WorksheetsBQS601 INTRODUCTION
Total questions: 17
Worksheet time: 10mins
Sum provided for work or services to be executed by a Nominated Sub Contractor.
The statement above is
Provisional Sum
Prime Cost Sum
Preliminaries Sum
Drain Sump
When there is Nominated Supplier, the Main Contractor may received
Profit and Attendance
Profit Only
Attendance Only
None of the above
When there is Provisional Sum, the Main Contractor may received
Profit and Attendance
Profit Only
Attendance Only
None of the above
Prime Cost sum is the money allocated for
Main Contractor
Nominated Sub Contractor
Sub Conctractor
Consultant
The Description show contract for
Provisional Sum
Preliminaries
Prime Cost Sum
The picture shows description for
Provisional Sum
Prime Cost Sum
Preliminaries Sum
Below are example of items under Preliminaries Sum EXCEPT
hoarding
site office
insurance
site transportation
fire fighting installation
Below are the THREE components of Surface Water Drainage EXCEPT
Sump
Channel
Culvert
Manhole
Based on V.5 SMM2, the below statement are true for measurement of Cascade drain EXCEPT
shall be enumerated
state the number of steps
state the total drop
state the angle of inclining
Surface water channels shall be given in
M
M2
M3
No
Construction of Sumps shall include
connection to existing drain
connection to existing sump
connection to existing manhole
Beds, benching and coverings shall each be given separately in metres stating the below EXCEPT
Nominal size of the pipe
Widths and thickness of the beds
Materials used
connection to existing drain
A Provisional Sum is primarily used when:
The work is always carried out by a nominated subcontractor
The work or cost cannot be entirely foreseen, defined or detailed at tender stage
The contractor wants additional profit
The work is always a temporary site facility
Which of the following is an example of a PC Sum according to the slide?
Site office
Hoarding install by Main Contractor
Lift installation by a nominated subcontractor
Site electricity
The unit for the Provisional Sum
m
m2
No
SUM
Which rate is identified for work that cannot be properly measured and valued?
Which rate is identified for work that cannot be properly measured and valued?
Pro-rata rate
Agreed rate
Daywork price
Classify each one as PS, PC or Preliminary based on the information givench the following
Lift installation by nominated subcontractor
PC SUM
Site office
Preliminary
Landscaping with insufficient design information
PROV SUM
Performance bond
Preliminary
Built-in furniture where details are not fully determined
PROV SUM