Quiz 3 Training Project Management [16/04/25]

Total questions: 5

Worksheet time: 10mins

Name
Class
Date
1.

Which TWO are objectives of the 'controlling a

stage' process?

1. To focus attention on achieving work within the

agreed tolerances

2. To create follow on action recommendations for

all open issues and risks

3. To understand how the quality required will be

achieved

4. To ensure that the stage’s products meet agreed

quality expectations

a)

1 and 2

b)

2 and 3

c)

3 and 4

d)

1 and 4

2.

When does the ‘directing a project’ process

start?

a)

When the project manager submits the project

brief for approval

b)

When the request to authorize a project is

received

c)

After the project has been authorized by business

layer

d)

After the project mandate has been received

3.

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

a)

Initiating a project

b)

Starting up a project

c)

Controlling a stage

d)

Managing product delivery

4.

Which process should be used to confirm that the project continues to deliver against the strategic objectives?

a)

Closing a project

b)

Initiating a project

c)

Managing a stage boundary

d)

Managing product delivery

5.

Which TWO are objectives of the 'starting up a project' process?

1. To create a common view of how the required quality will be achieved

2. To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based on agreed acceptance criteria for the project product

a)

1 and 2

b)

2 and 3

c)

3 and 4

d)

1 and 4