2391 Inspection & Testing Questions

Total questions: 40

Worksheet time: 1hrs 5mins

Name
Class
Date
1.

OSG gives the maximum stable value of Ze for a TT installation as:

a)

1660 ohms

b)

600 ohms

c)

200 ohms

d)

100 ohms

2.

Which type of earthing system relies on a separately supplied earth, usually the sheathing on the cable?

a)

TT

b)

TN-C-S

c)

IT

d)

TN-S

3.

Which of the following would not be one of the human senses to use during the initial verification of an addition to a lighting circuit:

a)

Sight

b)

Hearing

c)

Taste

d)

Touch

4.

On a standard TT installation, the result of the resistance of the earth electrode and the rated RCD residual operating current should not exceed:

a)

25V

b)

50V

c)

110V

d)

400V

5.

Which of the following protection devices is unlikely to be suited for short circuit currents in the region of 6kA:

a)

BS 3036 semi-enclosed fuse

b)

BS 88-3 cartridge fuse

c)

BS 88-2 general purpose fuse

d)

BS EN 60898 circuit breaker

6.

The term given to the person responsible for an electrical system is the:

a)

Competent person

b)

Electrician

c)

Duty holder

d)

Company manager

7.

Regional electricity companies quote a maximum likely value of external loop impedance (outside the consumer's installation) for a TN-S system as:

a)

0.35 ohm

b)

0.8 ohm

c)

21 ohm

d)

200 ohm

8.

EAWR states that working live is acceptable unless:

a)

Suitable tools are used

b)

Suitable PPE is worn

c)

It is reasonable in all circumstances for it to be dead

d)

An engineer gives you permission

9.

Overloaded windings on a 3 phase motor may be identified in the first instance by using which sense:

a)

Sight

b)

Smell

c)

Touch

d)

Taste

10.

Which of the following earthing systems has the path for earth leakage currents via the earth itself:

a)

TN-S

b)

TNC-S

c)

TN-C

d)

TT

11.

Which of the following is the correct voltage for carrying out an insulation resistance test on a 400V three-phase circuit terminated at an isolator?

a)

250 V

b)

400 V

c)

500 V

d)

1000 V

12.

A continuity test is to be carried out and the instrument has been confirmed as being in calibration and undamaged. Which of the following is the remaining check that needs to be carried out to confirm the instrument is suitable to use?

a)

Check the battery level

b)

Verify the test leads

c)

Inspect the display screen

d)

Ensure the correct settings are selected

13.

Which of the following is the minimum short circuit test current for a low resistance ohmmeter?

a)

50 mA

b)

100 mA

c)

200 mA

d)

300 mA

14.

In addition to calibration which of the following should be carried out and recorded?

a)

Regular conformation of the instrument`s compliance with BS 7671

b)

Extension of the instrument warranty period

c)

Regular instrument accuracy checks

d)

Closed circuit voltage checks

15.

Which of the following is the maximum voltage above which test leads must comply with the requirements of GS 38?

a)

25 V a.c.

b)

25 V d.c.

c)

50 V a.c.

d)

50 V d.c.

16.

During initial verification of a TN system the installation earth conductor was recorded as 16mm2. The minimum size of main bonding conductor should be:

a)

4mm2

b)

6 mm2

c)

10 mm2

d)

16 mm2

17.

Which of the following is not permitted for use as an earth electrode:

a)

Underground structural metalwork

b)

Metal water mains pipes

c)

Lead sheaths of cables

d)

Earth plates

18.

Which one of the following does not need to be checked for compliance during the visual inspection of an installation:

a)

presence of fire barriers

b)

correct connection of the supply authority's fuse

c)

routing of cables in safe zones

d)

connection of single pole devices in line conductors only

19.

End-to-end resistance checks would be carried out on a:

a)

radial circuit

b)

lighting circuit

c)

ring final circuit

d)

fused connection unit

20.

The purpose of the test button of a residual current device is to check the:

a)

Earth fault loop impedance

b)

Continuity of the earthing conductor

c)

Earth electrode resistance

d)

Mechanical operation of the rcd

21.

Given the following numbered tests, select the sequence in which these tests should be conducted for a new installation:- 1. functional 2. insulation resistance 3. polarity 4. continuity of final ring conductors 5. continuity of protective conductors

a)

1,3,4,5,2

b)

4,5,3,2,1

c)

5,4,2,3,1

d)

2,3,4,5,1

22.

Table 9A in the On Site Guide gives a value of 19.51 (mohm/m) for a line conductor of 2.5mm2 and a protective conductor of 1.5mm2. What would be the resistance of a circuit 25m in length when wired using these conductors?

a)

4.87 ohm

b)

487 ohm

c)

780 ohm

d)

0.487 ohm

23.

Which of the following tests would be carried out 'live'?

a)

Insulation Resistance

b)

Earth Continuity

c)

A Megger Test

d)

Functional testing

24.

An approved voltage tester can be used to:

a)

Establish whether a circuit conductor is live or not

b)

Determine the effectiveness of a disconnection device

c)

Measure the resistance of an earth continuity conductor

d)

Carry out continuity tests

25.

Which of the following does not form part of the earth fault loop impedance:

a)

The phase conductor

b)

The earth electrode

c)

The cable armouring

d)

The neutral within the consumer's installation

26.

An earth fault loop impedance tester should only allow current to flow for:

a)

0.4s

b)

4.0s

c)

40ms

d)

400ms

27.

A 100mA RCD protecting a TT installation tested at half the rated tripping current should:

a)

Not operate

b)

Operate within 50ms

c)

Operate within 100ms

d)

Operate within 300ms

28.

Which of the following requirements from GS 38 applies to test equipment which requires more than one test lead?

a)

The leads must be at least 1m in length

b)

The leads must have a csa of at least 1.5 mm2

c)

The leads must be colour coded for identification

d)

The leads must be permanently attached to the instrument

29.

Which of the following correctly describes the purpose of a continuity of ring final circuit conductors test?

a)

To confirm the conductors are installed as a complete ring

b)

To confirm polarity is correct at each point on the circuit

c)

To determine the R1+R2 value for the final circuit

d)

To confirm the conductors are the correct csa

30.

A test for continuity of circuit protective conductors is carried out at every point on a circuit. Which of the following describes the purpose of this test?

a)

To confirm correct polarity

b)

To confirm the conductors are correct csa

c)

To determine the R1+R2 value for the circuit

d)

To confirm exposed conductive parts are connected to the MET

31.

Which of the following factors directly affects the conductor resistance of a cable?

a)

Insulation and csa

b)

Length and csa

c)

Length and insulation

d)

Load current and csa

32.

Two identical cables are connected in parallel. Which of the following describes the effect on the combined conductor resistance compared to the single cable?

a)

Doubled

b)

Quartered

c)

Halved

d)

No effect

33.

Which of the following factors affect the insulation resistance of a cable?

a)

Conductor cross-sectional area

b)

Cable length

c)

Installation method

d)

Load current

34.

What is the effect on the combined insulation resistance at the DB when compared to that of a single circuit?

a)

Doubled

b)

Quartered

c)

Halved

d)

No effect

35.

Control gear and interlocks should be operated when carrying out:

a)

Functional testing

b)

Isolation testing

c)

Polarity testing

d)

Continuity testing

36.

Four circuits have insulation resistances of 20 M ohm, 25 M ohm, 40 M ohm and 50 M ohm. When tested together (insulation test) what would be the expected reading:

a)

0.135 M ohm

b)

6.5 M ohm

c)

7.4 M ohm

d)

13.5 M ohm

37.

Which of the following should accompany the inspection and test certificate:

a)

Two copies of test results

b)

Copies of the inspection and test schedules

c)

Copies of minor works certificates

d)

Invoices for any remedial work carried out

38.

Which of the following is not an example of an 'essential test' when carrying out minor works:

a)

Prospective fault current

b)

Earth fault loop impedance

c)

Insulation resistance

d)

Polarity

39.

Digital test instruments should have an accuracy, as stated in GN3, of what percentage of full scale deflection (fsd):

a)

1%

b)

3%

c)

5%

d)

7%

40.

What type of certificate is issued after a rewire of a domestic property?

a)

Minor works certificate

b)

Schedule of test results

c)

Electrical Installation Certificate

d)

Domestic Installation Certificate