WorksheetsConstruction Project Quiz
Total questions: 20
Worksheet time: 10mins
Which type of project would a private domestic client commission?
Office block.
House extension.
Shopping mall.
Leisure centre.
Which factor would a commercial client consider before choosing a contractor for a project?
Construction company has a modern image.
The managers and supervisors are well paid.
All skilled workers have brand new equipment.
A reputation for successful contract completion.
What is the purpose of Approved Document ‘A’ in the Building Regulations?
To ensure the appearance of the building is acceptable.
To confirm the structural integrity and safety of buildings.
To safeguard efficient broadband installation.
To guarantee the client brief is fully satisfied.
What does the term ‘retrofit’ mean?
Changing the design before work starts.
Including items as construction proceeds.
Adding something later to a completed project.
Removing an installation from a finished building.
Which project description applies when a factory unit is constructed?
Recreational.
Residential.
Industrial.
Leisure.
What type of community development project can be described as infrastructure?
Social housing.
Local transport.
Healthcare provision.
Educational establishments.
The term ‘utilities’ applies to which part of the built environment?
Retail park.
Sports stadium.
Gas service distribution.
Online shopping warehouse.
What is another term for the modular construction method?
Volumetric.
Immersive.
Panelised.
Mechanical.
What does the term ‘integration’ mean when applied to a supply chain?
Partners in the supply chain closely collaborate when planning a project.
Partners in the supply chain use their equipment resources separately.
Partners in the supply chain make sure they maximise individual profit.
Partners in the supply chain monitor each other to maintain skill levels.
Which term describes how ordering, storing, and using materials on site is controlled?
Organisational structure.
Integrated systems.
Inventory management.
Change management.
What document is issued by an architect to authorise a change request during construction?
Variation order.
Purchase order.
Requisition order.
Inspection order.
For which type of procurement route is a specific company team provided to develop the project concept?
Fast track.
Contractor led.
Lump sum price.
Two stage tender.
Which construction professional would plan and oversee the building of a bridge and its roadways?
Contracts manager.
Structural engineer.
Civil engineer.
Facilities manager.
What are the roles and responsibilities of a building services engineer?
Designs and installs electrical, heating and ventilation systems.
Creates the concept and design of the project to match the client brief.
Sustains safety and efficiency within the built environment.
Manages the contracts made as part of the delivery of a project.
What do the letters CPD stand for in relation to construction professions?
Continuing Personal Development.
Constant Personal Development.
Continuing Professional Development.
Constant Professional Development.
Which event would be recorded in a building passport?
Change of government.
Change in company profits.
Change of ownership.
Change in interest rates.
Which BIM term refers to the central source of digital information used throughout the lifecycle of a building?
Employer information requirements.
Asset information model.
Document management system.
Common data environment.
In a BIM system, what specific purpose is the Digital Plan of Work (DPoW) used for?
Standardising methods for creating, naming, and communicating information.
Providing information about what is required, when it is required and who provides it.
Setting out information required by the employer during the construction phase.
Providing role descriptions for those responsible for managing information.
In the acronym PESTLE, what does the letter ‘T’ stand for?
Technical.
Technographic.
Technological.
Technophobic.
Which term is used in the tendering process?
Metadata.
Curtailment.
Client need.
Prime cost.