PART VII - DRAINAGE STRUCTURES

Total questions: 19

Worksheet time: 11mins

Name
Class
Date
1.

IT IS MEANT TO STABILIZE THE FOUNDATION BED TO AVOID ANY POSSIBLE SETTLEMENT THAT MIGHT IMPAIR THE FUNCTION OF THE DRAINAGE STRUCTURE AND ALSO TO SERVE AS A UNIFORM CUSHION TO THE CULVERT

(a)  

2.

IF THE UNDERLYING SOIL AT THE DESIGNED BOTTOM GRADE OF THE CULVERT IS COMPOSED OF SUITABLE MATERIAL, IT SHOULD BE REMOVED REMOVED AND SUBSTITUTED WITH GRANULAR FILL COMPOSED OF SAND OR SANDY SOIL.

a)

TRUE

b)

FALSE

3.

NORMAL THICKNESS OF FOUNDATION FILL

a)

20 cm

b)

25 cm

c)

22 cm

d)

20 mm

4.

WHAT CAN BE USED TO SPREAD MANUALLY THE FOUNDATION FILL UNTIL THE WHOLE FOUNDATION BED IS COVERED, AS REQUIRED? (SELECT AS MANY)

a)

RAKES

b)

SHOVEL

c)

COMPACTOR

d)

SCRAPERS

5.

FOR _ CULVERTS, THE LAYERS ARE OF UNIFORM FLAT THICKNESS.

a)

BOX

b)

PIPE

c)

CIRCULAR

6.

______ ARE INSTALLED IN THE ORIGINAL STREAMBED WITH THEIR GRADES AND FLOW LINE CONFORMING TO THE NATURAL CHANNEL OR CANAL..

a)

BOX

b)

PIPES

c)

CIRCULAR

7.

WHICH IS TRUE IN THE STATEMENTS GIVEN?

a)

FOR BOX CULVERTS, THE BEDDING IS SHAPED SO THAT THE BOTTOM OF THE PIPE WILL BE IN CONTACT THROUGHOUT ITS FULL LENGTH.

b)

FOR CIRCULAR PIPES, THE BEDDING IS SHAPED SO THAT THE BOTTOM OF THE PIPE WILL BE IN CONTACT THROUGHOUT ITS FULL LENGTH.

8.

IT CAN BE DONE WITH HAND OR MECHANICAL EQUIPMENT CAREFULLY DONE TO ENSURE A THOROUGHLY TAMPED FOUNDATION FILL.

a)

COMPACTION

b)

EXCAVATION

c)

EMBANKMENT

9.

WHAT IS THE CORRECT ORDER PROCESS OF R.C. BOX CULVERT CONSTRUCTION PHASES

a)

CULVERT BASE - SIDE AND INNER WALLS - CULVERT SLAB

b)

SIDE AND INNER WALLS - CULVERT BASE - CULVERT SLAB

c)

CULVERT BASE - CULVERT SLAB - SIDE AND INNER WALLS

10.

WHAT IS THE CORRECT ORDER PROCESS OF R.C. PIPE CULVERT CONSTRUCTION PHASES

a)

INSTALLATION OF PIPE - COLLARING OF RC PIPES - BACKFILLING

b)

INSTALLATION OF PIPE - BACKFILLING - COLLARING OF RC PIPES

c)

COLLARING OF RC PIPES - INSTALLATION OF PIPE - BACKFILLING

11.

IN THE INSTALLATION OF RC PIPES, LAYING BEGINS AT _________ END OF THE CULVERT LINE TO USE GRAVITY IN PROPERLY INSTALLING THE PIPES.

a)

DOWNSTREAM

b)

UPSTREAM

12.

GROOVE ENDS ARE PLACED SUCH THAT THE PIPE ENDS FIT AS ITS NEAREST ENDS.

a)

TRUE

b)

FALSE

13.

_______ SEGMENT OF EACH PIPE SHOULD BE IN CONTACT WITH THE SHAPE OF THE BEDDING THROUGHOUT ITS FULL LENGTH.

a)

LOWER

b)

UPPER

14.

IN COLLARING OF RC PIPES, MORTAR PROPORTION IS ______ WITH ENOUGH WATER TO OBTAIN THE DESIRED CONSISTENCY.

a)

1:2

b)

2:1

c)

1:1

d)

2:2

15.

IN COLLARING THE RC PIPES, THE ______ IS TO FORM THE CONTINUOUS BEAD AROUND THE OUTSIDE THE PIPE.

a)

COLLAR

b)

SIDE WALLS

c)

BAKFILLING

16.

IN COLLARING THE RC PIPES, THE ______ OF PIPE IS FINISHED SMOOTH.

a)

INSIDE

b)

OUTSIDE

c)

HOLLOW

17.

BACKFILL ARE PLACED AND COMPACTED IN LAYERS NOT EXCEEDING ____ ON BOTH SIDES UP TO AN ELEVATION OF _____ ABOVE THE TOP OF THE CULVERT.

a)

15 cm , 30 cm

b)

30 cm , 15 cm

c)

15 cm , 20 cm

d)

10 cm , 30 cm

18.

(a)   MAYBE DONE MANUALLY USING RAKES AND SHOVELS AT A THIN LAYER WHICH IS MOST IDEAL TO PRODUCE EASY COMPACTION OF MATERIAL DONE USING HANAD TAMPERS TO INSURE A THOROUGHLY TAMPED BACKFILL.

19.

AFTER BACKFILLING, PIPE CULVERTS ARE PROTECTED BY PROVIDING EXTRA FILL AS COVER BEFORE ANY HEAVY EQUIPMENT IS PERMITTED TO CROSS DURING THE CONSTRUCTION OF THE ROADWAY TO PROTECT THE JOB FROM POSSIBLE DAMAGE BY EXCESSIVE LOADS.

a)

TRUE

b)

FALSE