6035 | Central Heating LO1 Part 2

Total questions: 14

Worksheet time: 7mins

Name
Class
Date
1.

The open vent to the F&E cistern must rise how far above the water level?

a)

150mm

b)

200mm

c)

450mm

d)

1000mm

2.

The circulator should be located a minimum of _____ below the F&E.

a)

1 metre

b)

2 metres

c)

5 metres

d)

7.5 metres

3.

The British Standards governing the float operated valves is?

a)

BS EN 806

b)

BS 6700

c)

BS 8000

d)

BS 1212

4.

How much does the system water expand by when heated?

a)

4%

b)

10%

c)

1,600 times

d)

0%

5.

The purpose of an air separator is?

a)

To allow close coupled pipework when positioning the cold feed and vent pipe

b)

To compensate for pressure differences when systems are not fully pumped

c)

To allow additional connections when installing the S-plan system

d)

To allow pressure relief when the water has expanded

6.

The maximum distance between the vent pipe and cold feed on a H-frame configuration is?

a)

200mm

b)

175mm

c)

150mm

d)

100mm

7.

What does port A for the three port mid-position valve control?

a)

The flow for the boiler

b)

Central heating

c)

Hot water

8.

A frost thermostat located on vulnerable pipework will override the programmer when it senses temperatures below _____.

a)

0°C

b)

-3°C

c)

5°C

d)

10°C

9.

Statement: The primary vent must terminate over the CWSC due to the chemical inhibitor present in the primaries.

a)

True

b)

False

10.

Which radiator valve would be be considered the valve adjusted by the engineer?

a)

Wheelhead valve

b)

TRV

c)

Remote head

d)

Lockshield valve

11.

To ensure the radiators have been balanced correctly, what temperature difference should there be between flow and return pipework?

a)

0°C

b)

5°C

c)

10°C

d)

15°C

12.

The radiator that heats up last in the system is referred to as?

a)

Principle radiator

b)

Index radiator

c)

Convection radiator

d)

Prefect radiator

13.

The rule of thumb method is referred to as:

a)

The sizing of the CWSC and F&E

b)

The maintenance of primary and secondary waters

c)

The principle of balancing the central heating system

d)

The method of installing radiators to the correct height

14.

In order to allow the air to be released from the system, what is installed at high points in the system?

a)

Automatic bypass valve

b)

Pressure relief valve

c)

Expansion vessel

d)

Automatic air valve