1.

Tom is a Servant leader of a complex software development project that is running using Agile development approach. Two developers are having difference in opinion about the technical approach of a user story. What needs to be done in this situation?

a)

A. Tom should assess the level of conflict and intervene appropriately

b)

B. Consult with product owner

c)

C. Entire team should gather to discuss the issue and produce a collective solution

d)

D. Tom should ask for further clarifications from both the developers

2.

Which of the following is not an example of the four values of the Agile Manifesto?

a)

A. Individuals and interactions over processes and tools

b)

B. Working software is the primary measure of progress

c)

C. Responding to change over following a plan

d)

D. Customer collaboration over contract negotiation

3.

An agile practitioner is explaining the Agile Manifesto to some end users in advance of a new project. Which of the following would the agile practitioner say is preferred in an agile project?

a)

A. Collaborating with customers

b)

B. Following a process and using the right tools

c)

C. Following a detailed project plan

d)

D. Creating extensive documentation for the system

4.

The ongoing sprint for a software development project that is being executed by following Agile - Scrum development approach needs to be cancelled as the sprint goal has become obsolete due to a sudden change in law associated to IT security. Who has authority to cancel the sprint ?

a)

A. Project Manager

b)

B. Sponsor

c)

C. Product Owner

d)

D. Scrum Master

5.

Agile project management and product development uses several different types of documents specific to each iteration, which are referred to as "artifacts". All of the following are Agile iteration artifacts except:  

a)

A. Iteration Vision Statement

b)

B. Iteration Backlog 

c)

C. Iteration Plan

d)

D. Iteration Burnup Chart 

6.

Tom is the newly appointed Project Manager of a software development project which has high degree of uncertainties and scope is not yet fully defined. Considering all the factors, he decides to adopt Agile development approach for running the project. Now, he has to come up with an initial cost estimate before the project work begins. What can be the best approach for the preparation of initial cost estimate as per the stated scenario?

a)

A. Using bottom up estimation technique to produce a detailed cost estimate

b)

B. Using Analogous estimation technique to produce a high-level cost estimate

c)

C. Doing reserve and technical performance analysis to come up with an initial cost estimate

d)

D. Using light weight estimation methods to generate a high-level cost forecast

7.

Your project is the part of a program whose goal is to improve communication system in the organization, Your project is in at Phase gate review, when one of the stakeholder highlighted that he is not receiving update, what would you do next?

a)

A. Share stakeholder register with him

b)

B. Update the lesson learned register

c)

C. Check communication plan

d)

D. Update issue log

8.

Your team member is not performing well for the past two months as a result project is lacking behind because of one team member. You went to him and talk to him. You shared that 3 of his family members are suffering from COVID. You gave him a week off to take care of his, family. Which skills you have used to come to this decision?

a)

A. Leadership skills

b)

B. Emotional intelligence

c)

C. Communication skills

d)

D. Influencing skills

9.

Which of the cost in quality is considered as outside cost?

a)

A. Training cost

b)

B. Testing cost

c)

C. Appraisal cost

d)

D. Warranty cost

10.

You are working on Project as a Project Manager, You are emphasizing it will be better to deliver value incrementally as compared to one go. Why you are doing that?

a)

A. You can earn more when value is delivered incrementally

b)

B. There will be less risk when delivering value in one go

c)

C. Both clients and vendors can go home early

d)

D. Value can be realized early on by delivering value incrementally

11.

The CEO project was deeply involved at the start of the project as this was one of the riskiest projects, now he has requested the Sponsor only to involve him in phase review meetings as he will be busy with upcoming projects. What document/ plan should the project manager update to reflect this?

a)

A. Stakeholder register

b)

B. Communication management plan

c)

C. Resource Management Plan

d)

D. Issue log

12.

You are the project manager of large R&D company, you are in planning procurement and shortlisting sellers, one of the steering committee members has asked you to select a seller, upon investigation you find that seller recommended by steering committee member is a good seller and meet all the the requirement but he is brother of steering committee member, what will the project manager do?

a)

A. Report unethical activity by steering committee member

b)

B. Report conflict of interest to sponsor

c)

C. Hire the seller

d)

D. Reject the seller since he does not meet selection criteria

13.

You are Project manager of an IT company, working on new technology with diverse audience, what is the first thing to do when you are working with diverse audience? 

a)

A. All of them must speak same language

b)

B. Diversity training

c)

C. Ground rules

d)

D. Identify training needs

14.

An unidentified risk has occurred what will the project manger do first?

a)

A. Update issue log

b)

B. Update risk register

c)

C. Implement agreed risk response

d)

D. Use Contingency reserve

15.

You are the project manager of multi year construction project, team members and stakeholder have been arguing for few weeks regarding a deliverable, You were unable to attend because of other issues in this project, however, now this has become top priority otherwise you can face delay of many critical deliverables. You listened to both parties, discussed with them and find a solution that both parties must give up something and agree on overall solution, Which conflict management technique you have used here?

a)

A. Problem solving

b)

B. Compromise

c)

C. Smooth

d)

D. Avoid

16.

On a project you are managing, you have been unable to obtain landlord approvals to install cable at various retail locations. You just learned about a project undertaken by your organization in the past that faced similar issues. If you had been aware of them during project planning, you could have taken proactive steps to avoid or mitigate the problems on your project. What might have been done differently to incorporate the knowledge gained from the previous project into your project?

a)

A.Development of more comprehensive risk response plans 

b)

B.Better communication between project managers within the company

c)

C.Improved utilization of the organizational knowledge base

d)

D.Utilization of a lessons learned register for your project

17.

All work planned to produce the deliverables of your project is now complete, and you begin to finalize activities for the project. What should you do next?

a)

A.Release the project team 

b)

B.Close contracts with vendors

c)

C.Hand over the final product

d)

D.Update the project charter