Approximately what percentage of the world’s gross product is spent on projects?
A. 10 percent
B. 25 percent
C. 50 percent
D. 75 percent
Which of the following is not a potential advantage of using good project management?
A. Shorter development times
B. Higher worker morale
C. Lower cost of capital
D. Higher profit margins
A ________ is a temporary endeavor undertaken to create a unique product, service, or result.
A. program
B. process
C. project
D. portfolio
Which of the following is not an attribute of a project?
A. projects are unique
B. projects are developed using progressive elaboration
C. projects have a primary customer or sponsor
D. projects involve little uncertainty
Which of the following is not part of the triple constraint of project management?
A. meeting scope goals
B. meeting time goals
C. meeting communications goals
D. meeting cost goals
______ is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
A. Project management
B. Program management
C. Project portfolio management
D. Requirements management
Project portfolio management addresses ______ goals of an organization, while project management addresses _______ goals.
A. strategic, tactical
B. tactical, strategic
C. internal, external
D. external, internal
Several application development projects done for the same functional group might best be managed as part of a _______
A. portfolio
B. program
C. investment
D. collaborative
Which of the following is not true?
A. Most American companies have a project management office.
B. You can earn an advanced degree in project management from hundreds of colleges and universities.
C. Employers are looking for project management skills in new graduates
D. IT hiring managers reported that project management certification did not affect starting pay.
What is the name of one of the popular certifications provided by the Project Management Institute?
A. Certified Project Manager (CPM)
B. Project Management Professional (PMP)
C. Project Management Expert (PME)
D. Project Management Mentor (PMM)
What Is Project?
A) A combination of unrelated activities with defined objectives
B) A combination of interrelated activities with defined objectives
C) A combination of interrelated activities with vague objectives
D) A combination of unrelated activities with vague objectives
How can project management be broadly defined?
A) Starting an activity with unlimited resources and time to achieve goals.
B) Starting an activity to achieve stated goals without any budget constraints.
C) Starting an activity to achieve stated goals using limited resources, budget, and time.
D) Starting an activity without defined goals, resources, budget, or time.
How can projects be defined?
A) Projects have no specified time frame and purpose.
B) Projects have a clear beginning but no specified time frame.
C) Projects have both a beginning and an end within a specified time frame and a purpose.
D) Projects have an end but no specified beginning or time frame.
How many categories of software projects are there?
A) Three categories
B) Four categories
C) Five categories
D) Six categories
What are the categories of software projects mentioned?
A) Research-based, Development, Evaluation, Industrial, Troubleshooting
B) Research-based, Development, Analysis, Industry-based, Problem-solving
C) Research-based, Development, Evaluation, Industry-based, Problem-solving
D) Research-based, Development, Validation, Industry-based, Problem-solving
What is the definition of a software development project?
A) Implementing source code without customer requirements
B) Creating software design without considering customer requirements
C) Making software design based on customer requirements and implementing it into source code
What is a primary goal of software project management?
A) Developing a software product without considering cost and time
B) Maintaining a software product with no consideration for project management principles
C) Delivering a software project with maximum cost, time, and product quality
D) Delivering a software project at minimum cost, within minimum time, and with good product quality
How can a process be defined?
A) A random sequence of actions
B) A predefined way of doing things, often broken down into a series of steps
C) A dynamic and constantly changing method
D) An abstract concept with no relation to tasks
How do project management processes and software engineering processes differ?
A) Project management processes focus on initiation and closure, while software engineering processes focus on planning and monitoring.
B) Project management processes define structure, steps, and procedures for software development, while software engineering processes focus on project initiation.
C) Project management processes are not related to software development, while software engineering processes focus on project closure.
D) Project management processes focus on project initiation, planning, monitoring, control, and closure, while software engineering processes define structure, steps, and procedures for various tasks in software development.
What are the advantages of structuring software development into a defined process model?
A) It makes the problem more complex, improving time estimates and progress visibility.
B) It lacks a structured approach, making it difficult to understand tasks at each stage.
C) It provides structure, improves time estimates, sharpens focus, and leads to better coding and documentation.
D) It does not improve time estimates and progress visibility, and it lacks structure.
What are the stages included in the Software Development Life-Cycle (SDLC)?
A) Design, analysis, development, testing, and implementation
B) Requirements analysis, design, development, testing, and implementation
C) Analysis, design, testing, implementation, and maintenance
D) Design, development, testing, and maintenance
What differentiates the Waterfall model from the stage-wise model?
A) The Waterfall model allows for some iteration between stages, whereas the stage-wise model follows a strictly sequential, unidirectional process.
B) The Waterfall model does not have fixed baselines, while the stage-wise model follows a fixed baseline approach.
C) The Waterfall model was developed after the stage-wise model, incorporating its limitations, while the stage-wise model was developed to address the problems of the Waterfall model.
D) The Waterfall model has a more flexible approach to addressing user needs, while the stage-wise model is rigid in addressing user requirements.
How does the Incremental Model approach the delivery of software to the client compared to conventional models?
A) The Incremental Model delivers the entire system to the client at the end of the project, whereas conventional models deliver it in a series of releases.
B) The Incremental Model delivers the system to the client in a series of intermediate working subsystems over time, gradually adding more functionality with each release.
C) The Incremental Model does not deliver the system to the client until all functionality is fully developed, unlike conventional models which release partial functionality.
D) The Incremental Model delivers the system to the client with all functionality in the first release, similar to conventional models.
When is the use of a prototype beneficial in a software development project?
A) A prototype is beneficial when all requirements of the system are clear at the start of the project.
B) A prototype is beneficial when exploring the technical feasibility of the system is unnecessary.
C) A prototype is beneficial when there is a clear understanding of the technical issues surrounding the system.
D) A prototype is beneficial when exploring requirements, concepts, or technical feasibility of the system is needed.
What are the two options you have with a prototype once it is developed?
A) You can discard the prototype and begin the system development from scratch (throw-away prototyping), or you can evolve the prototype into the final system (evolutionary prototyping).
B) You can keep the prototype as a backup and start the system development from scratch (backup prototyping), or you can evolve the prototype into the final system (evolutionary prototyping).
C) You can discard the prototype and start the system development from scratch (restart prototyping), or you can evolve the prototype into a different system (adaptive prototyping)
D) You can evolve the prototype into the final system (evolutionary prototyping), or you can develop the prototype further without making it the final system (iterative prototyping).
What is a key characteristic that differentiates Agile methods from older software development approaches?
A) Agile methods involve large development teams working in separate offices.
B) Agile methods prioritize face-to-face communication with users based in different working environments.
C) Agile methods emphasize delivering software systems in long, continuous development cycles.
D) Agile methods have smaller development teams working together in open plan offices and prioritize face-to-face communication with users often in the same working environment.
What are some key principles of Agile methods?
A) Working towards detailed documentation rather than face-to-face conversations.
B) Satisfying the customer through delayed delivery of valuable software.
C) Teams reflecting on their progress irregularly.
D) Welcoming changing requirements and valuing face-to-face conversations as a measure of progress.
Accountants usually define _________________ as a resource sacrificed or foregone to achieve a specific objective or something given up in exchange.
a. money
b. liability
c. trade
d. cost
What is the main goal of project cost management ?
a. to complete a project for as little cost as possible
b. to complete a project within an approved budget
c. to provide truthful and accurate cost information on projects
d. to ensure that an organization’s money is used wisely
Which of the following is not an output of estimating costs ?
a. activity cost estimates
b. a cost baseline
c. basis of estimates
d. project documents updates
If a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product ?
a. -5%
b. 5%
c. -$5
d. $5
_________________ reserves allow for future situations that are unpredictable.
a. Contingency
b. Financial
c. Management
d. Baseline
You are preparing a cost estimate for a building based on its location, purpose, number of square feet, and other characteristics. What cost-estimating technique are you using ?
a. parametric
b. analogous
c. bottom-up
d. top-down
_________________ involves allocating the project cost estimate to individual material resources or work items over time.
a. Reserve analysis
b. Life cycle costing
c. Project cost budgeting
d. Earned value analysis
__________________ is a project performance measurement technique that integrates scope, time, and cost data.
a. Reserve analysis
b. Life cycle costing
c. Project cost budgeting
d. Earned value management
If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what is its cost variance, and is it under or over budget ?
a. The cost variance is -$500, which is over budget.
b. The cost variance is -$500, which is under budget.
c. The cost variance is $500, which is over budget.
d. The cost variance is $500, which is under budget.
If a project is halfway completed, its schedule performance index is 110%, and its cost performance index is 95%, how is it progressing ?
a. It is ahead of schedule and under budget
b. It is ahead of schedule and over budget.
c. It is behind schedule and under budget.
d. It is behind schedule and over budget.
What is a common reason for cost overruns in software projects?
A) Emphasizing the importance of realistic project cost estimates from the beginning.
B) Low original cost estimates based on clear project requirements.
C) Delegating cost estimation to accountants rather than project managers.
D) Involvement of new technology or business processes with untested products and inherent risks.
How are costs typically measured?
A) In units of resources sacrificed or foregone.
B) In non-monetary units such as time and effort.
C) In monetary units like dollars.
D) In terms of the specific objective achieved.
What is a primary objective of Project Cost Management?
A) Ensuring that the project is completed within an approved timeline.
B) Making sure the project has accurate time and cost estimates.
C) Ensuring that the project is completed without any changes to the budget
D) Ensuring that the project is completed within an approved budget.
What is the difference between tangible costs or benefits and intangible costs or benefits in cost management?
A) Tangible costs or benefits are difficult to measure in monetary terms, while intangible costs or benefits can be easily measured in dollars.
B) Tangible costs or benefits are costs or benefits that an organization can easily measure in dollars, while intangible costs or benefits are difficult to measure in monetary terms.
C) Tangible costs or benefits are directly related to producing products and services, while intangible costs or benefits are indirectly related to performing the project.
What is the purpose of contingency reserves and management reserves in project cost management?
A) Contingency reserves are included to mitigate cost risk by allowing for future unpredictable situations, while management reserves are planned to cover known risks.
B) Contingency reserves are planned to cover known risks, while management reserves are included to mitigate cost risk by allowing for future unpredictable situations.
C) Both contingency reserves and management reserves are included to cover unplanned costs that may arise during the project.
What is life cycle costing in project cost management?
A) Life cycle costing is estimating the cost of a project plus the initial investment in products it produces.
B) Life cycle costing is estimating the total cost of a project, including the initial investment and maintenance costs of the products it produces.
C) Life cycle costing is estimating the cost of a project plus the additional costs incurred during the maintenance phase.
What are direct costs in the context of cost management?
A) Costs that can be directly related to producing the products and services of the project.
B) Costs that are indirectly related to performing the project.
C) Costs that are difficult to measure in monetary terms.
How do profits relate to revenues and expenses in cost management
A) Profits are revenues plus expenses.
B) Profits are revenues minus expenses.
C) Profits are equal to revenues only.
What is the purpose of reserves in project cost management?
A) Reserves are included to increase the project budget.
B) Reserves are included to ensure that all costs are known in advance.
C) Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future unpredictable situations.
How do management reserves differ from contingency reserves in project cost management?
A) Contingency reserves cover known risks, while management reserves cover unknown risks.
B) Contingency reserves are planned for known risks, while management reserves are for unplanned and unpredictable situations.
C) Contingency reserves are part of the project cost baseline, while management reserves are not accounted for in the project budget.
What does "life cycle costing" involve in project cost management?
A) Estimating the cost of a project plus the initial investment in products it produces.
B) Estimating the total cost of a project, including the initial investment and maintenance costs of the products it produces.
C) Estimating the cost of a project plus any unexpected expenses that may arise.
Define "indirect costs" in project cost management.
A) Costs that are directly related to producing the products and services of the project.
B) Costs that are not related to the products or services of the project, but are indirectly related to performing the project.
C) Costs that are difficult to measure in monetary terms.
What does "sunk cost" refer to in project cost management?
A) Money that has been spent in the past and should not be considered in future budgeting decisions.
B) Money that is allocated for unforeseen project expenses.
C) Money that is set aside for future project investments.
You have purchased a ticket for a movie that you were excited to see. Upon arriving at the cinema, you realize that the reviews for the movie are overwhelmingly negative, and you are having second thoughts about watching it. What is the best course of action regarding the sunk cost of the ticket?
A) Go ahead and watch the movie to not waste the money spent on the ticket.
B) Leave the cinema and consider the ticket cost as a sunk cost, making a decision based on whether you truly want to watch the movie.
C) Sell the ticket to someone else and recover at least a portion of the spent money.
D) Buy another ticket for a different movie to make the most of the trip to the cinema.
What is a crucial output of project cost management?
A) A resource requirements list
B) Project timelines
C) A cost estimate
D) Risk assessment report
Which cost estimation technique involves estimating costs based on historical data from similar projects?
A) Analogous or top-down estimates
B) Bottom-up estimates or Activity Based Costing
C) Parametric modeling
D) Three Point Estimates
Which cost estimation technique involves breaking down the project into smaller activities and estimating the costs for each activity?
A) Analogous or top-down estimates
B) Bottom-up estimates or Activity Based Costing
C) Parametric modeling
D) Three Point Estimates
Which cost estimation technique uses statistical relationships between historical data and other variables to estimate project costs?
A) Analogous or top-down estimates
B) Bottom-up estimates or Activity Based Costing
C) Parametric modeling
D) Three Point Estimates
In Three Point Estimates, what are the three values used to estimate the cost of an activity or task?
A) Best case, worst case, and most likely case
B) Average case, pessimistic case, and optimistic case
C) Initial estimate, revised estimate, and final estimate
D) Base case, upper case, and lower case
Which tool is focused on providing a time-phased budget during cost planning?
A) Cost-planning map
B) Cost baseline
C) Cost estimation model
D) Cost tracking sheet
What is the unique purpose of the cost-planning map in cost planning?
A) Establishing a time-phased budget
B) Providing a systematic methodology for cost planning
C) Combining cost estimation models
D) Tracking costs throughout the project
What is the primary purpose of a cost management plan in project management?
A) Tracking project schedule
B) Managing cost variances
C) Allocating resources
D) Documenting project objectives
Which cost component is a significant portion of total project costs, particularly in software projects?
A) Labor costs
B) Equipment costs
C) Material costs
D) Overhead costs
What is a critical input required for the cost budgeting process?
A) Project schedule
B) Project objectives
C) Work Breakdown Structure (WBS)
D) Risk assessment report
What is a key outcome of the cost budgeting process?
A) Allocation of project objectives
B) Development of project schedule
C) Provision of a cost baseline
D) Identification of project risks
What does Earned Value Management (EVM) integrate to measure project performance?
A) Risk management, time, and cost data
B) Scope, time, and cost data
C) Resource allocation, time, and cost data
D) Quality management, time, and cost data
What does the Rate of Performance (RP) measure in Earned Value Management (EVM)?
A) The ratio of actual work completed to the percentage of work planned to have been completed at a given time
B) The ratio of earned value to actual cost
C) The ratio of planned value to earned value
D) The ratio of planned value to actual cost
Which term in Earned Value Management (EVM) represents an estimate of the value of the physical work actually completed?
A) Actual cost (AC)
B) Earned value (EV)
C) Planned value (PV)
D) Rate of performance (RP)
Which term in Earned Value Management (EVM) is also known as the budget and represents the portion of the approved total cost estimate planned to be spent on an activity during a given period?
A) Actual cost (AC)
B) Earned value (EV)
C) Planned value (PV)
D) Rate of performance (RP)
What does Actual Cost (AC) represent in Earned Value Management (EVM)?
A) The ratio of earned value to actual cost
B) The total of direct and indirect costs incurred in accomplishing work on an activity during a given period
C) An estimate of the value of the physical work actually completed
D) The ratio of actual work completed to the percentage of work planned to have been completed at a given time
Which term in Earned Value Management (EVM) is the ratio of actual work completed to the percentage of work planned to have been completed at a given time?
A) Actual cost (AC)
B) Earned value (EV)
C) Planned value (PV)
D) Rate of performance (RP)
________________ formerly called the budgeted cost of work scheduled, also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period.
a. Planned value (PV)
b. Actual cost (AC)
c. Earned value (EV)
d. Cost baseline
. _________________formerly called actual cost of work performed, is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period.
a. Planned value (PV)
b. Actual cost (AC)
c. Earned value (EV)
d. Cost estimates
_________________formerly called the budgeted cost of work performed, is an estimate of the value of the physical work actually completed.
a. Planned value (PV)
b. Actual cost (AC)
c. Earned value (EV)
d. Basis of estimates
In a project, if the actual cost value is $2000 and its earned value is $4,000. what is its cost performance index?
a. 2
b. 1/2
c. $2000
d. -$2000
In a project, if the planned value is $5000 and its earned value is $1,000. what is its schedule performance index?
a. 5
b. 1/5
c. $4000
d. -$4000
In a project, if the planned value is $5000 and its earned value is $1,000. what is its schedule performance index?
a. $2000
b. -$2000
c. $3000
d. $1000
_________________ can be used to estimate the projected time to complete the project.
a. Cost performance index
b. Schedule performance index
c. Project cost budgeting
d. Earned value management
__________________ can be used to estimate the project cost of completing the project based on performance.
a. Cost performance index
b. Schedule performance index
c. Project cost budgeting
d. Earned value management
If the actual cost for a WBS item is $3000 and its earned value is $2,000, what is its cost variance, and is it under or over budget?
a. The cost variance is -$1000, which is over budget.
b. The cost variance is -$1000, which is under budget.
c. The cost variance is $1000, which is over budget.
d. The cost variance is $1000, which is under budget.
If a project is halfway completed, its schedule performance index is 90%, and its cost performance index is 50%, how is it progressing?
a. It is ahead of schedule and under budget.
b. It is ahead of schedule and over budget.
c. It is behind schedule and under budget.
d. It is behind schedule and over budget.
How is project planning defined in the context of a software project?
A) Planning involves making trade-offs among quality, schedule, cost, and organization benefits for successful project execution.
B) Planning focuses on executing a predefined project with minimal adjustments in a specific environment.
C) Planning primarily focuses on quality assurance and cost estimation for project success.
D) Planning involves the accurate prediction of resources needed for executing a project.
What does project planning aim to achieve in the context of software projects?
A) Achieving the project objectives without considering trade-offs
B) Allocating an unlimited budget to meet all project requirements
C) Making intelligent estimates of required resources to achieve project success
D) Focusing solely on cost control throughout the project lifecycle
Which of the following is a component of project planning related to managing uncertainties and potential issues in a project?
A) Resource planning
B) Task planning
C) Risk planning
D) Cost estimation
What component of project planning involves determining the monetary resources required for executing the project?
A) Effort estimation
B) Cost estimation
C) Task planning
D) Quality planning
In the context of software development, which type of project planning is typically associated with custom software development?
A) Top-down project planning
B) Bottom-up project planning
C) Both top-down and bottom-up project planning
D) Neither top-down nor bottom-up project planning
What are the key inputs for planning a top-down project?
A) Project scope, chosen software engineering model, and requirements
B) Project start date, project end date, and project duration
C) Project budget, defect prevention strategy, and WBS structure
D) Resource allocation, tool management, and risk management
What are some plan outputs of a top-down project plan?
A) Resource allocation, communication management, and defect prevention strategy
B) Configuration management, WBS structure, and effort estimate
C) Project start date, project end date, and project duration
D) Project budget, tool management, and risk management
When is a bottom-up project planning approach typically used in software projects?
A) When the project has a clear and well-defined scope from the beginning
B) When the project is large and lacks clarity at the outset
C) When the project requires rapid development
D) When the project involves a limited number of stakeholders
What are the primary inputs for project planning in a bottom-up approach?
A) Project scope, SLAs, and software requirements
B) Project start date, project end date, and project duration
C) Project budget, risk assessment, and tool management
D) Resource allocation, communication management, and defect prevention strategy
What is a key characteristic of software projects that make the bottom-up approach particularly suitable for project planning?
A) Well-defined project scope from the beginning
B) Rapid development and deployment requirements
C) Limited project budget and resources
D) Clear and structured communication among team members
In a bottom-up project plan, what are some of the project plan outputs that are generated?
A) Project budget, work breakdown structure (WBS), and project start date
B) Supplier management, communication management, and defect prevention strategy
C) Project duration, project cost, and resource allocation
D) Project end date, tool management, and risk management
Which step in the project planning process involves breaking down the project into smaller, manageable tasks?
A) Work breakdown
B) Time estimates
C) Milestone identification
D) Re-planning
Which project planning step involves determining the start and end times for each task or activity?
A) Activity sequencing (Activity networks)
B) Scheduling (Gantt chart)
C) Time estimates
D) Re-planning
What is the purpose of "Milestone identification" in the project planning process?
A) To determine the start and end times for each task
B) To break down the project into smaller, manageable tasks
C) To identify significant events or achievements in the project timeline
D) To sequence the activities in a project
What is the purpose of "Re-planning" in the project planning process?
A) To determine the start and end times for each task
B) To break down the project into smaller, manageable tasks
C) To adjust the project plan based on changes or new information
D) To sequence the activities in a project
In the project planning process, what is the purpose of "Activity Sequencing (Activity Networks)"?
A) To determine the start and end times for each task
B) To break down the project into smaller, manageable tasks
C) To sequence the activities based on their dependencies and relationships
D) To identify significant milestones in the project timeline
What is the purpose of "Time Estimates" in the project planning process?
A) To determine the start and end times for each task
B) To break down the project into smaller, manageable tasks
C) To provide an estimate of the time required to complete each activity or task
D) To identify significant milestones in the project timeline
What is the first step in creating a Work Breakdown Structure (WBS)?
A) Breaking the project down into its main objectives
B) Identifying the project's main areas of activity
C) Breaking down the project into lower levels of detail
D) Identifying the project's milestones
What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?
A) To estimate project costs accurately
B) To identify the critical path of the project
C) To break the project down into manageable work packages
D) To allocate resources efficiently
In project planning, how does breaking down the project into tasks aid in time estimation?
A) It allows for a more accurate prediction of the overall project duration
B) It helps identify the critical path of the project
C) It allows for a more accurate prediction of the project's budget
D) It helps in resource allocation
Why is it important to focus on the lowest level of the Work Breakdown Structure (WBS) when making time estimates?
A) To accurately predict project costs
B) To identify the critical path of the project
C) To make reasonably accurate predictions of the effort needed for each activity
D) To allocate resources efficiently
What is the primary purpose of identifying milestones in a project?
A) To measure project budget accurately
B) To provide intermediate reference points and gauge project progress
C) To identify the critical path of the project
D) To allocate resources efficiently
How should you identify milestones in a project?
A) By focusing on the lowest level of the WBS
B) By identifying any tasks that require extra attention
C) By focusing on the top level of the WBS and key stages representing significant progress
D) By identifying all the tasks in the project
In what way do milestones contribute to effective project management?
A) By determining the critical path of the project
B) By providing a basis for allocating resources
C) By facilitating the tracking of project progress and achievements
D) By generating project reports and documentation
How can milestones be utilized in project planning?
A) As a tool for breaking down the project into manageable tasks
B) As intermediate goals to aim for during the project
C) As a method for resource allocation
D) As a tool for risk assessment
Why is it recommended to use some or all of the project’s objectives as milestones?
A) To simplify project documentation
B) To align milestones with project tasks
C) To provide a clear link between milestones and project goals
D) To reduce the number of milestones
What can milestones be associated with in a project?
A) Allocation of resources
B) Task prioritization
C) Production of reports, documents, or subsystems
D) Risk management
What is the main purpose of activity sequencing in project planning?
A) To identify project milestones
B) To determine the start and end dates of each task
C) To establish the order in which tasks should be performed
D) To allocate resources effectively
What does the critical path in a project network represent?
A) The shortest route through the project network
B) The sequence of tasks that must not be delayed
C) The order in which activities are performed
D) The path with the most number of milestones
In Activity-on-the-Node diagrams, what do arrows represent?
A) The start dates of activities
B) The end dates of activities
C) The order in which activities must be performed
D) The critical path of the project
How is the critical path identified in the project network using the Critical Path Method (CPM)?
A) It is the path that involves the least number of tasks
B) It is the longest route through the project network
C) It is the path that includes all the milestones
D) It is the path with the highest number of dependencies
What is the primary advantage of using Gantt charts in project management?
A) Showing task relationships and dependencies
B) Explicitly representing activity durations and simultaneous tasks
C) Identifying the critical path of the project
D) Allowing for resource allocation and balancing
How are activities represented in Gantt charts?
A) As rectangles or nodes
B) As diamonds
C) As arrows
D) As circles
What does the size or length of an activity's node in a Gantt chart represent?
A) The task's priority
B) The task's complexity
C) The task's duration
D) The task's relationship to other tasks
In what way do project management software packages assist in scheduling?
A) By identifying the critical path of the project
B) By explicitly showing task relationships and dependencies
C) By attempting to achieve a balanced allocation of work over the project's duration
D) By providing a diagrammatical representation of the project
What does "re-planning" involve in project management?
A) Creating initial project plans
B) Going back through plans and making adjustments and rescheduling
C) Identifying milestones and critical paths
D) Allocating resources to tasks
Why are project management software tools particularly useful for re-planning?
A) To create initial project plans
B) To identify milestones and critical paths
C) To allocate resources to tasks
D) To make changes and assess the impact of adjustments in the plans
What is the main characteristic of rolling wave planning?
A) Detailed planning at project inception
B) Constructing a skeleton plan with key stages
C) Identifying project milestones before planning
D) Planning details that remain static throughout the project
In rolling wave planning, how is project planning performed?
A) 'On the fly' as the project progresses
B) In a detailed and comprehensive manner at the beginning
C) With a fixed and unchanging plan from start to finish
D) By pre-determining all tasks and milestones in advance
What is a significant benefit of using rolling wave planning?
A) Providing detailed project plans at the beginning
B) Adhering to a fixed project plan throughout the project
C) Allowing for flexibility and adaptation as the project progresses
D) Identifying all project milestones in advance
What is the primary purpose of a Project Initiation Document (PID)?
A) To outline project risks and issues
B) To define the project's purpose, objectives, plan, and risks
C) To provide a detailed breakdown of project tasks
D) To track project progress and milestones
What fundamental questions does a Project Initiation Document (PID) aim to answer about the proposed project?
A) When will the project be undertaken, and who will be involved?
B) How will the project be undertaken, and what are the expected outcomes?
C) What is the project aiming to achieve, why is it important, who will be involved, and how and when will the project be undertaken?
D) Why is the project important, and who will be involved?
In project management, what does a Project Initiation Document (PID) represent?
A) A detailed breakdown of project tasks
B) A definitive overview of the project, including its purpose, objectives, plan, and risks
C) A tool for tracking project expenses
D) A contract between stakeholders outlining their responsibilities
Which of the following processes involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule?
A. planning schedule management
B. defining activities
C. estimating activity resources
D. activity sequencing
Predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions are all examples of .
A. items in an activity list
B. items on a Gantt chart
C. milestone attributes
D. activity attributes
What are the different types of project planning?
A. Top – down plan
B. Top plan
C. Bottom -up plan
D. Bottom plan
You cannot start editing a technical report until someone else completes the first draft. What type of dependency does this represent?
A. finish-to-start
B. start-to-start
C. finish-to-finish
D. start-to-finish
Which technique of project planning is used to break the project down into lower levels?
A. Work breakdown.
B. Times estimates
C. Milestone identification.
D. Activity sequencing
What symbol on a Gantt chart represents a slipped milestone?
A. a black arrow
B. a white arrow
C. a black diamond
D. a white diamond
What are the techniques of project planning?
A. Work breakdown.
B. Times estimates.
C. Milestone identification.
D. Activity sequencing
E. Scheduling
F. Planning.
G. Top – down
H. Re-Planning
A, B, C, D, E, H
B, C, D, E, F, G, H, A
C, D, E, F, G, H, A, B
D, E, F, G, H, A, B, C
______ is a network diagramming technique used to predict total project duration.
A. PERT
B. A Gantt chart
C. Critical path method
D. Crashing
About CPM (Critical Path Method), which of the following statements is false?
A. This path is the shortest route through the project network
B. This path is a route through the project network.
C. Tasks with no relation among them are put in parallel.
D. This is the critical path for the project, and it defines the duration of the project.
In a project, the start date of Critical Path isn’t the start date of the project and end date of this path is the end date of the project?
A. True
B. False