WorksheetsQuiz 3 Training Project Management [16/04/25]
Total questions: 5
Worksheet time: 10mins
Which TWO are objectives of the 'controlling a
stage' process?
1. To focus attention on achieving work within the
agreed tolerances
2. To create follow on action recommendations for
all open issues and risks
3. To understand how the quality required will be
achieved
4. To ensure that the stage’s products meet agreed
quality expectations
1 and 2
2 and 3
3 and 4
1 and 4
When does the ‘directing a project’ process
start?
When the project manager submits the project
brief for approval
When the request to authorize a project is
received
After the project has been authorized by business
layer
After the project mandate has been received
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?
Initiating a project
Starting up a project
Controlling a stage
Managing product delivery
Which process should be used to confirm that the project continues to deliver against the strategic objectives?
Closing a project
Initiating a project
Managing a stage boundary
Managing product delivery
Which TWO are objectives of the 'starting up a project' process?
1. To create a common view of how the required quality will be achieved
2. To give authority to initiate the project
3. To appoint the resources needed to do the work to initiate the project
4. To ensure that projects are initiated based on agreed acceptance criteria for the project product
1 and 2
2 and 3
3 and 4
1 and 4