and explain how he made the mistake

b)

He should contact management and tell them to expect some changes in the next reporting period, and that things are starting to look gloomy.

c)

He should use the correct figures to calculate the information when it is time for the next report and ignore the fact the he reported incorrect information.

d)

He should tell management that the data he received from team members was incorrect and thus the report was not accurate.

37.

You have a project with the following activities: Activity A takes 40 hours and can start after the project starts. Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and take 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is TRUE if activity B actually takes 37 hours?

a)

The crititcal path is 67 hours

b)

The critical path changes to Start, B, d, End.

c)

The critical path is Start, A, C, E,F, End.

d)

The critical path increases by 12 hours

38.

Your task is to develop and install 10 printer drivers with a budget of $100.000 in 10 weeks. At week 5, 4 printer developed and installed and $47.500 was spent. What is CPI & SPI

a)

CPI\=0.84 & SPI\=0.80

b)

CPI\=$2.500 & SPI\=$10.000

c)

CPI\=1.02 & SPI\=1.08

d)

None

39.

Samantha is a Project Manager of a Software product. The project required an initial investment of $100,000. The project generated a revenue of $20,000 in the first year. There were operational cost of $5000 and tax liability of another $5000. What is the return on invested capital?

a)

5%

b)

10%

c)

20%

d)

0%

40.

You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following BEST describes what this type of input is called?

a)
  1. Mandatory dependency.

b)
  1. Discretionary dependency

c)
  1. External dependency.

d)
  1. Heuristic

41.

You are a project manager for the contruction of a major new manufacturing plant that has never been done before. The project cost is estimated at US$30,000,000 and will make use of three sellers. Once begun, the project cannot be cancelled as there will be a large expenditure on plant and equipment, As the project manager, it would be MOST important to carefully:Review all cost proposals from the sellers

a)
  1. Review all cost proposals from the sellers

b)

Examine the budget reserves.

c)
  1. Complete the project charter.

d)
  1. Perform an identification of risks.

42.

While testing the strength of concrete poured on your project, you discover that over 35% of the concrete does not meet your company's quality standards. You feel certain the concrete will function as it is, and you don't think the concrete needs to meet the quality level specified. What should you do?

a)
  1. Change the quality standards to meet the level achieved.

b)
  1. List in your reports that the concrete simply 'meets our quality needs'.

c)
  1. Ensure the remaining concrete meets the standard.

d)
  1. Report the lesser quality level and try to find a solution.

43.

A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?

a)
  1. Change requests

b)
  1. Schedule change control system

c)
  1. Recommended corrective actions

d)
  1. Reserves

44.

During the Plan Risk Management process, your team has come up with 434 risks and 16 major causes of those risks. The project is the last of a series of project that the team has worked on together. The sponsor is very supportive, and a lot of time was invested in making sure the project work was complete and signed off by all key stakeholders.

During project planning, the team cannot come up with an effective way to mitigate or insure against a risk. It is not work that can be outsourced, nor can it be deleted. What would be the BEST solution?


a)

Accept the risk.

b)
  1. Continue to investigate ways to mitigate the risk.

c)
  1. Look for ways to avoid the risk.

d)
  1. Look for ways to transfer the risk.

45.

You are the project manager for a new international project, and your project team includes people from four countries. Most of the team members have not worked on similar projects before, but the project has strong support from senior management. What is the BEST thing to do ensure that cultural differences do not interfere with the project?

a)

Spend a little more time creating the work breakdown structure and making sure it is complete.

b)

As the project manager, make sure you choose your words carefully whenever you communicate.

c)

Ask one person at each team meeting to describe something unique about their culture.

d)
  1. Carefully encode all of the project manager's communications.

46.

A project manager is taking over a project from another project manager during the planning process group. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be BEST to look at the:

a)

Communication management plan

b)

Update management plan

c)

Staffing management plan

d)

Schedule management plan

47.

A project manager is quantifying for her project. Several of her experts are offsite, but wish to be included. How can this be done?

a)

Use Monte Carlo analysis using the Internet as a tool.

b)

Apply the critical path method.

c)

Determine options for recommended corrective action.

d)

Apply the Delphi technique

48.

A project has a tight budget when you begin negotiating with a seller for a piece of equipment. The seller has told you that the equipment price is fixed. Your manager has told you to negotiate the cost with the seller. What is your BEST course of action?

a)

Make a good faith effort to find a way to decrease the cost.

b)

Postpone negotiations until you can convince your manager to change his mind.

c)

Hold the negotiations, but only negotiate other aspects of the project.

d)
  1. Cancel the negotiations.

49.

A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?

a)

Critical path method

b)

PERT

c)

Monte Carlo

d)

Resource leveling

50.

An experienced project manager has just begun working for a large information technology integrator. Her manager provides her with a draft project charter and immediately asks her to provide and analysis of the risks on the project. Which of the following would BEST help in this effort?

a)

An article from PM Network Magazine

b)

Her project scope statement from the project planning process.

c)

Her resource plan from the project planning process.

d)

A conversation with a team member from a similar project that failed in the past.

51.

A certified PMP is contacted by PMI and asked to provide information regarding another project manager who has been reported to be involved in unethical activities. The PMP certified project manager knows his information would support the accusations and the other project manager in question is a friend. He decides that the best thing to do would e to not respond and therefore neither confirm nor deny accusations. Would this be the right thing to do?

a)

Yes. It would be a safe thing to do just ignore the request and stay out of it.

b)

No. If he know something, he required by the Code of Ethics and Professional Conduct conduct to cooperate.

c)

No. It would be better to deny the charges against his friend to maintain the relationship.

d)
  1. Yes. It is expected that project managers will support each other in the field against outsiders.

52.

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the labor hours per installation from past project to predict the future/ This is an example of which of the following?

a)

Parametric estimating

b)

3-point estimating

c)

Analogous estimating

d)

Monte Carlo analysis.

53.

You have been appointed as the manager of a new, large and complex. Because this project is business-critical and very visible, senior management has told you to analyze the project's risks and prepare response strategies for them as soon as possible. The organization has risk management procedures that are seldom used or followed, and has had a history of handling risks badly. The project's first milestone is in two weeks. In preparing the risk response plan, input from which of the following is genereally LEAST important?

a)

Project team members

b)

Project sponsor

c)
  1. Individuals reponsible for risk management policies and templates.

d)
  1. Key stakeholders.

54.

A project manager discovers a defect in a deliverable due to the customer under contract today. The project manager knows the customer does not have the technical understanding to notice the defect. The deliverable meets the contract requirements but it does not meet the project manager's quality standard. What should the project manager do in this situation?

a)

Issue the deliverables and get formal acceptance from the customer.

b)

Note the problem in the lessons learned so future projects do not encounter the same problem.

c)

Discuss the issue with the customer.

d)
  1. Inform the customer that the deliverables will be late

55.

If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity?

a)

1

b)

1.3

c)

3

d)

6

56.

You are in a middle of a two-year project to deploy new technology to field offices across the country. A hurricane caused power outages just when the upgrade near completion. When the power was restored, all of the project reports and historical data were lost with no way of retrieving them. What should have been done to prevent this problem?

a)

Purchase insurance

b)

Plan for a reserve fund.

c)

Monitor the weather and have a contigency plan.

d)
  1. Schedule the installation outside the hurricane season.

57.

 Management tells a project manager to subcontract part of the project to a company that management has worked with manay times. Under these circumstances, the project manager should be MOST concerned about:

a)

Making sure the company has the qualifications to complete the project.

b)

Meeting management expectations of time.

c)

The cost of the subcontracted work.

d)

The contract terms and conditions

58.

An activity has an ES=3, LS=13, EF=9 and LF=19 of day 19. The activity

a)

Is on the critical path

b)

Has a lag

c)

Is progressing wellIs not on the critical path

d)
  1. Is not on the critical path

59.

A system development project is nearing project closing when a previously unidentified risk is discovered. This could potentially affect the project's overall ability to deliver. What should be done NEXT?

a)

Alert the project sponsor of potential impacts to cost, scope, or schedule.

b)

Qualify the risk.

c)

Mitigate this risk by developing a risk response plan.

d)

Develope a workaround

60.

Three students from another country are working as interns on a project. The project manager has arranged for some games to play as team-building activities to help create a close knit sense of team with the group members. At the event where the activities are taking place, the three students refuse to participate, claiming the behaviour involved is unacceptable in their country and they would be very uncomfortable participating. What should the project manager do?


a)
  1. He should tell the students that they need to become familiar with the how things are done in this country and that they must play along.

b)
  1. He should excuse the students from playing and arrange to discuss with them alternative activities that they would more comfortable with.

c)
  1. He should report the students to their functional manager and request they be removed from the project since their attitude will have a negative impact on the project.

d)
  1. He should tell the students they are excused from the activities and to not attend any team building activites in the future.

61.

The cost performance index of a project is 0.6 and the schedule performance index is 0.71. The project has 625 work packages and is being completed over a four-year period. The team members are very inexperienced, and the project received little support for proper planning. Which of the following is the BEST thing to do?

a)

Update risk identification and analysis.

b)
  1. Spend more time improving the cost estimates.

c)
  1. Remove as many work packages as possible.

d)
  1. Reorganize the responsibility assignment matrix.

62.

A project manager discovers an urgent need for outsourced resources on the project. He knows he has the money to cover the cost of these resources. He goes to the procurement manager and explains the situation, insisting a contract be drawn up today so he can obtain resources and circumvent the standard procedure.Is this the correct process to follow?

a)
  1. Yes, of course. For urgent needs, it is not necessary to follow the organization's procedure regarding procurement.

b)
  1. Yes. Urgent needs from projects should always be dealt with immediatedly as directed by the project manager.

c)
  1. No. The procurement manager has a process to follow when creating contracts that helps protect the company and its projects.

d)
  1. No. The procurement manager should be checking in with the project manager to see if he is in need of a contract, rather than making the project manager come and ask for one.

63.

While preparing your risk responses, you identify additional risks. What should you do?


a)
  1. Add reserves to the project to accomodate the new risks and notify management.

b)
  1. Document the risk items, and calculate the expected monetary value based on probability and impact that result from occurrences.

c)
  1. Determine the risk events and the associated cost, then add the cost to the project budget as a reserve.

d)
  1. Add a 10% contingency to the project budget and notify the customer.


64.

The engineering department wants the project objective to be a 10% improvement in throughput. The IT department wants no more than 5% of its resources to be used on the project. Management, who is also your boss, wants the project team to decrease tax liability. The BEST thing you can do is:

a)
  1. Put a plan together that meets all the objectives.

b)
  1. Have these people get together and agree on one objective.

c)
  1. Include the engineering and information technology objectives but hold further meetings.

d)
  1. Include only management's objective.

65.

You have just been assigned as the project manager for a new telecommunication project that is entering the second phase of the project. There appear to be many risks on this project, but no one has evaluated them to assess the range of possible project outcomes. What needs to be done?


a)
  1. Plan Risk Management.

b)
  1. Perform Quantitative Risk Analysis

c)
  1. Plan Risk Responses.

d)
  1. Monitor and Control Risks.

66.

You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual hours spent on project activities. This results in skewed project statistics. What is the MOST appropriate action to be taken?

a)

Discuss the impacts of these actions with team members.

b)
  1. Report the team member's action the their functional managers.

c)

Continue reporting information as presented to you.

d)

Provide accurate and truthful representations in all project reports.

67.

Which of the following are GENERALLY illustrated BETTER by bar charts than network diagram?

a)

Logical relationships

b)

Critical paths

c)

Resource trade-offs.

d)

Progress or status.

68.

Assuming that the ends of a range of estimate are +/- 3 sigma from the mean, which of the following range estimate involves the LEAST risk?

a)

30 days, plus or minus 5 days.

b)

22-30 days

c)

Optimistic 26 days, most likely\=30 days, pessimistic\=33 days.

d)

Mean of 28 days

69.

A project manager is working with a vendor on a project when she learns that the vendor has bribed a subcontractor to work on this project instead of fulfilling previous commitments to other projects. What should she do?


a)

She should report the offense to management and the project managers of the affected project.

b)

She should not do anything because thisis th vendor's problem. The project manager herself didn't do anything wrong

c)

She should report this to other subcontractor so they know they could get more money form the vidor

d)

She should resign form the project so as remove herself form this type of activity, but keep it to herself rather than cause problems

70.

During project excuting, a team member identifies a risk that is not in the risk register. What should you do?

a)

Get further information on how the team member identified the risk, because you already performed a detailed analysis and did not identify this risk.

b)

Disregard the risk, because risks were identified during project planning.

c)

Inform the customer about the risk.

d)
  1. Analyze the risk.

71.

During project executing, a major problem occurs that was not included in the risk register. What should you do FIRST?

a)
  1. Create a workaround.

b)

Reevaluate the Identify Risks process.

c)
  1. Look for any unexpected effects of the problem.

d)
  1. Tell management.

72.

The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others?


a)
  1. Include the expected monetary value of the risk in the new cost estimate.

b)
  1. Talk to the customer about the impact of the change.

c)
  1. Analyze the impacts of the change with the team.

d)
  1. Change the risk management plan.


73.

Which of the following is a chief characteristic of the Delphi technique?

a)
  1. Extrapolation from historical records form previous projects.

b)
  1. Expert opinion

c)

Analytical hierarchy process.

d)
  1. Bottom-up approach. 

74.

A project has had some problems, but now seems under control. In the last few months, almost all the reserve has been used up and most of the negative impacts of events that had been predicted have occurred. There are only four activities left, and two of them are on the critical path. Management now informs the project manager that it would be in the performing organization's best interest to finish the project two weeks earlier than scheduled in order to receive an additional profit. In response, the project manager sends out a request for proposal for some work that the team was going to do, in the hopes that another company might be able to do the work faster. The project manager can BEST be said to be attempting to work with:

a)
  1. Reserve

b)
  1. Opportunities

c)
  1. Scope verification

d)
  1. Threats

75.

Monte Carlo analysis is used to:

a)


  1. Get an indication of the risk involved in the project

b)
  1. Estimate an activity's length

c)
  1. Simulate the order in which activities occur.

d)
  1. Prove to management that extra staff is needed.

76.

A project team is creating a project management plan when management asks them to identify project risks and provide some form of qualitative output as soon as possible. What should the project team provide?

a)

Prioritized list of project risks

b)

Risk triggers

c)

Contigency reserves

d)

Probability of achieving the time and cost objectives.

77.

A project manager is creating a risk response plan. However, everytime a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for project manager do?

a)

Document the new risk and continue the Plan Risk Responses process.

b)

Make sure the project work is better understood.

c)

Spend more time making sure the risk responses are clearly defined.

d)

Get more people involved in the Identity Risks process. since risks have been missed.

78.

A watchlist is and output of which risk management process?

a)

Plan Risk Responses

b)
  1. Perform Quantitative Risk Analysis

c)
  1. Perform Qualitatitive Risk Analysis

d)
  1. Plan Risk Management

79.

During the Identify Risk process, a project manager made a long list of risk identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers has been identified. Later, in the Plan Risk Responses process. he took all the risks identified by the stakeholder and determined ways to mitigate them. What has he done wrong?

a)
  1. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved.

b)
  1. More people should be involved in the Plan Risk Responses process.

c)
  1. The project manger should have create workarounds.

d)
  1. Triggers are not identified until the Identify Risks process


80.

Lag means:

a)

The amount of time an activity can be delayed without delaying the project finish date.

b)

The amount of time an activity can be delayed without delaying the early start date of its successor

c)

Waiting time

d)

The product of a forward and backward pass.

81.

During the Identify Risk process, a project manager made a long list of risk identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers has been identified. Later, in the Plan Risk Responses process. he took all the risks identified by the stakeholder and determined ways to mitigate them. What has he done wrong?

a)
  1. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved.

b)
  1. More people should be involved in the Plan Risk Responses process.

c)
  1. The project manger should have create workarounds.

d)
  1. Triggers are not identified until the Identify Risks process

82.

Which of the following risk events is MOST likely to interfere with attaining a project's schedule objective?

a)
  1. Delays in obtaining required approvals

b)
  1. Substantial increase in the cost of purchased materials

c)

Contract disputes that generate claims for increased payments

d)
  1. Slippage of the planned post-implementation review meeting

83.

You are in the middle of a new product development for your publicly traded company when you discover that the previous project manager made a $3mil payment that not approved in accordance with your company policies. Luckily, the project cost performance index is 1,2. What should you do?

a)
  1. Contact your manager.

b)
  1. Put the payment in a escrow account

c)
  1. Bury the cost in large cost center available

d)
  1. Ignore the payment

84.

Which of the following MUST be an agenda item at all team meeting?

a)

Discussion of project risks.

b)

Status of current activities.

c)

Identification of new activities.

d)

Review of project problems.

85.

Which of the following is the BEST project management tool to use to determine the longest time the project will take?

a)

WBS

b)

Network diagram

c)

Bar chart

d)

Project charter

86.

If a risk has a 20% chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project?

a)

Less than 1%

b)

20%

c)

60%

d)

80%

87.

A decision has to be made regarding project selection. Several project managers have been asked to give their opinions to the executive committee. Each project manager has a personal interest because the project chosen will drive which project manager will be assigned. The project chosen will be high priority and high visibility, with substantial reward for success. How should the project managers make their recommendations?

a)

They should each explain why the project they would be in charge of would be the best to choose and provide documentation to substantiate it

b)

They should recommend the project that would be best for the company in the long run, regardless of who is going to run it.

c)

They should make a chart that shows the pros and cons of each project making sure to list more pros for the one they would run and less cons to prove its value

d)

They should not give an opinion since it would not be objective

88.

Which of the following is CORRECT?

a)

The critical path helps prove how long the project will take

b)
  1. There can be only one critical path

c)
  1. The network diagram will change every time the end date changes

d)
  1. A project can never have negative float


89.

If a risk event has a 90% chance of occuring, and the consequences will be US$10,000, what does US$9,000 represent?

a)
  1. Risk value

b)
  1. Present value

c)
  1. Expected monetary value

d)
  1. Contingency

90.

When checking the calendar of a team member to schedule a meeting, you see she has scheduled a meeting with a key stakeholder that you were not informed of. The BEST approach would be to:

a)

Avoid mentioning it to the team member but continue to watch her activities.

b)

Notify your boss about the problem

c)

Address the concern with the team member's boss

d)
  1. Address the concern with the team member

91.

What is the duration of a milestone?

a)
  1. Shorter than the duration of the longest activity.

b)
  1. Shorter than the activity it represent

c)
  1. There is no duraton.

d)
  1. Same length as the activity it represents.

92.
  1. Identify Risks and Monitor and Control Risks

a)
  1. Perform Quantitative Risk Analysis and Identify Risks

b)

Identify Risks and Monitor and Control Risks

c)
  1. Perform Qualitative Risk Analysis and Monitor and Control Risks

d)
  1. Identify Risks

93.

Your employee is three days late with a report. Five minutes before the meeting where the topic of the report is to be discussed, she hands you the report. You notice some serious errors in it. What should you do?

a)

Cancel the meeting and reschedule when the report is fixed

b)

Go to the meeting and tell the other attendees there are errors in the report.

c)

Force the employee to do the presentation and remain silent as the other attendees find the errors

d)

Cancel the meeting and rewrite the report yourself

94.

Which of the following BEST describes the relationship between standard deviation and risk?

a)
  1. Nothing

b)

Standard deviation tells you if the estimate is accurate.

c)

Standard deviation tells you how unsure the estimate is

d)

Standard deviation tells you if the estimate includes a pad

95.

What should be done with risks on the watchlist?

a)

Document them for historical use on other projects.

b)

Document them and revisit during project monitoring and controlling

c)

Document them and set them aside because they are already covered in your contigency plans.

d)
  1. Document them and give them to the customer.


96.

A manager has responsibility for a project that has the support of a senior manager. From the beginning, you have disagreed with the manager as to how the project should proceed and what the deliverables should be. You and she have disagreed over many issues in the past. Your department has been tasked with providing some key work packages for the project. What should you do?

a)
  1. Provide the manager with what she needs.

b)
  1. Inform your manager of your concerns to get her support

c)
  1. Sit down with the manager at the beginning of the project and attempt to describe why you object to the project, and discover a way to solve the problem.

d)
  1. Ask to be removed from the project

97.

The float of an activity is determined by:

a)
  1. Perform a Monte Carlo analysis.

b)
  1. Determining the waiting time between activities.

c)
  1. Determining lag.

d)
  1. Determining the amount of time the activity can be delayed before it delays the critical path.

98.

All of the following are ALWAYS inputs to the risk management process EXCEPT

a)

Historical information

b)

Lesson learned

c)

WBS

d)
  1. Project status report.

99.

A large, complex construction project in a foreign country requires coordination to move the required equipment through crowded city streets. To ensure the equipment is transported successfully, your contact in that country informs you that you will have to pay the local police a fee for coordinating traffic. What should you do?

a)

Do not pay the fee because it is a bribe

b)

Eliminate the work

c)

Pay the fee

d)

Do not pay the fee if it is not part of the project estimate

100.

Human resource management includes ____ processes.

a)
  1. 3

b)

4

c)
  1. 5

d)
  1. 6