wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Soundness Testing Quiz

Total questions: 54

Worksheet time: 27mins

Name
Class
Date
1.

What should be checked during the visual inspection before soundness testing?

a)

Open ends, soldered joints made, compression joints tight, clips are in place

b)

Open ends, soldered joints made, compression joints loose, clips are missing

c)

Closed ends, soldered joints made, compression joints tight, clips are in place

d)

Open ends, unsoldered joints, compression joints tight, clips are in place

2.

What is the next step after the visual inspection in soundness testing?

a)

Conducting a pressure test

b)

Carrying out the soundness test

c)

Performing a leak test

d)

Conducting a flow test

3.

What types of pipes require different soundness tests?

a)

Rigid pipe (copper and steel) and plastic pipe

b)

Flexible pipe and plastic pipe

c)

Rigid pipe (copper and steel) and flexible pipe

d)

Copper pipe and steel pipe

4.

What is the first step in the testing and decommissioning process?

a)

Set up equipment

b)

Visual inspection

c)

Test period

d)

Final check

5.

Which step comes immediately after setting up the equipment in the testing and decommissioning process?

a)

Visual inspection

b)

Final check

c)

Test period

d)

Complete documentation

6.

What is the final step in the testing and decommissioning process?

a)

Final check

b)

Test period

c)

Complete documentation

d)

Visual inspection

7.

What is the first step in the soundness testing of rigid pipes (copper and steel)?

a)

Walk around the system and check for leaks

b)

Slowly fill the system with water

c)

Attach the hydraulic test bucket

d)

Pump system up to 1.5 times the working pressure

8.

How long should the system be left to stand for temperature stabilization during soundness testing?

a)

15 minutes

b)

45 minutes

c)

30 minutes

d)

60 minutes

9.

What should be done if the system works at 3 bar during soundness testing?

a)

Test it at 3 bar

b)

Test it at 4.5 bar

c)

Test it at 6 bar

d)

Test it at 1.5 bar

10.

What should be checked after leaving the system for one hour during soundness testing?

a)

Temperature increase

b)

Water level

c)

Pressure drop

d)

Pipe material

11.

What should be done if a pressure drop is detected during soundness testing?

a)

Increase the pressure

b)

Rectify and re-test

c)

Decrease the pressure

d)

Ignore and proceed

12.

What is the first step in Test A for soundness testing of a plastic pipe (polybutylene)?

a)

Walk around the system and check for leaks

b)

Pump system to 1 bar

c)

Slowly fill the system with water

d)

Increase pressure to 1.5 times working pressure

13.

How long should you wait after pumping the system to 1 bar before checking for loss of pressure?

a)

15 minutes

b)

30 minutes

c)

45 minutes

d)

60 minutes

14.

To what pressure should the system be increased for 15 minutes during Test A?

a)

1 bar

b)

1.5 times working pressure

c)

2 times working pressure

d)

0.5 times working pressure

15.

What should be done after reducing the pressure to one-third for a further 45 minutes?

a)

Walk around the system and check for leaks

b)

Increase pressure to 1.5 times working pressure

c)

Check for pressure loss

d)

Slowly fill the system with water

16.

What is the main reason for not wanting to damage the plastic pipe or O rings during Test A?

a)

To save time

b)

To ensure the system is sound

c)

To avoid additional costs

d)

To prevent water wastage

17.

What is the first step in Test B for soundness testing of a plastic pipe (polybutylene)?

a)

Walk around system and check for leaks

b)

Pump system to manufacturer’s test pressure

c)

Slowly fill the system with water

d)

Inspect the pressure loss after 30 minutes

18.

How long should you leave the system after inspecting the pressure loss for the first time in Test B?

a)

30 minutes

b)

60 minutes

c)

90 minutes

d)

120 minutes

19.

What should you do if the total pressure loss is less than 0.2 bar in Test B?

a)

Refill the system with water

b)

Soundness is good

c)

Check for leaks again

d)

Increase the test pressure

20.

Why is it important not to damage the plastic pipe or O rings during Test B?

a)

To ensure accurate pressure readings

b)

To prevent water contamination

c)

To avoid system malfunction

d)

To maintain system integrity

21.

What is the first step in the flushing and disinfecting process after a new system or section of pipework has been installed?

a)

Re-fill the system

b)

Open the kitchen tap

c)

Add disinfectant to the system

d)

Re-fill the system with water and then drain down from the lowest point

22.

How long should disinfectant be added to the system according to BS6700?

a)

30 minutes

b)

1 hour

c)

2 hours

d)

3 hours

23.

Which of the following is NOT a step in the flushing and disinfecting process?

a)

Re-fill the system

b)

Open the kitchen tap and allow water to run until clear of debris/colour

c)

Add disinfectant to the system for 1 hour

d)

Leave the system empty for 24 hours

24.

What is the first step in the flushing and disinfecting process according to the provided material?

a)

Drain system

b)

Test chlorine levels at each outlet

c)

Flush system through from each outlet until no chlorine is present

d)

Add chlorine to the system

25.

According to the provided material, what standard is referenced for testing chlorine levels?

a)

BS6700

b)

ISO9001

c)

ANSI/NSF 61

d)

EPA 810

26.

What should be done after draining the system in the flushing and disinfecting process?

a)

Add more chlorine

b)

Test chlorine levels at each outlet

c)

Flush system through from each outlet until no chlorine is present

d)

Close all outlets

27.

What tool is used to check the flow rate according to the provided learning material?

a)

Pressure gauge

b)

Wier cup

c)

Thermometer

d)

Hydrometer

28.

How should dirt and debris be flushed through according to the provided learning material?

a)

Using a pressure gauge

b)

As per BS6700

c)

With a thermometer

d)

Using a hydrometer

29.

What should be done to all draw-off points during testing and decommissioning?

a)

Measure the temperature

b)

Check the flow rate

c)

Open all draw-off points, making sure they open and shut off

d)

Measure the pressure

30.

What tool is used to check the pressure according to the provided learning material?

a)

Wier cup

b)

Thermometer

c)

Pressure gauge

d)

Hydrometer

31.

What should be done to all valves during testing and decommissioning?

a)

Ensure correct temperature is set and recorded

b)

Open and close all valves to ensure operation and label all valves

c)

Ensure correct temperature setting and inform customer

d)

Ensure correct temperature at draw-off points

32.

What is the purpose of checking blending valves during testing and decommissioning?

a)

Ensure correct temperature setting and inform customer

b)

Ensure correct temperature at draw-off points

c)

Ensure correct temperature is set and recorded

d)

Open and close all valves to ensure operation and label all valves

33.

What should be ensured about thermostats during testing and decommissioning?

a)

Ensure correct temperature is set and recorded

b)

Open and close all valves to ensure operation and label all valves

c)

Ensure correct temperature setting and inform customer

d)

Ensure correct temperature at draw-off points

34.

What should be ensured about temperatures during testing and decommissioning?

a)

Ensure correct temperature setting and inform customer

b)

Ensure correct temperature at draw-off points

c)

Ensure correct temperature is set and recorded

d)

Open and close all valves to ensure operation and label all valves

35.

What should be done after the system has been proved?

a)

Disassemble the system

b)

Complete the documentation and hand over to the customer

c)

Ignore the system

d)

Reinstall the system

36.

What should be shown to the customer during the handover of the system?

a)

Only the settings

b)

Only the valves

c)

All the settings and valves

d)

None of the settings and valves

37.

Which of the following is NOT mentioned as part of the documentation to be handed over to the customer?

a)

Manufacturer’s instructions

b)

Benchmark certificate

c)

Warranty

d)

User manual

38.

Which of the following is the first step in decommissioning a hot water system for maintenance and replacement of components?

a)

Components identified

b)

Heat source safely isolated

c)

Customer informed

d)

Fuses removed

39.

What should be done to the heat source during the decommissioning of a hot water system?

a)

Components identified

b)

Heat source safely isolated

c)

System drained to safe location

d)

Open ends capped

40.

Which of the following actions ensures safety by preventing accidental re-energization of the system?

a)

Warning notice placed on heat source

b)

Fuses removed

c)

System drained to safe location

d)

No dead legs left

41.

What is the purpose of placing a warning notice on the heat source during decommissioning?

a)

To inform the customer

b)

To identify components

c)

To ensure the heat source is safely isolated

d)

To cap open ends

42.

What should be done to the system to ensure it is safe to work on and no water remains in the pipes?

a)

Components identified

b)

System drained to safe location

c)

Open ends capped

d)

No dead legs left

43.

What is the first step when a system is temporarily decommissioned for a component replacement?

a)

The system is refilled and tested

b)

The part is replaced

c)

The customer will have to be informed

d)

A hose pipe is connected to a suitable drain point

44.

What must be done to the system before it is labeled during decommissioning?

a)

The system is refilled and tested

b)

The system will be safely isolated

c)

The part is replaced

d)

The customer will have to be informed

45.

Where is the hose pipe connected during the decommissioning process?

a)

To a suitable drain point

b)

To the main water supply

c)

To the system's main valve

d)

To the customer's water outlet

46.

What happens after the part is replaced in the decommissioning process?

a)

The system is safely isolated

b)

The system is refilled and tested

c)

The customer is informed

d)

The hose pipe is connected

47.

Which of the following items may need periodic maintenance or replacement, leading to temporary system decommissioning?

a)

Hot water cylinder

b)

Electrical wiring

c)

Insulation material

d)

Paint

48.

Which of the following is NOT listed as a common item that may need periodic maintenance or replacement?

a)

Boiler

b)

Shower

c)

Valves

d)

Electrical outlets

49.

What is one of the common items that may need periodic maintenance or replacement, causing the system to be temporarily decommissioned?

a)

Cold water storage cistern

b)

Light bulbs

c)

Carpeting

d)

Windows

50.

Which of the following items is included in the list of common items that may need periodic maintenance or replacement?

a)

Terminal fitting

b)

Wallpaper

c)

Furniture

d)

Flooring

51.

When is a system permanently decommissioned?

a)

When a new system is installed alongside the old system

b)

When an old system is stripped out and replaced by an updated system

c)

When the system is temporarily shut down

d)

When the system is moved to a different location

52.

What must be done to the system during decommissioning?

a)

The system will be upgraded

b)

The system will be safely isolated and labeled

c)

The system will be expanded

d)

The system will be painted

53.

What is connected to a suitable drain point during decommissioning?

a)

A water pipe

b)

A gas pipe

c)

A hose pipe

d)

An electrical wire

54.

Who needs to be informed during the decommissioning process?

a)

The system manufacturer

b)

The customer

c)

The government

d)

The neighbors