1.

What is the primary purpose of "Determination of Employment" in construction contracts?

a)

To enable the contractor to claim additional payments

b)

To terminate the contract for minor breaches

c)

To provide a mechanism for addressing serious breaches of contract

d)

To bypass legal procedures for resolving disputes

2.

Under what circumstances can a construction contract be discharged?

a)

Completion of the project

b)

By breach, agreement, or consent

c)

When the employer delays payment

d)

By non-payment of liquidated damages

3.

Which of the following is NOT a contractor default under Clause 25.1?

a)

Failure to commence the works

b)

Persistent refusal to comply with Architect’s Instructions

c)

Delays caused by force majeure

d)

Abandonment of the works

4.

What must the employer prove to invoke Clause 25.1(a) for failure to commence works?

a)

The contractor failed to submit progress reports

b)

The contractor lacked reasonable cause for failing to start works

c)

The contractor delayed in submitting the work program

d)

The contractor requested an extension of time

5.

What does "reasonable cause" mean in the context of Clause 25.1(b) regarding suspension of work?

a)

Employer's consent to suspend work

b)

Circumstances beyond the contractor’s control

c)

Delays in payment by the subcontractor

d)

Poor performance of workers

6.

What is the most common ground for determination under Clause 25.1(c)?

a)

Failure to provide adequate manpower

b)

Failure to proceed regularly and diligently

c)

Failure to submit claims on time

d)

Failure to remove defective works

7.

Which of the following is NOT considered a failure to proceed regularly and diligently?

a)

Removing labor and plant from the site

b)

Falling significantly behind schedule

c)

Adjusting the work program without notifying the architect

d)

Missing the contract Completion Date

8.

What is the first step in the determination process under Clause 25.2?

a)

Issuance of the determination notice

b)

Issuance of a default notice specifying the contractor's breach

c)

Termination of the contractor’s employment

d)

Hiring a replacement contractor

9.

How many days must the contractor be given to remedy a default after receiving a default notice?

a)

7 days

b)

10 days

c)

14 days

d)

28 days

10.

What should the termination notice include?

a)

The contractor’s progress reports

b)

The date of site handover

c)

Details of the default and the employer’s decision to terminate

d)

A list of potential replacement contractors

11.

After determination, what must the contractor do under Clause 25.4(a)?

a)

Provide a new work program

b)

Immediately vacate the site and cease work

c)

Compensate the employer for all incurred costs

d)

Submit claims for additional costs

12.

What rights does the employer have after determining the contractor’s employment?

a)

To stop all work indefinitely

b)

To complete the works through another contractor or departmentally

c)

To withhold all remaining payments indefinitely

d)

To assign all works to subcontractors

13.

If the contractor disputes the default notice issued under Clause 25.2, what is the next step in the determination process?

a)

The employer must immediately issue the termination notice

b)

The contractor must submit evidence to justify their position

c)

The employer must appoint an arbitrator to resolve the dispute

d)

The contractor is required to vacate the site immediately

14.

What must the employer prove to invoke Clause 25.1(e) regarding subcontracting defaults?

a)

Subcontracting was limited to labor-only services

b)

Subcontracting involved substantial works without prior consent

c)

Subcontracting was for minor tasks

d)

The subcontractor failed to submit a performance bond

15.

What constitutes abandonment of works under Clause 25.1(f)?

a)

Temporary stoppage due to adverse weather

b)

Total cessation of all works without due cause

c)

Delays in material delivery

d)

Temporary removal of labor from the site

16.

What evidence can support claims of abandonment?

a)

Architect’s report on defective works

b)

Contractor’s removal of all resources from the site

c)

Revised project timelines

d)

Employer’s delay in issuing payments

17.

When does the employer lose the right to determine a contractor’s employment?

a)

After issuing a default notice

b)

Upon issuance of the Completion Certificate

c)

Upon failure to assign a new contractor within 28 days

d)

After the defects liability period ends

18.

What is the employer’s obligation regarding temporary buildings after determination?

a)

To permit their continued use by the new contractor

b)

To request their removal by the contractor

c)

To use them for project storage

d)

To demolish them immediately

19.

What happens to the contractor’s financial claims after determination?

a)

The contractor is entitled to all outstanding payments

b)

The employer is relieved of any obligation to make further payments

c)

The contractor must pay penalties for all defaults

d)

All claims are resolved immediately in court

20.

Which case supports that the contractor could not be allowed to stay and continue work at site after his employment had been determined under the contract by Employer

a)

Kong Wah Housing Development SB v Desplan Construction Trading SB

b)

Arab Malaysian Corp Builders SB v ASM Development SB

c)

Fernbrook Trading Co Ltd v Taggart

d)

Jackson v Eastbourne Local Board