UAS Manajemen Proyek TI

Total questions: 100

Worksheet time: 1hrs 15mins

Name
Class
Date
1.

Apa yang dimaksud dengan PERT?

a)

Program Evaluation and Review Technique

b)

Critical Path Method

c)

Early Start

d)

Late Finish

2.

Apa rumus untuk menghitung slack?

a)

Slack = LF - EF

b)

Slack = ES - LF

c)

Slack = LS - ES

d)

Slack = EF - LS

3.

Apa yang harus dilakukan untuk mengidentifikasi jalur kritis?

a)

Mengisi baris Average

b)

Mengisi baris LS

c)

Menghitung ES dan LF untuk masing-masing kegiatan

d)

Membuat diagram urutan sesuai activity dan predecessornya

4.

Apa yang harus dilakukan setelah membuat diagram urutan sesuai activity dan predecessornya?

a)

Mengisi baris LF

b)

Mengisi baris LS

c)

Mengisi baris Average

d)

Mengisi baris EF

5.

Apa yang dimaksud dengan CPM?

a)

Early Start

b)

Program Evaluation and Review Technique

c)

Late Finish

d)

Critical Path Method

6.

Apa yang harus dilakukan setelah mengisi baris LS?

a)

Mengisi baris LF

b)

Mengisi baris Average

c)

Mengisi baris ES

d)

Mengisi baris EF

7.

Apa yang harus dilakukan setelah mengisi baris EF?

a)

Melengkapi nilai baris LF

b)

Mengisi nilai finish baris EF

c)

Mengisi nilai finish baris LF

d)

Mengisi nilai finish pada baris ES

8.

Apa yang harus dilakukan setelah mengisi nilai finish pada baris ES?

a)

Melengkapi nilai baris LF

b)

Mengisi nilai finish baris EF

c)

Melengkapi nilai baris EF

d)

Mengisi nilai finish baris LF

9.

Apa kelebihan dari Model Markov?

a)

Lebih lambat dan kurang akurat dibandingkan dengan Simulasi Monte Carlo.

b)

Mudah diturunkan dari data suksesi.

c)

Tidak memberikan wawasan mendalam tentang perubahan dalam sistem dari waktu ke waktu.

d)

Memiliki keunggulan dalam kecepatan dan akurasi karena sifat analitisnya.

10.

Apa kekurangan dari Model Markov?

a)

Asumsi property Markov mungkin tidak valid untuk sistem yang dimodelkan.

b)

Pelanggan dapat masuk dan keluar pasar kapan saja.

c)

Analisis Markov dapat memprediksi hasil masa depan dalam situasi di mana informasi hasil sebelumnya tidak ada.

d)

Matriks transisi merangkum semua parameter penting dari perubahan dinamis.

11.

Apa yang dimaksud dengan ISO 27001?

a)

Standar untuk manajemen risiko

b)

Standar untuk sistem manajemen kualitas

c)

Standar untuk manajemen keuangan

d)

Standar untuk manajemen sumber daya manusia

12.

Tahapan pertama dalam proses manajemen risiko adalah...

a)

Analisis risiko

b)

Identifikasi risiko

c)

Penerapan ISO 27001

d)

Strategi manajemen risiko

13.

Apa yang dimaksud dengan risiko murni?

a)

Risiko yang bersifat subyektif

b)

Risiko yang tidak melibatkan spekulasi

c)

Risiko yang bersifat statis

d)

Risiko yang melibatkan spekulasi

14.

Manfaat dari penerapan ISO 27001 adalah...

a)

Meningkatkan risiko kualitas produk

b)

Meningkatkan risiko keuangan

c)

Meningkatkan risiko keamanan informasi

d)

Meningkatkan risiko manajemen sumber daya manusia

15.

Apa yang dimaksud dengan strategi 'Mengurangi Risiko'?

a)

Mengikuti pedoman yang ditetapkan

b)

Menghindari risiko denda dan biaya pembelaan

c)

Menerima risiko

d)

Memperbaiki kelemahan keamanan

16.

Teknik apa yang digunakan dalam analisis risiko untuk membuat model probabilistik?

a)

Industry benchmarking

b)

Simulasi Monte Carlo

c)

Decision Trees

d)

Risk-Adjusted Discount Rate

17.

Apa yang dimaksud dengan identifikasi risiko?

a)

Proses untuk mengurangi risiko

b)

Proses untuk menerima risiko

c)

Proses untuk menghindari risiko

d)

Proses untuk mengidentifikasi kemungkinan timbulnya risiko atau kerugian

18.

Tujuan utama implementasi manajemen risiko dalam proyek adalah...

a)

Mempertahankan stabilitas pemasukan

b)

Meningkatkan risiko keuangan

c)

Meningkatkan risiko kemandekan oleh perubahan

d)

Mengurangi risiko biaya manajemen

19.

Apa yang dimaksud dengan risiko spekulatif?

a)

Risiko yang bersifat dinamis

b)

Risiko yang bersifat obyektif

c)

Risiko yang tidak melibatkan spekulasi

d)

Risiko yang melibatkan spekulasi

20.

Bagaimana cara mengelompokkan risiko?

a)

Dengan melihat strategi manajemen risiko

b)

Dengan melihat tahapan penerapan ISO 27001

c)

Dengan melihat tipe-tipe risiko

d)

Dengan melihat ukuran risiko

21.

Apa definisi Rencana Manajemen Proyek?

a)

Dokumen yang diacu dalam pelaksanaan, pengawasan, dan penutupan proyek

b)

Dokumen resmi proyek yang disetujui oleh pemberi kerja

c)

Dokumen yang diacu dalam pelaksanaan, pengawasan, dan penutupan proyek, yang menjamin proyek mencapai sasarannya bila diikuti dengan baik

d)

Sekumpulan aktivitas yang dilakukan secara kolektif pada awal manajemen proyek

22.

Apa kegunaan Rencana Manajemen Proyek?

a)

Sebagai dasar untuk menilai kinerja dalam kegiatan pengawasan proyek

b)

Sebagai dasar untuk menilai kinerja dalam kegiatan pengawasan proyek

c)

Mendokumentasi keputusan penting dan pertimbangannya

d)

Mendokumentasi asumsi-asumsi yang dijadikan dasar dalam perencanaan

23.

Apa saja elemen-elemen perencanaan proyek?

a)

Menentukan standar & prosedur proyek, identifikasi & perkiraan resiko, membuat budget, rencana proyek dasar

b)

Rencana komunikasi, identifikasi & perkiraan resiko, membuat budget, rencana proyek dasar

c)

Lingkup proyek, alternatif & feasibility, jadwal kegiatan, rencana komunikasi

d)

Rencana komunikasi, menentukan standar & prosedur proyek, identifikasi & perkiraan resiko, membuat budget

24.

Apa yang dimaksud dengan Work Breakdown Structure (WBS)?

a)

Teknik untuk memecah komponen ke level-level berikutnya sampai dengan tugas serta membuat jadwal kegiatan

b)

Teknik untuk memecah komponen ke level-level berikutnya sampai dengan tugas dan menentukan sumber-sumber daya serta membuat jadwal kegiatan

c)

Teknik untuk memecah komponen ke level-level berikutnya sampai dengan tugas dan menentukan sumber-sumber daya

d)

Teknik untuk memecah komponen ke level-level berikutnya sampai dengan tugas

25.

Apa yang dimaksud dengan komunikasi efektif dalam manajemen proyek?

a)

Mengurangi kepercayaan di antara pemangku kepentingan

b)

Membantu menghilangkan penundaan yang tidak perlu

c)

Mendorong konflik antar tim

d)

Meningkatkan tingkat stres

26.

Apa itu komunikasi push dalam manajemen proyek?

a)

Metode yang memungkinkan pemangku kepentingan mengakses informasi di waktu luang mereka

b)

Pertemuan tatap muka atau percakapan telepon

c)

Solusi perangkat lunak yang memfasilitasi komunikasi real-time

d)

Mengirimkan informasi kepada penerima tanpa mengharapkan tanggapan segera

27.

Apa alat kolaborasi yang memfasilitasi komunikasi real-time antara pemangku kepentingan proyek?

a)

Cisco Webex

b)

Bitbucket Atlassian

c)

Dropbox

d)

Microsoft Teams

28.

Apa yang dimaksud dengan manajemen virtual dalam proyek TI?

a)

Proses di mana seseorang mengelola proyek dengan menggunakan teknologi augmented reality

b)

Proses di mana seseorang mengelola proyek dengan menggunakan teknologi virtual reality

c)

Proses di mana seseorang mengelola proyek secara langsung di kantor

d)

Proses di mana seseorang mengelola proyek melalui tim jarak jauh atau virtual

29.

Apa tantangan yang dihadapi dalam manajemen proyek virtual?

a)

Prioritaskan membangun kepercayaan

b)

Komunikasi lambat

c)

Membangun kepercayaan

d)

Memantau progress

30.

Apa solusi dari tantangan manajemen virtual?

a)

Tetapkan norma komunikasi

b)

Fokus pada hasil

c)

Jadikan karyawan merasa dalam satu tim

d)

Membangun kepercayaan

31.

Apa yang dimaksud dengan komunikasi interaktif dalam manajemen proyek?

a)

Pertemuan tatap muka atau percakapan telepon

b)

Mengirimkan informasi kepada penerima tanpa mengharapkan tanggapan segera

c)

Solusi perangkat lunak yang memfasilitasi komunikasi real-time

d)

Metode yang memungkinkan pemangku kepentingan mengakses informasi di waktu luang mereka

32.

Apa alat kolaborasi yang memungkinkan pengguna berbagi file serta menyimpan dan mengeditnya secara real time?

a)

Asana

b)

Google Docs

c)

Zoom

d)

Microsoft Teams

33.

Apa yang dimaksud dengan komunikasi pull dalam manajemen proyek?

a)

Pertemuan tatap muka atau percakapan telepon

b)

Solusi perangkat lunak yang memfasilitasi komunikasi real-time

c)

Metode yang memungkinkan pemangku kepentingan mengakses informasi di waktu luang mereka

d)

Mengirimkan informasi kepada penerima tanpa mengharapkan tanggapan segera

34.

Apa alat manajemen proyek berbasis cloud yang menyediakan kemampuan seperti pemantauan kemajuan, pelacakan obyektif, dan penjadwalan tugas?

a)

Microsoft Teams

b)

Asana

c)

Dropbox

d)

Cisco Webex

35.

kompetensi untuk mengidentifikasi, menganalisis dan merespon resiko-resiko yang berkaitan dengan proyek yang dikerjakan. adalah...

a)

risk management

b)

procurement management

c)

communication management

d)

stakeholders management

36.

4 phase Project Life Cycle adalah

a)

The Conceptualization Phase - The Planning Phase - The Action Phase - The Termination Phase

b)

The Starting Phase - The Planning Phase - The Execution Phase - The Termination Phase

c)

The Conceptualization Phase - The Planning Phase - The Execution Phase - The Takeover Phase

d)

The Conceptualization Phase - The Planning Phase - The Execution Phase - The Termination Phase

37.

PMBOK adalah

a)

panduan yang memuat himpunan istilah dan pedoman untuk 

manajemen sumber daya yang diterbitkan oleh 

Project Management Institute (PMI).

b)

panduan yang memuat tata kelola  

manajemen yang diterbitkan oleh 

Project Management Institute (PMI).

c)

panduan yang memuat himpunan istilah dan pedoman untuk 

manajemen proyek yang diterbitkan oleh 

Project Management Institute (PMI).

d)

panduan yang memuat himpunan istilah dan pedoman untuk 

manajemen proyek yang diterbitkan oleh 

Professional Management Institute (PMI).

38.

CPM dalam manajemen proyek merupakan singkatan...

a)

Critical Path Method

b)

Critical Path Momment

c)

Critical Payless Method

d)

Critical Path Management

39.

Usaha untuk menentukan beberapa banyak uang, usaha (effort), sumber daya, dan waktu akan dibutuhkan untuk membangun sebuah proyek...

a)

estimasi

b)

cost

c)

risiko

d)

time

40.

5. Menurut PMBOK, kegiatan yang dilakukan dalam tahapan Initiating adalah :

a)

Develop Project Charter

b)

Develop Project Managemnt Plan

c)

Point A dan B benar

d)

Identify Stakeholder

41.

Apa fungsi dari Project Charter?

a)

A.     Dokumen hasil implementasi proyek

b)

B. Dokumen formal yang menandakan inisiasi proyek sebagai baseline awal proyek

c)

C. Dokumen perencanaan pengembangan

d)

D. Dokumen Pengesahan Proyek

42.

Apa yang tidak bisa kita dilakukan pada aplikasi trello ?

a)

Membuat ruang diskusi

b)

Membuat list

c)

Membuat penilaian tugas

d)

Menambahkan program kegiatan

e)

Membuat label

43.

Aplikasi kolaborasi yang memungkinkan kita untuk mengatur berbagai proyek dalam satu tempat disebut ?

a)

Aplikasi zoom

b)

Aplikasi Colab

c)

Aplikasi google meet

d)

Aplikasi trello

e)

Aplikasi videoshow

44.

Apa yang dimaksud dengan manajemen proyek?

a)

Strategi pemasaran produk baru

b)

Pendekatan untuk meningkatkan kinerja karyawan

c)

Metode pengelolaan keuangan perusahaan

d)

Metode perencanaan dan pengelolaan sumber daya untuk menyelesaikan sebuah proyek

45.

Apa yang menjadi perbedaan utama antara manajemen proyek dan manajemen konvensional?

a)

Rentang waktu yang dijalankan

b)

Jenis sumber daya yang digunakan

c)

Tujuan yang ingin dicapai

d)

Jumlah anggota tim yang terlibat

46.

Apa yang dimaksud dengan pendekatan tradisional dalam manajemen proyek?

a)

Pendekatan yang dikembangkan untuk beberapa industri seperti manufaktur

b)

Pendekatan yang dikembangkan khusus untuk software engineering

c)

Pendekatan yang fokus kepada kolaborasi tim

d)

Pendekatan yang berfokus kepada sumber daya yang dibutuhkan untuk masing-masing tugas

47.

Apa yang menjadi ciri khas dari pendekatan Scrum dalam manajemen proyek?

a)

Anggota tim memiliki beban tanggung jawab yang biasa diemban oleh project manager

b)

Berfokus kepada sumber daya yang dibutuhkan untuk masing-masing tugas

c)

Pendekatan yang bersifat lebih kontinyu

d)

Dikembangkan khusus untuk software engineering

48.

Tahapan manajemen proyek yang mana yang dilakukan setelah menentukan tujuan proyek dan ruang lingkup proyek?

a)

Penutupan

b)

Perencanaan

c)

Pelaksanaan

d)

Pengawasan

49.

Apa yang menjadi tanggung jawab utama dari seorang project manager dalam tahapan pelaksanaan proyek?

a)

Memastikan semua hal berjalan sesuai dengan timeline dan anggaran dana yang sudah ditentukan

b)

Membuat rancangan mengenai keseluruhan proyek secara lebih rinci

c)

Mengukur setiap progres yang ada agar sesuai dengan perencanaan

d)

Menyelesaikan kontrak dengan pihak eksternal yang dilibatkan

50.

Apa yang dilakukan saat proses penutupan proyek?

a)

Menyelesaikan kontrak dengan pihak eksternal yang dilibatkan, membuat arsip dokumen-dokumen penting, dan juga membuat laporan proyek

b)

Membuat rancangan mengenai keseluruhan proyek mulai dari permulaan sampai akhir secara lebih rinci

c)

Mengukur setiap progres yang ada agar sesuai dengan perencanaan

d)

Memilih sumber daya yang akan mengerjakan proyek, memilih team leader, membuat kontrak dengan vendor, supplier

51.

Who is accountable for ordering product backlog items?

a)

The Developers

b)

The Scrum Master

c)

The Scrum team

d)

The Product Owner

52.

Who is accountable for a Sprint Backlog item that is taken on by a Development Team member?

a)

The Development Team

b)

The Product Owner

c)

The Scrum Master

d)

This particular Development Team member

53.

In Scrum, one role supports the Scrum team in focusing on creating high-value increments. Which role is this?

a)

The Developers

b)

The Product Owner

c)

The Scrum Master

54.

Who should attend the sprint planning meeting?

a)

Only the Developers because they estimate the chosen product backlog items

b)

Only the Developers and the Scrum Master because they should provide input and lead the meeting

c)

Only the Product Owner and the Scrum Master because they estimate and order the items

d)

The entire Scrum team because each role must contribute their own part to this meeting

55.

A Scrum team works with sprints of two weeks. The sprint review takes usually two to three hours, but never more than four hours.

Is this good practice?

a)

Yes, the time-box is four hours, but it is usually shorter for two-week sprints.

b)

Yes, there is no predefined number of hours for sprints shorter than a month.

c)

No, the sprint takes less than a month, so the sprint review should never last four hours.

d)

No, the time-box should be two hours since the sprint is two weeks.

56.

What is a statement of value as described in the Agile Manifesto?

a)

Comprehensive documentation over working software

b)

Contract negotiation over customer collaboration

c)

Following a plan over responding to change

d)

Individuals and interactions over processes and tools

57.

Apa yang dimaksud dengan Earned Value Management (EVM)?

a)

Sebuah metode untuk mengukur kepuasan karyawan dalam sebuah proyek

b)

Sebuah teknik manajemen proyek untuk mengukur kinerja dan progres dari proyek

c)

Sebuah pendekatan untuk mengukur keberlanjutan lingkungan dalam proyek

d)

Sebuah strategi untuk menilai keberhasilan pemasaran proyek

58.

Apa yang dimaksud dengan Planned Value dalam Earned Value Management?

a)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

b)

Jumlah pendapatan yang harus diperoleh setelah proyek rampung

c)

Jumlah uang yang telah dikeluarkan proyek saat pekerjaan sedang dilakukan

d)

Jumlah pendapatan yang telah diraih dari proyek

59.

Apa yang dimaksud dengan Earned Value dalam Earned Value Management?

a)

Total pendapatan yang telah diraih dari proyek

b)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

c)

Jumlah uang yang telah dikeluarkan proyek saat pekerjaan sedang dilakukan

d)

Jumlah pendapatan yang harus diperoleh setelah proyek rampung

60.

Apa yang dimaksud dengan Actual Cost dalam Earned Value Management?

a)

Nilai pasar dari biaya yang dikeluarkan oleh proyek saat pekerjaan sedang dilakukan

b)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

c)

Total pendapatan yang telah diraih dari proyek

d)

Jumlah pendapatan yang harus diperoleh setelah proyek rampung

61.

Apa keunggulan dari Earned Value Management?

a)

Memberikan visibilitas dan kendali yang lebih besar atas kegiatan proyek

b)

Meningkatkan kualitas proyek serta memungkinkan manajemen untuk meraih nilai akuntabilitas yang lebih dari cukup

c)

Semua jawaban di atas benar

d)

Memungkinkan karyawan dan tim manajemen untuk menyelesaikan pekerjaan sesuai jadwal proyek

62.

Apa yang dimaksud dengan Baseline dalam Earned Value Management?

a)

Sebuah teknik manajemen proyek untuk mengukur kinerja dan progres dari proyek

b)

Total pendapatan yang telah diraih dari proyek

c)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

d)

Titik referensi untuk semua aktivitas terkait evaluasi

63.

Apa yang dimaksud dengan Prinsip Planned Value dalam Earned Value Management?

a)

Sebuah teknik manajemen proyek untuk mengukur kinerja dan progres dari proyek

b)

Total pendapatan yang telah diraih dari proyek

c)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

d)

Nilai pasar dari biaya yang dikeluarkan oleh proyek saat pekerjaan sedang dilakukan

64.

Apa yang dimaksud dengan Prinsip Earned Value dalam Earned Value Management?

a)

Sebuah teknik manajemen proyek untuk mengukur kinerja dan progres dari proyek

b)

Total pendapatan yang telah diraih dari proyek

c)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

d)

Nilai pasar dari biaya yang dikeluarkan oleh proyek saat pekerjaan sedang dilakukan

65.

Apa yang dimaksud dengan Prinsip Actual Cost dalam Earned Value Management?

a)

Nilai pasar dari biaya yang dikeluarkan oleh proyek saat pekerjaan sedang dilakukan

b)

Jumlah nilai yang diharapkan dari proyek dalam kurun waktu yang telah disepakati

c)

Sebuah teknik manajemen proyek untuk mengukur kinerja dan progres dari proyek

d)

Total pendapatan yang telah diraih dari proyek

66.

Apa yang dimaksud dengan Proses kerja EVM?

a)

Untuk memberikan perkiraan akurat terkait masalah kinerja proyek

b)

Untuk menemukan variasi dalam proyek berdasarkan perbandingan pekerjaan yang dilakukan dengan pekerjaan yang telah direncanakan

c)

Untuk menyediakan data kuantitatif yang kelak dapat digunakan project manager sebagai pertimbangan sebelum mengambil keputusan

d)

Semua jawaban di atas benar

67.

Apa itu metode jalur kritis (CPM)?

a)

Algoritme untuk mengukur produktivitas tim

b)

Teknik untuk mengidentifikasi tugas penting dalam proyek

c)

Metode untuk menghitung biaya proyek

d)

Strategi untuk mengelola konflik dalam tim

68.

Mengapa menggunakan metode jalur kritis?

a)

Untuk menentukan strategi pemasaran proyek

b)

Untuk menghindari penghambat dalam proyek

c)

Untuk memfasilitasi manajemen sumber daya yang lebih efektif

d)

Untuk menghitung biaya proyek

69.

Bagaimana cara menemukan jalur kritis dalam proyek?

a)

Menghitung biaya proyek secara manual

b)

Membuat daftar aktivitas dan mengidentifikasi dependensi

c)

Menggunakan diagram Gantt untuk memetakan jalur kritis

d)

Menggunakan algoritme untuk menentukan jalur kritis

70.

Apa yang dimaksud dengan kelonggaran waktu dalam metode jalur kritis?

a)

Waktu yang harus dihabiskan untuk menyelesaikan tugas kritis

b)

Waktu yang dapat digunakan untuk menunda tugas tanpa konsekuensi

c)

Waktu tambahan untuk menyelesaikan proyek lebih cepat

d)

Waktu yang harus dihabiskan untuk menyelesaikan tugas nonkritis

71.

Apa yang dilakukan saat terjadi kekurangan sumber daya dalam proyek?

a)

Menambahkan lebih banyak tugas ke jalur kritis

b)

Mempercepat semua tugas dalam proyek

c)

Mengubah jalur kritis menjadi jalur nonkritis

d)

Menggunakan teknik pemerataan sumber daya

72.

Bagaimana cara mempercepat jadwal proyek menggunakan metode jalur kritis?

a)

Dengan menggunakan teknik fast tracking dan crashing

b)

Dengan mengurangi jumlah tugas dalam proyek

c)

Dengan menunda tugas nonkritis

d)

Dengan menambahkan lebih banyak tugas ke jalur kritis

73.

Apa yang dimaksud dengan teknik fast tracking dalam metode jalur kritis?

a)

Teknik untuk menghitung kelonggaran waktu

b)

Teknik untuk mempercepat keseluruhan durasi proyek

c)

Teknik untuk menjalankan aktivitas secara bersamaan

d)

Teknik untuk mengurangi jumlah tugas dalam proyek

74.

Apa yang dimaksud dengan teknik crashing dalam metode jalur kritis?

a)

Teknik untuk mempercepat keseluruhan durasi proyek

b)

Teknik untuk menjalankan aktivitas secara bersamaan

c)

Teknik untuk menghitung kelonggaran waktu

d)

Teknik untuk alokasi lebih banyak sumber daya guna mempercepat aktivitas

75.

Apa singkatan dari PERT?

a)

Program Execution and Review Technique

b)

Project Execution and Review Technique

c)

Project Evaluation and Review Technique

d)

Program Evaluation and Review Technique

76.

Apa fungsi utama dari Bagan PERT?

a)

Mengelola keuangan proyek

b)

Memonitor progres proyek

c)

Membuat peta jalan proyek

d)

Mengatur sumber daya proyek

77.

Apa perbedaan utama antara Bagan PERT dan Bagan Gantt?

a)

Bagan PERT menawarkan kustomisasi, sedangkan Bagan Gantt menawarkan organisasi

b)

Bagan PERT menawarkan organisasi, sedangkan Bagan Gantt menawarkan kustomisasi

c)

Bagan PERT adalah grafik batang, sedangkan Bagan Gantt adalah aliran

d)

Bagan PERT adalah aliran, sedangkan Bagan Gantt adalah grafik batang

78.

Apa langkah pertama dalam membuat Bagan PERT?

a)

Perkirakan kerangka waktu proyek

b)

Menghubungkan tugas proyek

c)

Menentukan dependensi tugas

d)

Mengidentifikasi tugas proyek

79.

Apa yang dimaksud dengan dependensi tugas dalam Bagan PERT?

a)

Tugas atau milestone yang bergantung pada tugas lain

b)

Tugas yang tidak terkait dengan tugas lain

c)

Tugas yang tidak memerlukan sumber daya

d)

Tugas yang memiliki sumber daya terbanyak

80.

Apa yang dilakukan dengan menghubungkan tugas proyek dalam Bagan PERT?

a)

Membuat panah untuk merepresentasikan dependensi tugas

b)

Mengelola progres tugas

c)

Membuat simpul untuk merepresentasikan peristiwa proyek

d)

Menghitung perkiraan waktu proyek

81.

Apa yang dimaksud dengan waktu optimis dalam perhitungan durasi tugas menggunakan rumus PERT?

a)

Rata-rata waktu yang dibutuhkan untuk menyelesaikan tugas

b)

Jumlah waktu maksimum yang diperlukan untuk menyelesaikan tugas

c)

Perkiraan terbaik tentang waktu yang dibutuhkan untuk menyelesaikan tugas

d)

Jumlah waktu minimum yang diperlukan untuk menyelesaikan tugas

82.

Kapan sebaiknya menggunakan Bagan PERT?

a)

Untuk menentukan jalur kritis proyek

b)

Semua jawaban di atas

c)

Untuk mengevaluasi sumber daya proyek

d)

Untuk memperkirakan waktu proyek

83.

Apa yang dapat dilakukan dengan Bagan PERT sebelum proyek dimulai?

a)

Semua jawaban di atas

b)

Mengomunikasikan tujuan proyek kepada pemangku kepentingan

c)

Mengidentifikasi tugas proyek

d)

Memperkirakan waktu yang dibutuhkan untuk menyelesaikan tugas individu

84.

Apa yang dimaksud dengan simpul dalam Bagan PERT?

a)

Keterkaitan logis antara tugas proyek

b)

Tugas yang perlu diselesaikan agar simpul dapat diimplementasikan

c)

Peristiwa proyek yang merupakan komponen besar dari proyek

d)

Dependensi tugas yang tidak memiliki sumber daya

85.

Apa yang dimaksud dengan dependensi tanpa sumber daya dalam Bagan PERT?

a)

Dependensi yang memiliki sumber daya terbanyak

b)

Dependensi yang tidak memiliki tugas nyata yang perlu diselesaikan

c)

Dependensi yang tidak memerlukan waktu untuk diselesaikan

d)

Dependensi yang tidak memerlukan sumber daya

86.

Apa yang dapat dilakukan dengan Bagan PERT untuk memperkirakan durasi tugas?

a)

Menghitung waktu optimis, pesimis, dan paling mungkin

b)

Mengelola progres tugas

c)

Menghubungkan tugas proyek

d)

Membuat panah untuk merepresentasikan dependensi tugas

87.

Apa yang dilakukan dengan mengelola progres tugas dalam Bagan PERT?

a)

Menghubungkan tugas proyek

b)

Mengidentifikasi tugas proyek

c)

Menutup dependensi dan mengurangi masalah selama proses

d)

Perkirakan kerangka waktu proyek

88.

Apa yang dapat dilakukan dengan Bagan PERT setelah semua tugas proyek selesai?

a)

Perkirakan kerangka waktu proyek

b)

Mengarsipkan materi di ruang bersama untuk menjadi referensi di masa mendatang

c)

Mengidentifikasi tugas proyek

d)

Menghubungkan tugas proyek

89.

Apa yang dimaksud dengan rumus PERT dalam perhitungan durasi tugas?

a)

Rumus untuk menghitung rata-rata waktu yang dibutuhkan untuk menyelesaikan tugas

b)

Rumus untuk menghitung waktu optimis, pesimis, dan paling mungkin

c)

Rumus untuk menghitung perkiraan durasi tugas dan waktu penyelesaian

d)

Rumus untuk menghitung waktu yang dibutuhkan untuk menyelesaikan tugas

90.

Analisis markov merupakan suatu bentuk khusus dari model probabilistik yang lebih umum dikenal sebagai proses stokastik. Apa yang dimaksud dengan proses stokastik?

a)

a. Suatu barisan kejadian yang berulang kali

b)

b. Teknik perhitungan rantai markov

c)

c. Konsep dasar rantai markov

d)

d. Suatu barisan kejadian yang memenuhi hukum-hukum peluang

91.

Sifat rantai markov adalah sebagai berikut, kecuali

a)

a. Memiliki jumlah state yang terbatas

b)

b. Memiliki matriks berpasangan

c)

c. Memiliki transisinya stasioner

d)

d. Memiliki sifat markov

92.

Salah satu ciri dari analisis markov yaitu

a)

a. Probabilitas transisi hanya tergantung pada status awal

b)

b. Probabilitas transisi akan berubah pada waktu tertentu

c)

c. Memiliki nilai random

d)

d. Menghitung probabilitas di waktu lampau

93.

Ada beberapa syarat yang harus dipenuhi dalam menerapkan analisis rantai markov yaitu, kecuali

a)

a. Jumlah probabilitas transisi untuk keadaan awal sistem tidak sama dengan 1

b)

b. Probabilitas transisi konstan sepanjang waktu

c)

c. Probabilitas berlaku untuk semua partisipan dalam sistem

d)

d. Kondisi independent sepanjang waktu

94.

Arti kata stokastik adalah...

a)

Rerata

b)

Random

c)

Rentang

d)

Validitas

95.

Apa kelebihan dari Model Markov?

a)

Lebih lambat dan kurang akurat dibandingkan dengan Simulasi Monte Carlo.

b)

Mudah diturunkan dari data suksesi.

c)

Tidak memberikan wawasan mendalam tentang perubahan dalam sistem dari waktu ke waktu.

d)

Memiliki keunggulan dalam kecepatan dan akurasi karena sifat analitisnya.

96.

Apa kekurangan dari Model Markov?

a)

Asumsi property Markov mungkin tidak valid untuk sistem yang dimodelkan.

b)

Pelanggan dapat masuk dan keluar pasar kapan saja.

c)

Analisis Markov dapat memprediksi hasil masa depan dalam situasi di mana informasi hasil sebelumnya tidak ada.

d)

Matriks transisi merangkum semua parameter penting dari perubahan dinamis.

97.

Apa itu analisis Markov?

a)

Metode untuk memprediksi nilai variabel yang dipengaruhi oleh keadaannya saat ini dan keadaan masa depan

b)

Metode untuk memprediksi nilai variabel yang dipengaruhi oleh keadaannya saat ini dan kegiatan sebelumnya

c)

Metode untuk memprediksi nilai variabel yang dipengaruhi hanya oleh keadaannya saat ini

d)

Metode untuk memprediksi nilai variabel yang dipengaruhi oleh keadaannya saat ini dan keadaan sekitarnya

98.

Proses yang dilakukan pada saat penilaian risiko yaitu :

a)

Penetapan Konteks - Analisa Risiko - Penanganan Risiko

b)

Identifikasi Risiko - Analisa Risiko - Evaluasi Risiko

c)

Identifikasi Risiko - Analisa Risiko - Penanganan Risiko

d)

Penetapan Konteks - Analisa Risiko - Evaluasi Risiko

99.

4 kategori penanganan risiko, yakni

a)

Terima, alihkan, kurangi, hindari

b)

Terima, kendalikan, kurangi, hindari

c)

Kendalikan, tangani, terima, hindari

d)

Terima, alihkan, tangani, hindari

100.

Definisi Resiko adalah

a)

bentuk keadaan

ketidakpastian tentang suatu keadaan yang akan terjadi nantinya

b)

bidang ilmu yang membahas tentang bagaimana suatu organisasi menerapkan ukuran

c)

Mampu memberi arah bagi suatu perusahaan dalam melihat pengaruh

d)

manajemen perusahaan melakukan tindakan berupa mengidentifikasi setiap bentuk risiko