wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Revision Chapter 1 and 2

Total questions: 15

Worksheet time: 7mins

Name
Class
Date
1.

What is a key responsibility of the Quantity Surveyor (QS) during the post-contract award phase?

a)

Submit building plans for approval

b)

Evaluate interim payment, manage variation, prepare final account

c)

Coordinating the contract document

d)

Prepare progress claim, warranty, handing over documents

2.

Which statement best distinguishes Contract Management (CM) from Project Management (PM)?

a)

CM relevant during pre-contract phase before work begins, PM post contract

b)

CM focus on administration of legal agreement, PM from inception to completion

c)

PM delas with finance and scheduling, CM control quality and performance

d)

PM focus on contructing a physical work, CM focue only on documentation

3.

What is the main role of the One Stop Centre (OSC)?

a)

Managing on-site construction activities

b)

Provide financial support and funding

c)

Coordinate and streamline submission and approval of development application

d)

Oversee procurment and supply construction material for goverment project

4.

In a Build, Operate, and Transfer (BOT) procurement model, what is the final step of the process?

a)

Private entity own and operate the facility

b)

Facility is sold to third party, profit shared between government and private

c)

Government purchase faility from the private entity

d)

Private entity hands the completed and operational to the government

5.

Who is the Nominated Sub-Contractor?

a)

Contractor has a direct contract with project owner, separate from main contract

b)

Specialist contractor chosen by client, contract with main contractor

c)

Contractor chosen by main contractor to carry out part of work

d)

Specialist contractor chosen by main contractor, contract with client

6.

In a traditional project lifecycle, which of the following activities occurs during the Pre-Contract Phase?

a)

Main contractor taking posession of the site and mobilizing resources

b)

Evaluate tender submission from contractors and awarding the contract

c)

Rectifying defect identifies during the liability period

d)

Issue interim payment certificate to the contractor

7.

What is the primary purpose of contract management?

a)

To ensure that construction materials are purchased on time

b)

To design and monitor only the project’s technical aspects

c)

To manage the legal agreement between parties and ensure obligations are fulfilled efficiently and fairly

d)

To supervise site workers during construction

8.

Why is the feasibility study considered a crucial stage in the inception phase of a project?

a)

Reduces cost by eliminating the need for professional consultants

b)

Determines project viability from technical and economic perspectives

c)

Allows immediate commencement of construction work

d)

Serves primarily as a marketing document for investors

9.

The procurement method in construction refers to:

a)

Process and strategy of acquiring a built facility from initiation to handover

b)

Process of selecting consultants for project design

c)

Method of project payment during construction

d)

Design stages before tendering

10.

In the Traditional (Design-Bid-Build) procurement method, which statement is true?

a)

Design and construction are carried out by a single entity

b)

Construction can begin before design completion

c)

The contractor has major control over the project design

d)

The design and construction phases are separated and sequential

11.

The Construction Management (CM) approach is most suitable for:

a)

Small projects with simple design

b)

Projects requiring strict separation between designer and builder

c)

Large and complex projects requiring flexibility and early start

d)

Projects where the owner has limited involvement

12.

In a Lump Sum Contract (Fixed Price), the contractor:

a)

Is reimbursed based on actual cost plus fee

b)

Bears the risk of cost overruns due to estimation errors

c)

Is paid based on unit rates for completed work

d)

Can revise the price freely during construction

13.

Which type of lump sum contract is most suitable for large and complex projects with complete design and detailed measurements?

a)

Based on drawings and specifications

b)

Based on the Bill of Quantities (BQ)

c)

Based on the Schedule of Rates

d)

Measure and Value Contract

14.

The Measure and Value Contract is best used when:

a)

The full project scope is known and fixed

b)

The project has repetitive maintenance works

c)

The client wants cost certainty from the start

d)

The project require confidentiality and flexibility

15.

A private developer partners with the government to design, finance, build, and operate a toll highway before handing it back after 30 years. Which model applies?

a)

Build-Lease-Transfer (BLT)

b)

Public Finance Initiative (PFI)

c)

Build-Operate-Transfer (BOT)

d)

Built-Own-Operate-Transfer (BOOT)