1.

The following are characteristics of a project except

a)

Complex

b)

Repetitive

c)

Has an established objective

d)

None of the choices

2.

It is a tool used to define and group a project’s discrete work elements in a way that helps organize and define the total work scope.

a)

Work Breakdown Structure

b)

Risk Assessment Matrix

c)

Gantt Chart

d)

PERT-CPM

3.

The following must be considered in estimating cost and time EXCEPT

a)

Adding allowance for risk in each activity

b)

Use of multiple sources for a more accurate estimate

c)

Enough planning horizon to avoid inflation or other changes

d)

None of the choices

4.

A dummy activity is used to describe:

a)

Precedence relationship

b)

Necessary time delays

c)

Resource restrictions

d)

All of the above

5.

The critical path of the network is the:

a)

Shortest path of through the network

b)

Path with the fewest activities

c)

Path with the most activities

d)

Longest time path through the network

6.

CPM with 3-time estimates assumes that the distribution of completion time for a project is

a)

normal

b)

binomial

c)

poisson

d)

exponential

7.

It is to reduce the likelihood that the event will occur.

a)

Risk Sharing

b)

Risk Mitigation

c)

Risk Transfer

d)

Risk Avoidance

8.

IF AN ACTIVITY HAS A ZERO SLACK, IT:

a)

Means the project is expected to be delayed

b)

Must be a dummy activity

c)

Is on the critical path

d)

None of the choices

9.

Which of the following statements concerning a Gantt chart is true?

a)

Gantt charts are particularly helpful for scheduling and planning large projects

b)

Gantt charts are particularly helpful for scheduling and planning project complex precedence relationships.

c)

The Gantt chart indicates where extra time is available and activities can be delayed.

d)

The Gantt chart has been a popular projects scheduling tool but is not widely used now.

10.

Activities on the critical path are critical because they

a)

Represent the maximum project completion time

b)

Cannot tolerate any delay in completion

c)

Represent the most expensive in terms of resources

d)

Represent the largest and most complex activities of the project

11.

Which one is not a key project metric?

a)

effort

b)

cost

c)

time

d)

performance

12.

In a CPM/PERT network, an event refers to

a)

The occurrence of a delay in the project

b)

An activity inserted into the network to show a precedence relationship with no passage of time

c)

The beginning or completion of an activity or project

d)

The earliest an activity can start

13.

Activity definition is a part of what knowledge area?

a)

integration

b)

time

c)

cost

d)

quality

14.

It is accomplishing tasks with the least amount of resources (time, money, equipment/facilities, technology - know-how, procedure, process, skills).

a)

efficiency

b)

effectiveness

c)

productivity

d)

reliability

15.

The CIT-U ETEEAP students had an outreach program on the outskirts of Barangay Labangon last year. The following were the conceptualized activities taken. The school president required the following action plan which was carried out in 15 days.

If you were the project manager of this outreach program, how many days did the CIT-U ETEEAP students make in the fundraising?

a)

3 days

b)

4 days

c)

5 days

d)

6 days

16.

Based on the constructed PERT/CPM network. What was the project completion time?

a)

12 days

b)

13 days

c)

14 days

d)

15 days

17.

Based on the constructed PERT/CPM network. What was the critical path?

a)

A-B-D-E-F-H-I

b)

A-B-D-E-G-I

c)

A-C-E-F-H-I

d)

Both A and C

e)

Both A and B

18.

Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the Outreach Program started?

a)

April 25, 2022

b)

April 26, 2022

c)

April 22, 2022

d)

April 21, 2022

19.

Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the fundraising activity started?

a)

April 14, 2022

b)

April 13, 2022

c)

April 15, 2022

d)

April 16, 2022

20.

Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the fundraising activity ended?

a)

April 15, 2022

b)

April 16, 2022

c)

April 18, 2022

d)

April 19, 2022

21.

Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year.

If you were assigned to the reservation of guest speakers, when did you start this activity?

a)

April 11, 2022

b)

April 12, 2022

c)

April 13, 2022

d)

April 14, 2022

22.

Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When did you start disseminating the information?

a)

April 19, 2022

b)

April 22, 2022

c)

April 21, 2022

d)

April 20, 2022