CAPM_Integration

Total questions: 20

Worksheet time: 10mins

Name
Class
Date
1.

The project manager has received a change request from the project sponsor to reduce the budget by 20%. After the project manager has reviewed the change, he decides that the only way this can be done is by removing a part of the project that was not completed yet. Who needs to approve this change?

a)

Project Team

b)

Change Approval Board

c)

Change Management Board

d)

Change Control Board

2.

The CEO of a small business has requested that the company's accounting software be upgraded to better support the financial records. He has requested that the software include a report that can forecast the following month's expenses. Where should the CEO outline why this project needs to get done?

a)

Business Documents

b)

Scope Outline

c)

Scope Statement

d)

WBS

3.

Project manager Mike worked with the sponsor Chris to the get the project charter approved for the new office reorganization project. While reviewing the requirements, both Mike and Chris are sure that there is no need to upgrade the current wireless network in the office. Where is the best place Mile and Chis can store this information?

a)

Project Charter

b)

Business Case

c)

Assumption Documentation

d)

Assumption Log

4.

While working on creating a project management plan, the project manager has brought a group of expert programmers and planners to ensure it is created correctly. What tool best describes this approach?

a)

Meeting

b)

Interpersonal and Team Skills

c)

Data Analysis

d)

Data Gathering

5.

When a project has been executed, what input would best help the project manager determined how to manage changes to the project?

a)

Change Control Plan

b)

Project Management Plan

c)

Change control Board

d)

Change Control Charts

6.

Company XYZ has been executing a new business development project for the last 4 months. Stakeholders have requested several changes to the scope and have gotten them approved. After a change is approved, what is the best next step to conduct on a project?

a)

Execute approved change request in the process : Direct and Manage project Work

b)

Execute approved change request in the process : Monitor and Control project Work

c)

Validate the change request in the Validate scope process

d)

Close the change request in the Close Project or Phase process

7.

A change control board has informed the project manager that a change request made by stakeholder Mark to reduce the schedule of the project by 2 weeks was rejected. What is the first step the project manager should take?

a)

Resubmit the change request

b)

Ask to Mark to change his request to 1 week

c)

Consult the project team to see how to get this change approved

d)

Update the change Log

8.

The deliverable for the product improvement project has been accepted by the sponsor. What should the project manager do next?

a)

Move onto the next phase or project

b)

Release the project team

c)

Move the Close Project or Phase Process

d)

Determine what went wrong or right on this project

9.

While getting ready to manage the project schedule, the project manager would like to document how accurate the schedule must be and what model the team would use to create the schedule. What document would this information be in?

a)

Scope Management Plan

b)

Schedule Management Plan

c)

Schedule Baseline

d)

Schedule Data

10.

In developing the schedule management plan which of the following tools will the project manager use?

a)
  • Data Representation

b)
  • Data Analysis

c)
  • Decision Making

d)
  • Project Management Information System

11.

When developing the cost management plan, which tool or technique would include reviewing the different funding options?

a)
  • Meetings

b)
  • Data Analysis

c)
  • Expert Judgment

d)
  • External Funding

12.

While working on a multinational project, the project manager has decided to represent the project budget in American dollars even though the project will span nine different countries.

This will make it uniform and easier for the stakeholders to understand the budget.

Where will the project manager document the units of measurement for the budget?

a)
  • Cost management plan

b)
  • Funding management plan

c)
  • Units of measurement plan

d)
  • Currency format plan

13.

The project manager has met with the project team to determine when to do the inspections on the project.

The project manager would like to do minimal inspections but still have a high quality product.

Which of the following actions would lead to less inspections and high quality?



a)
  • Well defined requirements

b)
  • Larger budget

c)
  • Implement more preventive actions

d)
  • Conduct more control quality

14.

Which of the following statements about quality management is false?


a)
  • Customer satisfaction is a test of quality

b)
  • It’s cheaper to let customers find defects

c)
  • Prevention leads to less inspections

d)
  • Management is responsible for quality

15.

While managing a project, the project manager needs to be aware of the different types of resources. Equipment, materials, facilities and infrastructure would be considered what type of resources?


a)
  • Team resources

b)
  • Physical resources

c)
  • Personnel resources

d)
  • Location resources

16.

One of the main goals of communications management is to _____ ?

a)
  • Prevent misunderstandings and miscommunications

b)
  • Select the communications method

c)
  • Determine which message to send

d)
  • Collect the stakeholder's requirements

17.

While discussing risk management with a team member, what should the project manager say about the different levels of risk?

a)
  • There are two levels of risk: individual project risks and overall project risks

b)
  • There is only one level of risk: individual project risks

c)
  • There is only one level of risk: overall project risks

d)
  • There two levels of risk: overall project risks and operational risks

18.

When creating a scope baseline, the project manager has decided to include the location of where the work is supposed to take place. Where in the WBS will this information be stored?

a)
  • In each work package on the WBS

b)
  • In each deliverable on the scope statement

c)
  • In each work package on the WBS dictionary

d)
  • On the activity list

19.

When conducting procurement management on a project, what is one of the first things a project manager should research before awarding the contract?

a)
  • Laws and regulations of the country

b)
  • The sponsor requirements

c)
  • What terms and conditions to put in the contract

d)
  • What payment terms to put in the contract

20.

The project manager has begun to identify the stakeholders for the network redesign project.

One person is very vocal about the effects of the project on his role in the organization.

The person feels they will lose their job once the project is complete. Is this person a stakeholder?

a)
  • Yes, since the person is impacted by the project

b)
  • Yes, since the person will gain a new role in the organization

c)
  • No, since the person will not be with the company after the project is done

d)
  • No, since the person is not part of the project team