WorksheetsProject/Maintenance Management Q2
Total questions: 5
Worksheet time: 3mins
Name
Class
Date
1.
What is the SLACK for this activity B?
a)
7
b)
3
c)
1
2.
What is the FLOAT of an ACTIVITY in CRITICAL PATH?
a)
2
b)
1
c)
0
3.
Which of the following is/are TRUE for a CRITICAL Path?
(i) Is the LONGEST PATH of the network
(ii) Is the EARLIEST COMPLETION DATE of the project
(iii) Is the path where all activities have ZERO FLOAT
a)
i and ii
b)
i and ii
c)
i, ii, and iii
4.
What is the CRITICAL PATH of this project?
a)
1-2-3-4-5-6
b)
1-2-4-5-6
c)
1-2-3-5-6
5.
The team monitors resources, costs, quality, and budgets. It also revises or changes plans and shifts resources to meet time and cost demands
a)
PLANNING
b)
SCHEDULING
c)
CONTROLLING
100 %