How are Engineering Workflows initiated in Windchill?
Change Request
Change Notice
Problem Report
Change Report
Which of the following would be an example of a good problem report?
Part ABC123 did not fit in the enclosure. See markup for corrections that need to be made.
Initial release for Part ABC123.
Need to fix part ABC123.
Add 4 rivets.
Which of the following is autogenerated once a Problem Report is approved and a Project Manager is assigned.
Change Record
P1 Task
Change Request
Change Task
When are documents sent to SAP?
When the P1 task is completed.
When the P3 task is completed.
When the CT16 is completed.
When the CN28 is completed.
When are parts/BOMs sent to SAP?
When the CT1 is completed.
When the CN28 is completed.
When the P34 is completed.
When the P3 is completed.
After this task is completed, no part or document changes can be made.
CT1
P1
P3
P4
Why is it important to use excellent descriptions for Problem Reports and/or Change Notices?
Downstream buyers need to understand what is happening with the change.
The Context Owner needs to fully understand the issue before approving the Problem Report.
Good descriptions help MEs and other plant individuals complete their jobs.
It helps Field Services know what changes affect their products in the field.
What is the purpose of the P3 task?
To review an initial release or changes made to a part or BOM.
Windchill requires it to release a part.
It is a rework task.
To design or modify parts or BOMs.
Which of the following would be a correct order for completing tasks?
CN28, CT1, CT16, P1, P3
P1, P3, CN28, CT1, CT16
CT1, CT16, CN28
P1, P3, CT1, CT16, CN28
Which Windchill Number is placed on the drawing?
PR number
CN number
CR number
CT number