1.
If a project has a 60% chance of earning $100,000 and a 40% chance of losing $100,000, the expected monetary value for the project is:
a)
A. Gained $100,000
b)
B. Loss of $60,000
c)
C. Earned $20,000
d)
D. Loss of $40,000
2.
While planning your risk management, your team came up with 434 risks and 16 main causes of these risks. The project is the last in a series of projects on which the team will work together. The sponsor was highly motivated and a significant amount of time was invested to ensure the project charter was completed and signed by all key stakeholders. During the project planning phase, the team does not come up with an effective way to reduce or escape risk. It is not a job that can be outsourced or eliminated. The best solution is:
a)
Take risks
b)
Continued investigation to mitigate risks
c)
Look for ways to avoid risks
d)
Find ways to transfer the risk
3.
In which of the following contract types is the seller most involved in the scope of the project?
a)
Fixed price contract
b)
Cost plus fixed fee contract
c)
Time and materials contracts
d)
Purchase order contract
4.
During which part of the contracting process does contract negotiation take place?
a)
Purchasing plan
b)
Contract signing plan
c)
Request seller reply
d)
Select seller.
5.
A PM is creating requests for proposal (RFP). What process of purchasing management is he in?
a)
Purchasing plan
b)
Contract signing plan
c)
Request seller reply
d)
Select seller.
6.
A customer on a project tells the PM that he has run out of money to pay for the project. What should the PM do first?
a)
A. Change the work schedule to be done later than the old schedule so that customers have more capital
b)
B. Begin closing administrative activities
c)
C. Stop work
d)
D. Reducing personnel of part of the project team (release part of the team)
7.
Negotiations between the two parties are becoming complicated, so party A makes some notes that both parties sign. However, when the work was completed, Party B affirmed that they did not request the provision of an item that both parties agreed on during the negotiation process, because it was not included in the next contract. In this case, party B:
a)
Not true, because both parties must comply with what they agreed to
b)
Yes, that's why it's an offer
c)
In general, it is true, because both parties are only required to perform what is written in the contract.
d)
In general it is wrong, since all contracts must be respected
8.
You are assigned to manage a project that is halfway completed according to schedule. After an extensive review, you discover that the project is far behind schedule, and the project will likely take twice as long as the previous PM's original estimate. however, the sponsor has been told the project is on schedule. The best onions are:
a)
A. Try to restructure the schedule to meet the project deadline
b)
B. Report your assessment to the sponsor
c)
C. Transfer the project back to the old PM
d)
D. Continue working with the schedule planned by the old PM and report this at the first missed milestone.
9.
You are in the middle of a project developing a new product for a publicly traded company, and you learn that the previous PM paid $3,000,000 without approval according to company policy. Luckily, CPI=1.2. what should you do?
a)
A. Contact your manager
b)
B. Put that payment into a 3rd party account (escrow account) as evidence
c)
C. Hide this expense in the largest cost center available.
d)
D. Refuse this expense
10.
PM brings together the project team, identifies the 56 risks in the project, identifies risk triggers, ranks them in a risk level matrix, tests assumptions, and estimates the quality of the data used. The project team continues to move through the risk management process. What did PM forget to do?
a)
Risk simulation
b)
Reduces and mitigates risks
c)
Overall risk rating for the project
d)
Bring along the parties involved in the project
11.
After much excitement and hard work, the contract declared the work for the project complete. Even when there is agreement that the contract declares the work complete, the PM is still concerned about actually determining all of the buyer's requirements. PM attended the contractor conference. He asks you for advice on what to do next during the conference call. What is the best advice you can give him to help him?:
a)
You do not need to participate in the conference, the conference manager will do that
b)
Make sure you don't negotiate the scope of the project
c)
Make sure you gave the seller enough time to answer the question. They don't want to answer questions when their competitors are also present at the conference.
d)
Let the project sponsor run the conference and you will play the role of “good guy” in the conference.
12.
In the risk management process, which factor determines the transfer of a type of risk (risk made)?
a)
Identify risks
b)
Quantitative risk analysis
c)
Risk response plan
d)
Risk control
13.
During the project execution phase, an employee identifies a risk that is not on the log. What should you do?
a)
Get more information about how the employee identified the risk, since you have performed a detailed analysis and failed to identify this risk.
b)
Do not pay attention to risks, because risks have been identified during the project planning stage
c)
Inform customers about this risk
d)
Analyze this risk
14.
Which of the following actions occurs during procurement planning?
a)
Make-or-buy decision
b)
Answer seller's questions about bid documents
c)
Create terms and conditions in contracts
d)
Generate requests for proposal or bid documents
15.
A PM asks multiple stakeholders to determine the probability and impact of some risk. He then analyzed the hypotheses. He is moving to the next step of risk management. Based on the above information, what did PM FORGET to do?
a)
Trend estimation in risk analysis
b)
Identify risk triggers
c)
Provides standard risk rate matrix
d)
Create a backup plan
16.
large and complex construction project in an outsourcing company required coordination to move the required equipment across a busy street. To ensure the device is transported safely, your contacts in this country advise you to pay the local police a fee to facilitate transportation. what should you do?
a)
A. Failure to pay is therefore a bribe
b)
B. Exclusion of work
c)
C. Pay the fee
d)
D. Do not pay a fee if it is not part of the project estimate
17.
A systems development project was nearing its end date when a previously unknown risk was discovered. This has the potential to impact the project's overall ability to deliver products. What should be done next?
a)
Alert project sponsor of potential impacts to cost, scope, and schedule
b)
Quantify risks
c)
Mitigate risks by developing a risk response plan
d)
Building unplanned remediation around ongoing risks (wordaround)
18.
A major negotiation with a potential subcontractor is scheduled for tomorrow, and you discover there's a good chance the project will be postponed. What should you do?
a)
A. Don't spend much time preparing for the negotiation
b)
B. Cut down on negotiation time
c)
C. Only negotiate general items
d)
D. Postpone the negotiation
19.
The board of directors has promised you a preferential fee from customers if you complete the project early. While completing a key deliverable, your team reports that the product meets the contract requirements but does not provide the functionality the customer needs. If the product is delivered late, the project cannot be completed early. what should you do /
a)
A. Provide the deliverable as it is
b)
B. Inform the customer of the situation and find a mutually acceptable solution
c)
C. Begin compiling a list of customer-caused delays in preparation for negotiations
d)
D. Cut back on other activities in a way that will go unnoticed to provide more time to fix the deliverable
20.
You are finding that it is difficult to accurately estimate the costs that will be affected by risk. You should estimate with:
a)
Quantitative basis
b)
Arithmetic basis
c)
Qualitative basis
d)
Economic basis
21.
Which of the following would be best for the PM to do in the seller response request portion of the contract management activity?
a)
Estimate the risks
b)
Confirm that the submission has been sent.
c)
Confirm that changes to the contract have been made
d)
Answer customer questions about bidding documents
22.
project has some problems, but is still under control. By the final months of the project, most of the provisions have been used and most of the negative effects of anticipated events have occurred. There are 4 remaining activities and 2 of them are on the critical path. Management informed the PM that the company would prefer to complete the project 2 weeks earlier than scheduled to receive additional profits. In response, the PM sends out a request for proposals for some of the work the project team is about to do, hoping another company will complete the work faster. PM is best to try to work with
a)
Provisions
b)
Opportunities.
c)
Verify scope
d)
Risks.
23.
You're a PM, a program manager here to help with the bid for her latest project. You want to protect your company from financial risks. You already have a limited scope definition. What type of contract is best to choose?
a)
Fixed price contract
b)
Cost plus percent of cost CPPC contract (cost plus percent of cost CPPC)
c)
Time and materials contracts
d)
CPFF cost-plus-fixed-fee contract
24.
If a risky event has a 90% chance of occurring, and the outcome is $10,000, the corresponding $90,000 is:
a)
Risk value
b)
Present value - the current value of cash flows that will bring a certain amount of investment capital turnover in the future
c)
Expected monetary value
d)
Random budget
25.
What type of contract would you NOT want to use if you don't have the manpower to check the invoices?
a)
A. Cost-plus-fixed-fee (CPFF) contract
b)
B. Time and materials contract (TM)
c)
C. Fixed Price Contract (FP)
d)
D. Fixed price incentive contract (FPIF-fixed price incentive fee)
26.
While preparing your risk response plan, you identify a few additional risks. What should you do?
a)
Add a reserve to the project to consider new risks and communicate them to management
b)
Record risk items and calculate an expected monetary value based on the probability and impact of the outcome of the risk occurrence.
c)
Identify risk events and associated costs, then add these costs to the project budget as a contingency.
d)
Add 10% of the cost of surprises to the project budget and notify the customer
27.
The project is halfway through when you discover that a software vendor for your project is having great difficulty keeping employees due to a labor dispute. Many other projects in your company also use your services. What should you do?
a)
A. Try to keep their requests in your project
b)
B. Talk to other PMs in the company about labor issues
c)
C. Contact the company and advise that you will cancel their work on the project unless they resolve the labor dispute
d)
D. End business with this company
28.
project team has completed, and the customer has accepted, the project scope is complete. However, the lessons learned requested by the project management department have not yet been completed. What is the status of the project?
a)
A. The project is not completed because the project needs to be replanned
b)
B. The project is not complete until the entire project and deliverables are complete and accepted
c)
C. The project is complete because the customer has accepted the deliverable
d)
D. The project is completed because the project has reached the due date (reach the due date).
29.
Which of the following statements about change control is true?
a)
A fixed price contract reduces the need for change control
b)
Changes rarely provide real benefits to the project
c)
Contracts should include procedures appropriate to changes
d)
The more detailed the parameters will eliminate the causes of change
30.
Risk tolerance is determined to help:
a)
The project team can classify project risks
b)
PM estimates the project
c)
The project team creates the project schedule.
d)
Management knows other managers will act on the ntn project
31.
Which statement regarding the bid documents is correct?
a)
Well designed bid documents can simplify the comparison of response.
b)
Bid documents must be strict and inflexible to allow the buyer's comments and suggestions to be considered.
c)
In general, bid documents should not include standard estimates
d)
Well-designed bid documents do not include a contract statement of work
32.
The organization is trying to decide whether to divide the contract management department and assign contracting responsibility to a department with direct responsibility for the project. A contract specialist does not really want this separation because they will lose……………………… in a decentralized (or decentralized) contracting environment.
a)
A. The company's project management performance standards
b)
B. Loyalty to the project (loyalty)
c)
C. Experience
d)
D. Access to others with similar expertise
33.
You have just begun administering a contract when management decides to terminate the contract. What should you do first?
a)
Go back and ask for the seller's response
b)
Return to contract planning.
c)
Complete contract management (contract admin).
d)
At the end of the contract.
34.
In what risk management processes will risks be identified?
a)
Quantitative risk analysis and risk identification
b)
Identify risks and control risks
c)
Identify risks and control risks
d)
Identify risks
35.
You are a PM for a construction project of a large new manufacturing plant and have never worked on it before. The project cost is estimated to be $30,000,000 and will use 3 vendors. Once started, the project cannot be canceled, and there will be a large cost in equipment and plant. As the PM of this project, the most important thing to be very careful about is:
a)
Review all chargebacks from the seller.
b)
Check your contingency budget.
c)
Complete project goals
d)
Carry out risk identification.
36.
Conference of Contractors is part of:
a)
Contract signing plan
b)
Contract management
c)
Request seller responses
d)
Buying and selling plan and what can be recovered
37.
You are ½ of the way through a major network rollout. There are 300 locations in the US and 20 in the UK. A software seller has just released a major software upgrade for several installed devices. Quality enhancement provides customers with functionality they require that was not available at the time the project began. Under these conditions, what action is best?
a)
A. Continue as planned, your customer will not request changes
b)
B. Inform customers about quality improvement and its impact on project timing and functionality
c)
C. Change settings and adjust schedules if necessary as it supports the customer's first request
d)
D. Install changes to the remaining locations and continue as scheduled
38.
All of the following are always inputs to the risk management process except:
a)
Courtesy information
b)
Lessons learned
c)
WBS
d)
Project status report
39.
A check of the cost reimbursable contract (cost reimbursable CR) identifies high quotes that have been performed. If the contract does not specify corrective actions, the buyer should:
a)
Continue making payments for the project
b)
Pay half until the problem is fixed
c)
Void the contract and initiate legal action to recover the overpayment
d)
Change the contract to require more frequent inspections
40.
CPI=0.6, SPI=0.71. The project has 625 work packages and is being completed over a period of more than 4 years. Project team staff were very inexperienced and the project received little support for appropriate planning. Which of the following is best to do?
a)
Updated risk identification and analysis
b)
Spend more time improving cost estimates.
c)
Eliminate as many work packages as possible
d)
Reorganize the responsibility assignment matrix
41.
As part of your records management system, you are trying to make sure that all records from the contract are recorded and indexed. Which of the following should you not worry about?
a)
Proposal
b)
Statement of work
c)
Terms and conditions
d)
Negotiation process
42.
The project team seemed to like to argue: they argued about everything. Fortunately, the PM has set up a system of check-ins and team-building meetings that will help and encourage the project team to collaborate more with each other. The latest thing they debate is whether they should complete the work package themselves or outsource it. What process of purchasing management are they in?
a)
Contract management
b)
Purchasing plan
c)
Request seller reply
d)
Select seller
43.
Your project has just been promoted and you are looking for a tutor to complete your network quickly. There is no time to put out a request for proposals (RFP) so you choose to use a company you have used many times for software development. The main concern in this situation is
a)
Collusion between subcontractors
b)
Professional qualifications of contractors
c)
Evaluation standards of contractors
d)
Organize contractor conferences.
44.
The project manager is asked by the client to make significant changes to the project. These changes are not addressed in the Design Document or Project Scope. What is the best way for the project manager to respond to the request?
a)
Inform the customer that scope changes are not permitted.
b)
Submit change request to Change Management.
c)
Deploy required changes immediately.
d)
Redesign the entire project from scratch.
45.
Workarounds are identified in which risk management process?
a)
Identify risks
b)
Quantitative risk analysis
c)
Risk response plan
d)
Risk control
46.
An experienced PM has just started working in a large IT integration organization. Her manager provided her with a draft of the project charter and immediately asked her to provide an analysis of the risks in the project. Which of the following can best help PM?
a)
An article from PM online magazine
b)
State the project scope from the project planning stage
c)
Resource planning from the project planning stage
d)
A conversation with an employee from a similar project that failed in the past
47.
To complete the work on your project, you have been provided with confidential information from all your customers. A university contacts you to ask for help with their research. Such help will require you to provide the company with some customer data from your files. what should you do?
a)
A. Release the information, but delete all references to the customer's identity
b)
B. Only provide important (or necessary? – high-level) information
c)
C. Contact your customers and seek permission to provide their information
d)
D. Providing information
48.
You are in the midst of a 2-year project to roll out offices across the country. A storm caused a power outage when the upgrade was nearly completed. When the power came back on, all project reports and historical data were lost and there was no way to get them back. What should be done to mitigate this risk?
a)
Warranty of purchase
b)
Plan for a reserve fund
c)
Control the weather and have a plan for the unexpected
d)
Schedule deployment outside of storm season
49.
Your employee is 3 days behind the reporting schedule. 5 minutes before the meeting where the topic of the report will be discussed, she gives you the report. You notice there are some serious errors in there, what should you do?
a)
A. Cancel the meeting and reschedule the meeting after the report has been corrected
b)
B. Go to the meeting and tell everyone in attendance that there is an error in the report
c)
C. Force employees to give presentations and other participants to silently look for errors
d)
D. Cancel the meeting and rewrite the report yourself
50.
The PM and the project sponsor are discussing project costs and when it would be best for their company to participate in the project or hire another company to do it. If they ask for your opinion, you should say that the company would be better off doing this project itself if:
a)
There is too much proprietary data
b)
The company has the expertise but does not have the available human resources
c)
The company does not need to control the work
d)
The company's resources are limited
51.
During the project implementation phase, project team employees hand over the project products to the seller. However, the seller rejected these products, claiming that they did not meet the requirements on page 300 of the technical specification. You have reviewed the document and agree. What's the best thing to do?
a)
A. Explain that the contract is wrong and should be changed
b)
B. Make a change request
c)
C. Review the requirements and meet with the person responsible for this to review the WBS dictionary
d)
D. Meet with the project team to review the requirements on page 300
52.
A PM for a seller was told by her management that the project should do what it could to reward incentives. The main objective of preferential clauses in contracts is
a)
Reduced prices from buyers
b)
Helps sellers control costs
c)
Synchronize goals
d)
Reduce risk from the seller by transferring risk to the buyer
53.
A seller is awarded a contract to build a pipeline. The terms and conditions of the contract required that a work plan be presented to the buyer for approval before work began, but the seller failed to provide a work plan. Which of the following is best for the seller's PM to do?
a)
File a letter of intent (file a letter of intent)
b)
Build a work plan and present it to the seller to make the work go smoothly (move thing along).
c)
Provide a default text (default letter)
d)
Ask the seller to stop work until a work plan is prepared.
54.
All of the following are factors in project risk assessment except:
a)
A. Risk event
b)
B. Risk probability
c)
C. Amount at risk (amout at stake)
d)
D. Insurance costs
55.
The customer requests that a project change be made that will increase project risk. Which of the following should you do in front of everyone?
a)
Take into account the expected monetary value of the risk in the new cost estimate
b)
Talk to customers about the impact of the change
c)
Analyze the impact of changes with the project team
d)
Change the risk management plan
56.
client gives you a statement of work for an 8-month project that is complex and has a few unknowns. The customer asks you to just “get it done” and only wants to meet you at the end of the 8th month when you hand over the completed project. In this situation, the best thing to do is:
a)
A. Complete the project as requested, but verify the scope with the customer occasionally throughout the project
b)
B. Completed the project in just 8 months without any contact with the customer during this period
c)
C. Ask management for occasional confirmation with customers
d)
D. Complete the project, but note that the customer does not want to be contacted
57.
You are working on a large construction project that is within the boundaries. Resources are used gradually (remain steady), your boss has just rewarded you for your effort. A project team member returns from a meeting with a client and tells you that the client is dissatisfied with the project's performance. The first thing you should do is:
a)
A. Talk to your manager
b)
B. Complete project team building exercises and invite customer representatives to attend
c)
C. Change the basic schedule path
d)
D. Meet with customers to find out details (uncover detail)
58.
Which of the following is NOT the PM's responsibility?
a)
A. Maintain the confidentiality of confidential customer information
b)
B. Determine the legality of corporate procedures
c)
C. Make sure that a conflict of interest does not affect the legitimacy of the client's interests
d)
D. Provide accurate and honest results in cost estimates
59.
The project team is arguing about which potential seller should accept the offer. One project employee argued for a trusted vendor while another employee wanted the project to go to a different vendor. What part of the purchasing management process is the project team in?
a)
Purchasing plan
b)
Contract signing plan
c)
Request seller reply
d)
Select seller.
60.
You are equipped as a manager of a large, new and complex project. Because this project is business-critical and very visible, senior managers tell you to analyze project risks and prepare a risk response strategy as early as possible. The organization has a risk management process that is rarely used, and has a history of poor risk capture. The first milestone of the project is within 2 weeks. While preparing a risk response plan, where the input comes from is usually the least important of the following answers:
a)
Project team staff
b)
Project sponsor
c)
Individuals responsible for risk management policies and templates
d)
Key stakeholders
61.
During a meeting with a few stakeholders, the PM is asked to add work to the project scope. The PM used information relevant to the project before the project charter was signed and remembered that the sponsor had explicitly rejected funds for the scope mentioned by the stakeholders. The best thing a PM should do is:
a)
A. Let the sponsor know the requirements of relevant parties
b)
B. Evaluate the impact of additional ranges
c)
C. Tell stakeholders that scope cannot be added
d)
D. Add work if there is time left in the project schedule
62.
All of the following must be present for a contract to exist except:
a)
Contract statement of work.
b)
Acceptance
c)
Seller's address
d)
Buyer's signature.
63.
What should be accomplished with the risks on the watchlist?
a)
Record them for historical information for use in other projects
b)
Record them and review them during the project
c)
Record them and put them aside as they are part of your contingency plan
d)
Record them and give them to the customer
64.
Which of the following is an important characteristic of the Delphi technique?
a)
Conclusion from historical records from previously implemented projects
b)
Expert opinion
c)
Hierarchical analysis process
d)
Bottom-up approach.
65.
Terminating a contract is different from ending administrative activities in that it terminates the contract
a)
Occurs before the end of administrative activities
b)
It's the only thing that concerns the customer
c)
Including return of property
d)
Can be completed more than once per contract
66.
The project manager is developing a plan for the project. The project manager identified tasks and assigned appropriate resources. The tool is used to notify that some resources have been allocated. What will be the project manager's next step?
a)
Move resources.
b)
Request additional resources.
c)
Adjust resources
d)
Draft overtime budget
67.
project manager is assigned to a large project that has been in progress a number of times. The project team has just completed the design phase of the project and is underway in the implementation phase. At this point, what changes can be made without running the risk of redoing the entire design phase?
a)
Limit
b)
Mission
c)
Detailed design
d)
Transfer date
68.
A new PM is starting to create a contract statement of work. A related party wants to add a few items to the contract statement of work. Another stakeholder just wants to describe the functional requirements. The project is important to the PM's company, but a seller will do this. What would you advise this PM?
a)
A. The contract statement of work should be general to allow the seller to make his own decisions
b)
B. The contract statement of work should be general to allow for future revisions
c)
C. The contract statement of work should be detailed to allow for future revisions
d)
D. The contract statement of work should be as detailed as possible for the type of project
69.
You are in a complicated negotiation when the other side says: "We need to finish in 1 hour because I have to catch a plane". What negotiation strategy is this person using?
a)
Good guy, bad guy (good guy, bad guy)
b)
Delay
c)
Deadline
d)
Extreme demands.
70.
project performed under a cost-reimbursable contract is finally nearing its end. The buyer must remember what to do
a)
Reduce project risk level
b)
Check for agreement with the seller's price
c)
Estimate the fees he must pay
d)
Make sure the seller doesn't add any resources
71.
The project team is debating the prospective seller, who has submitted proposals. One employee argued for a trusted vendor, while another employee wanted another vendor to take the project. The best things PMs should remind their teams to focus on during the selection process are:
a)
A. Contract documents
b)
B. Check the contract
c)
C. Evaluation standards
d)
D. Contract management plan
72.
The software development project is not developing well. There are more than 30 stakeholders, and no one agrees on the project goals. One stakeholder believes the project could get a 30% improvement while another believes it could go up to 50%. PM then 10% improvement is more realistic. The best solution is:
a)
A. Continue developing the project and seek additional information afterward to resolve the issue
b)
B. Take the average and use it as a target
c)
C. Perform a feasibility analysis
d)
D. Ask the sponsor for the final decision
73.
You are the PM for one of many projects in a large and important program. At an important meeting, you notice that another PM reported her project on schedule. Looking through your project a few weeks ago, you remembered that many deliverables from other projects were delayed. What should you do?
a)
A. Meet with the program manager
b)
B. Develop a risk control plan
c)
C. Discuss the problem with your supervisor
d)
D. Meet the other PM
74.
You are working on a research and development project, and the client asks you to include a special component in the project. You know that it means extra work, and you don't want to exceed available reserves. what should you do?
a)
A. Delete lower priority work packages to free up available time and resources
b)
B. Use reserves from contingent appropriations to offset costs
c)
C. Follow the contract change control process
d)
D. Request additional reserves from the sponsor
75.
What is one of the main goals in the negotiation process?
a)
. Get a fair and reasonable price.
b)
Negotiate a price according to the seller's estimate
c)
Make sure all project risks are thoroughly described
d)
Make sure there is an effective communications management plan in place
76.
project has a tight budget when you start negotiating with a seller about equipment. The seller tells you that the price of this device is fixed. Your manager told you to negotiate the price with the seller. Which action is best/
a)
A. Make a good commitment effort to find ways to reduce prices
b)
B. Postpone negotiations until you convince your manager to change his mind
c)
C. Still negotiating, but only on other aspects of the project
d)
D. Cancel negotiation
77.
Near the end of your final project, a group of stakeholders want to add requirements as they know they will be impacted by your project. This will be a hassle since you are not including time and cost in the project management plan for these types of requests. The best things you can do to prevent these problems in upcoming projects are:
a)
A. Review the WBS dictionary carefully, looking for incomplete descriptions
b)
B. Review the project's principles carefully and check for business gaps
c)
C. Do an extra thorough job of contract planning
d)
D. Pay more attention to the leadership of relevant parties
78.
Your company has an emergency and needs the contract work completed as soon as possible. Given this situation, which of the following would be most beneficial to add to the contract?
a)
A statement of employment contract
b)
Requirements in which subcontracts may be used
c)
Deals
d)
A force majeure clause
79.
Your employee is 3 days behind the reporting schedule. 5 minutes before the meeting where the topic of the report will be discussed, she gives you the report. You see some serious errors in the report. Can this be prevented?
a)
A. Require employees to update routines
b)
B. Train and mentor employees
c)
C. Make sure the employee is capable of doing the job
d)
D. Postpone the meeting earlier because you don't have time to review the report
80.
You're always told by management to cut the project estimate by 10% after you give it to them. The scope of the new project is not clear and there are more than 30 parties involved. Management wants to reduce break time by 25% as a result of the project. Which of the following is the best action in this situation?
a)
A. Replan to get a 35% improvement in break time
b)
B. Reduce the estimate and record the change in the risk response plan
c)
C. Provide an accurate estimate of the actual cost and try to justify it
d)
D. Meet with the project team to determine where you can save 10%.
81.
The project manager discovered an issue with the project's statistics module. Measurements are stated in US units, but foreign programmers use international units. Where in the project could this problem have been avoided?
a)
Project planning
b)
Test the project.
c)
Project control.
d)
Project turnaround
82.
Which of the following best describes the PM's role in the contract signing process?
a)
PM only has an unimportant role
b)
PM should be the one negotiating.
c)
PM should provide a clear understanding of project risks.
d)
The PM should tell the contract manager how to handle the contract signing process.
83.
Which of the following communication techniques will best improve stakeholders' understanding of the project?
a)
Implementation emails to all employees about project goals and desired outcomes
b)
Executive meetings with stakeholders to explain project goals and desired outcomes
c)
Town hall meetings with the project team provide information and stakeholders have the ability to ask questions.
d)
Resistance from stakeholders in the project management team.
84.
Which of the following is NOT an input to the initialization process group?
a)
company processes
b)
the corporate culture
c)
historical WBSs (previous WBSs)
d)
project scope statement (project scope report)
85.
Buying insurance is the most obvious example of risk:
a)
Mitigation
b)
Transfer
c)
Acceptance
d)
Avoidance
86.
The various project evaluation activities from the evaluation teams within the project represent centralized evaluation
a)
How does an individual team member perform on the project?
b)
1 evaluate the effectiveness of the project team
c)
A group of construction efforts
d)
Reduce employee turnover rate
87.
The 1-year communications project was halfway through when you replaced the previous project director. The project entailed 3 different clients and a project team of 30 people. You want to know the communication requirements and what type of technology is used to support project communications. Where do you find that information?
a)
Project management plan
b)
Information distribution plan
c)
Column chart
d)
Communication management plan
88.
The project manager uses a cause-and-effect analysis chart to identify factors that may cause risk. What part of the quality management process is the project manager involved in?
a)
quality analysis
b)
Implement quality assurance
c)
quality control
d)
Plan quality management
89.
The director and the entire project team are looking forward to the new project. This is the first project management assignment. The project team feels they will be able to complete work that they have never done before. Yes. 29 people contributed to the product description and the project team had 9 experts with extensive experience in their fields. Partway through the planning, three groups of the technical team were disagreeing on the scope of the two statements. One group pointed to the draft WBS and said that work packages should be supplemented. One group said that special work packages should not be done. Members of the third group agreed with both groups. on,How should a project manager best resolve conflicts?
a)
He should listen to different perspectives, determine the best choice, and make that choice.
b)
He should defer discussions, meet with individuals and determine the best approach.
c)
He should listen to different points of view, encourage reasoned discussion, and facilitate an agreement.
d)
He will help groups focus on aspects that are relevant to their perspectives, and build unity by reducing tension and building a common focus group.
90.
The project team created a plan that describes how they will implement quality assurance provisions. The content primarily concerns the organization's structure, responsibilities, procedures, and other information about the management plan. quality management. If it changes during the project, which of the following will also change?
a)
quality
b)
quality management
c)
Project manager
d)
quality control
91.
A project to implement a new piece of software is underway. The project manager works with the quality assurance department to make them confident that the project meets quality standards. What MUST be done before progress can be made? This program?
a)
Review quality issues
b)
quality improvement
c)
There is a quality assurance mechanism
d)
re-execute
92.
The project you are working on is increasing cost efficiency, increasing productivity, and increasing morale. The reason for that?
a)
Project goals go hand in hand with implementation organization
b)
quality increases
c)
The project focuses on cost reduction
d)
reward individual efforts
93.
In what situations can WBS effectively support communication?
a)
Internally within the project team
b)
Internally within the organization
c)
External communication with customers
d)
Both internal and external project communication
94.
Communication is often enhanced when the sender………..receiver
a)
talk to
b)
show attitude (by body movements such as facial expressions) when talking to
c)
speak slowly
d)
Show interest in your point of view
95.
When planning your project, which factor do you put first: quality, cost or completion schedule?
a)
Cost is the most important, followed by quality, with implementation schedule ranked last
b)
Quality is most important, more than cost and implementation schedule
c)
Implementation schedule (time) is the most important, then quality, cost last
d)
depending on each project
96.
Correspondence, contract changes and payable claims are ...... of contract management
a)
Product
b)
Tools
c)
Function
d)
Input
97.
One obstacle for project teams in a matrix organization is:
a)
Team organization is a focusing technique
b)
Team members can come from sources and can be difficult to motivate
c)
Teams are also centralized
d)
The teams are so large that they are difficult to handle
98.
Who will bear the cost risk in a fixed price (FP) contract?
a)
Project team
b)
Buyer
c)
Seller
d)
Manager
99.
Correspondence, contract changes and payable claims are ...... of contract management
a)
Product
b)
Tools
c)
Function
d)
Input
100.
In which of the following organizational structures does the project manager have the least power?
a)
Project organization
b)
Organize the network matrix
c)
Weak matrix organization
d)
Organized by function
100 %