Which of the following is not a characteristic of a project?
Constrained by limited resources
Planned, executed, and controlled
Creates a unique product or service
Can be ongoing and repetitive
Industry standards and regulations are considered _________.
Important
Enterprise Environmental Factors that could impact the project
Part of the sponsor's responsibilities
Part of the lessons learned from previous projects
Industry standards and regulations are considered _________.
Important
Enterprise Environmental Factors that could impact the project
Part of the sponsor's responsibilities
Part of the lessons learned from previous projects
According to the PMBOK Guide (Sixth Edition), which of the following is not a part of the Executing Process Group?
Acquire resources
Develop team
Manage communications
Determine budget
According to the PMBOK Guide (Sixth Edition), which of the following is not a part of the Executing Process Group?
Acquire resources
Develop team
Manage communications
Determine budget
You are a working for an organization that has given you total responsibility and authority over resources, budget and timelines. You are most likely working in which type of organization?
Strong Matrix
Projectized
Functional
Functional Matrix
What is Project Management?
It has a definite start date and end date
A temporary endeavor undertaken to create a unique product, service, or result
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements
Projects are often utilized as a means of achieving an organization's strategic plan
Of the following, which one is not part of Project Integration Management?
Development of the project management plan
Interaction between project teams
Executing the project management plan
Approving changes to the project plan