1. Project Management Terms

Total questions: 54

Worksheet time: 44mins

Name
Class
Date
1.

A temporary endeavor that produces a unique product, service, or result

Temporary in nature and has a definite beginning and ending

Can be part of a large Program or Portfolio

(a)  

2.

A Project is:

a)

Unique

b)

Temporary

c)

Progressively Elaborated

d)

Finite

3.

It is the application of knowledge, skills, tools, and techniques to satisfy project requirements

(a)  

4.

These are examples of Project Management Activities:

a)

Preparing a business case to justify the investment

b)

Estimating resources and times

c)

Developing and implementing a management plan for the project

d)

Leading and motivating the project delivery team

5.

These are examples of Project Management Activities:

a)

Operative Activities

b)

Managing the risks, issues, and changes in the project

c)

Monitoring progress against plan

d)

Closing the project in a controlled fashion when appropriate

6.

Group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually



(a)  

7.

Organizational Structure that standardizes the processes and facilitates the sharing of resources, methodologies, tools, and techniques

(a)  

8.

Select the correct type of Project Management Office.

Supports the project manager, such as providing templates, training, or lessons learned from other projects.

a)

Supportive

b)

Controlling

c)

Directive

9.

Select the correct type of Project Management Office.

Determines the framework or methodology and use of specific forms

a)

Supportive

b)

Controlling

c)

Directive

10.

Select the correct type of Project Management Office.

Controls the project. The PM will be assigned and report to the PMO.

a)

Supportive

b)

Controlling

c)

Directive

11.

It is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

(a)  

12.

Deals with the ongoing production of goods and/or Services

Considers the acquisition, development, and utilization of resources that firms need to deliver the goods and services

(a)  

13.

Money, Brand Reputation, Customer Service, New or Change product or Service are all examples of the Project (a)  

14.

Takes a company from current state to desired state

(a)  

15.

It is a collection of logically related project activities that culminate in the completion of one or more deliverables.

(a)  

16.

It is any unique and verifiable product, service, or result.

(a)  

17.

It is a representation of the phases that a project typically goes through from start to finish

• Can be either predictive or adaptive

(a)  

18.

It is a framework within which project decisions are made

Three pillars:

• Structure

• People

• Information

(a)  

19.

Individuals, groups, or organizations that may affect, be affected or perceive to be affected by the project.

(a)  

20.

Select all the types of Stakeholders

a)

Project Manager

b)

Customer

c)

Project team

d)

Project Sponsor

e)

Functional Manager

21.

Select the correct Stakeholder:

Provides resources and support

a)

Project Manager

b)

Customer

c)

Project team

d)

Project Sponsor

e)

Functional Manager

22.

Select the correct Stakeholder:

Departmental Manager, i.e Manager of Engineering, Vice President of Marketing, Director of IT. Generally controls resources.

a)

Project Manager

b)

Customer

c)

Project team

d)

Project Sponsor

e)

Functional Manager

23.

Select all the Project Manager Roles

a)

Initiator

b)

Negotiator

c)

Listener

d)

Coach

e)

Punisher

24.

Select all the Project Manager Roles

a)

Finisher

b)

Facilitator

c)

Listener

d)

Coach

e)

Working Member

25.

It is a significant event or achievement in a project that marks a key point or completion of a major deliverable.

(a)  

26.

Refers to the amount of time it takes to complete a specific task or activity within a project.

(a)  

27.

Select the missing project role:

a)

Project Manager

b)

Project Coordinator

c)

Project Expeditor

28.

Select the missing project role:

a)

Project Manager

b)

Project Coordinator

c)

Project Expeditor

29.

Select the missing project role:

a)

Project Manager

b)

Project Coordinator

c)

Project Expeditor

30.

Select all the possible Organizational Structures

a)

Functional Organizations

b)

Matrix Organization

c)

Project Oriented Organizations

d)

Hybrid

31.

Select the correct Organizational Structure:

A structure that groups staff members according to their area of expertise (sales, marketing, construction, etc.).

Functional structures require the project team members to report directly to the functional manager

a)

Functional Organizations

b)

Matrix Organization

c)

Project Oriented Organizations

d)

Hybrid

32.

Select the correct Organizational Structure:

A structure where the PM has the greatest amount of authority. The project team is assigned to the project on a full-time basis. When the project is complete, the project team members move on to other assignments within the organization.

a)

Functional Organizations

b)

Matrix Organization

c)

Project Oriented Organizations

d)

Hybrid

33.

Select the correct Organizational Structure:

There are three ______ structures: weak, balanced, and strong. The different structures are reflective of the project manager's authority in relation to the functional manager's authority.

a)

Functional Organizations

b)

Matrix Organization

c)

Project Oriented Organizations

d)

Hybrid

34.

Select the correct Project Boss based on its characteristics:

• Internal or External

• Project Champion

• Funding the project

• Maybe used to resolve conflicts in the project

a)

Sponsor

b)

Program Manager

c)

Product Owner

35.

Select the correct Project Boss based on its characteristics:

• Senior to Project Manager

• Maybe responsible for several projects executing at the same time

• Maybe used to resolve conflicts in the project

a)

Sponsor

b)

Program Manager

c)

Product Owner

36.

Select the correct Management type

• It encompasses the strategic planning, development, and lifecycle management of a product or service.

• It involves understanding the market needs, defining product strategy, gathering requirements, and overseeing the product's development, launch, and ongoing optimization.

• Product managers are responsible for the overall success of the product, aligning it with business objectives and customer demands.

a)

Product Management

b)

Project Management

c)

Portfolio Management

37.

Select the correct Management type

• Focuses on the successful execution and delivery of specific projects within a defined scope, timeline, and budget.

• Project managers are responsible for planning, coordinating, and managing the activities required to achieve project goals.

• They ensure the project is completed on time, within budget, and according to the specified quality standards.

a)

Product Management

b)

Project Management

c)

Portfolio Management

38.

You look stressed out, draw something cool here

39.

Select the correct area of a Project:

Work to be done

a)

Scope

b)

Schedule

c)

Cost

d)

Quality

40.

Select the all areas of a Project:

a)

Scope

b)

Schedule

c)

Cost

d)

Quality

e)

People

41.

Select the all areas of a Project:

a)

Resources

b)

Communications

c)

Risk

d)

Procurements

e)

Stakeholders engagement

42.

They are potential events or situations that may occur in the future and have an impact on the project's success.

a)

Issue

b)

Assumptions

c)

Risk

d)

Constraints

43.

They refer to problems or challenges that arise during the course of a project. They are typically negative events or circumstances that can hinder

a)

Issue

b)

Assumptions

c)

Risk

d)

Constraints

44.

They are statements or beliefs that are considered to be true or valid for the purpose of planning and decision-making.

a)

Issue

b)

Assumptions

c)

Risk

d)

Constraints

45.

They are limitations or restrictions that affect project planning and execution.

a)

Issue

b)

Assumptions

c)

Risk

d)

Constraints

46.

Write one Project Constraint

(a)  

47.

What are the two Project Management Approaches

a)

Predictive/Adaptive

b)

Predictive/Fixed

c)

Uncertain/Adaptive

d)

Uncertain/Fixed

48.

Select the correct Project Management Approach.

Also known as traditional or waterfall.

• Linear and sequential process.

• Detailed planning and documentation up front, with a focus on predicting and defining the project scope, objectives, timeline, and deliverables.

• Extensive upfront planning.

• Emphasis on control and documentation.

• Limited flexibility, limited changes with a well defined change control process

a)

Predictive

b)

Adaptive

49.

Select the correct Project Management Approach.

Also known as agile or iterative.

• It embraces change throughout the project and emphasizes continuous feedback and improvement.

• Iterative and incremental development

• Customer collaboration

• Emphasis on adaptability

• Self-organizing teams

• The adaptive approach, commonly used in agile methodologies like Scrum or Kanban

a)

Predictive

b)

Adaptive

50.

• It refers to the ability to recognize, understand, and manage emotions, both in oneself and in others.

• It involves being aware of one's own emotions, effectively handling them, empathizing with others, and using emotions to guide thinking and behavior.

(a)  

51.

These are all aspects of (a)   .

• Relationship Building

• Communication and Conflict Management

• Motivation and Influence

• Leadership and Decision Making

• Stakeholders Management

52.

Leadership vs. Management

• It focuses on tasks, processes, and operations to ensure efficient execution

• It involves planning, organizing, coordinating, and controlling resources

• Managers have formal authority and responsibility within the organization

• They maintain stability, control, and order, ensuring established processes and procedures are followed.

• Focus on coordinating and directing tasks, resources, and processes to achieve predetermined objectives.

a)
Management
b)

Leadership

53.

Leadership vs. Management

• Focuses on inspiring and influencing others

• Involves setting direction, motivating and empowering individuals

• They inspire and influence others

• They encourage collaboration, trust, and empowerment

a)
Leadership
b)

Management

54.

Select the correct answer:

a)

Management

b)

Leadership