The following are characteristics of a project except
Complex
Repetitive
Has an established objective
None of the choices
It is a tool used to define and group a project’s discrete work elements in a way that helps organize and define the total work scope.
Work Breakdown Structure
Risk Assessment Matrix
Gantt Chart
PERT-CPM
The following must be considered in estimating cost and time EXCEPT
Adding allowance for risk in each activity
Use of multiple sources for a more accurate estimate
Enough planning horizon to avoid inflation or other changes
None of the choices
A dummy activity is used to describe:
Precedence relationship
Necessary time delays
Resource restrictions
All of the above
The critical path of the network is the:
Shortest path of through the network
Path with the fewest activities
Path with the most activities
Longest time path through the network
CPM with 3-time estimates assumes that the distribution of completion time for a project is
normal
binomial
poisson
exponential
It is to reduce the likelihood that the event will occur.
Risk Sharing
Risk Mitigation
Risk Transfer
Risk Avoidance
IF AN ACTIVITY HAS A ZERO SLACK, IT:
Means the project is expected to be delayed
Must be a dummy activity
Is on the critical path
None of the choices
Which of the following statements concerning a Gantt chart is true?
Gantt charts are particularly helpful for scheduling and planning large projects
Gantt charts are particularly helpful for scheduling and planning project complex precedence relationships.
The Gantt chart indicates where extra time is available and activities can be delayed.
The Gantt chart has been a popular projects scheduling tool but is not widely used now.
Activities on the critical path are critical because they
Represent the maximum project completion time
Cannot tolerate any delay in completion
Represent the most expensive in terms of resources
Represent the largest and most complex activities of the project
Which one is not a key project metric?
effort
cost
time
performance
In a CPM/PERT network, an event refers to
The occurrence of a delay in the project
An activity inserted into the network to show a precedence relationship with no passage of time
The beginning or completion of an activity or project
The earliest an activity can start
Activity definition is a part of what knowledge area?
integration
time
cost
quality
It is accomplishing tasks with the least amount of resources (time, money, equipment/facilities, technology - know-how, procedure, process, skills).
efficiency
effectiveness
productivity
reliability
The CIT-U ETEEAP students had an outreach program on the outskirts of Barangay Labangon last year. The following were the conceptualized activities taken. The school president required the following action plan which was carried out in 15 days.
If you were the project manager of this outreach program, how many days did the CIT-U ETEEAP students make in the fundraising?
3 days
4 days
5 days
6 days
Based on the constructed PERT/CPM network. What was the project completion time?
12 days
13 days
14 days
15 days
Based on the constructed PERT/CPM network. What was the critical path?
A-B-D-E-F-H-I
A-B-D-E-G-I
A-C-E-F-H-I
Both A and C
Both A and B
Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the Outreach Program started?
April 25, 2022
April 26, 2022
April 22, 2022
April 21, 2022
Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the fundraising activity started?
April 14, 2022
April 13, 2022
April 15, 2022
April 16, 2022
Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When was the fundraising activity ended?
April 15, 2022
April 16, 2022
April 18, 2022
April 19, 2022
Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year.
If you were assigned to the reservation of guest speakers, when did you start this activity?
April 11, 2022
April 12, 2022
April 13, 2022
April 14, 2022
Based on the constructed GANTT CHART. Supposed Activity A started on April 8, 2022, Friday. The work schedule is from Mondays to Saturdays. Assuming there were no holidays for the month of April last year. When did you start disseminating the information?
April 19, 2022
April 22, 2022
April 21, 2022
April 20, 2022