EMJ33303 Quiz 1 - Energy Regulations and Standards

Total questions: 30

Worksheet time: 23mins

Name
Class
Date
1.

What is the minimum energy consumption threshold under EMEER 2008 that requires compliance?

a)

1,000,000 kWh over 6 months

b)

2,000,000 kWh over 12 months

c)

3,000,000 kWh over 6 months

d)

5,000,000 kWh over 1 year

2.

What is the penalty for non-compliance with EMEER 2008?

a)

RM1,000 fine

b)

RM5,000 fine or 1 year imprisonment or both

c)

RM10,000 fine

d)

No penalty

3.

Who must appoint a Registered Electrical Energy Manager (REEM) under EMEER 2008?

a)

All residential users

b)

Any installation consuming more than 3,000,000 kWh in 6 months

c)

Power station operators only

d)

Only energy consultants

4.

Which regulation enforces MEPS in Malaysia?

a)

Renewable Energy Act 2011

b)

Electricity Regulations 1994 and Amendment 2013

c)

Energy Efficiency Act 2005

d)

Building Code of Malaysia

5.

What is the minimum star rating for an air-conditioner to be sold in Malaysia under MEPS?

a)

1-Star

b)

2-Star

c)

3-Star

d)

5-Star

6.

What must be included on the Energy Efficiency Label under MEPS?

a)

Star rating, price, and expiry date

b)

Manufacturer, model, star rating, and QR code

c)

Store name and serial number

d)

Product color and warranty

7.

Which agency administers the SAVE 4.0 program?

a)

KeTSA

b)

Tenaga Nasional Berhad

c)

SEDA with Energy Commission (ST)

d)

Department of Environment

8.

How much is the maximum e-rebate under SAVE 4.0 for eligible appliances?

a)

RM100

b)

RM200

c)

RM300

d)

RM400

9.

What is a key goal of the SAVE 4.0 program?

a)

To ban non-Malaysian made appliances

b)

To encourage the use of high-energy appliances

c)

To increase use of 4- and 5-star rated appliances

d)

To replace all old appliances by law

10.

What does a lower BEI value indicate?

a)

Higher operational cost

b)

Poor energy efficiency

c)

Better energy efficiency

d)

Higher energy consumption

11.

BEI is calculated using which formula?

a)

Energy Usage / Population

b)

Energy Consumption (GJ) / Gross Floor Area (m²)

c)

Power Load / Number of Devices

d)

Monthly Energy Bills / Total Rooms

12.

What is the primary objective of the BEI program?

a)

Create new building designs

b)

Penalize buildings with high electricity bills

c)

Promote data-driven energy optimization in government buildings

d)

Increase taxes on inefficient buildings

13.

What is the minimum energy use requirement to qualify for EACG 1.0?

a)

10,000 kWh/month

b)

50,000 kWh/month

c)

100,000 kWh/month

d)

500,000 kWh/month

14.

Which organization must conduct the energy audit under EACG?

a)

SEDA Malaysia

b)

Registered Energy Service Company (ESCO)

c)

Tenaga Nasional

d)

Malaysian Energy Foundation

15.

What is the minimum timeline for completing the energy audit under EACG 2.0?

a)

6 months

b)

3 weeks

c)

2 months

d)

1 year

16.

How is an EPC project typically funded?

a)

Fully funded by government budget

b)

By tenants of the building

c)

Fully funded by the ESCO via bank loans

d)

Crowdfunding

17.

What is the usual payback method for ESCOs in EPC?

a)

Monthly building rental

b)

Government grant

c)

Energy savings shared with ESCO

d)

Maintenance charges

18.

What is the typical duration range for an EPC project?

a)

1–2 months

b)

2–6 years

c)

10–20 years

d)

Indefinite

19.

Which level of certification is NOT part of AEMAS?

a)

1 Star

b)

2 Star

c)

3 Star

d)

4 Star

20.

What is the main purpose of AEMAS Gold Standard certification?

a)

Tax exemption

b)

Award for green innovation

c)

Recognition for sustainable energy management

d)

Discount on electricity tariffs

21.

What organization implements AEMAS in Malaysia?

a)

SEDA

b)

MGTC (Malaysian Green Technology Corporation)

c)

KeTSA directly

d)

TNB

22.

What management principle is ISO 50001:2011 based on?

a)

Lean Six Sigma

b)

Plan-Do-Check-Act (PDCA)

c)

SMART Goals

d)

Energy Audit Cycle

23.

What are the benefits of implementing ISO 50001?

a)

Better lighting

b)

Reduced staff

c)

Improved competitiveness and reduced emissions

d)

Free electricity

24.

What is the purpose of the Energy Planning stage in ISO 50001?

a)

To allocate staff bonuses

b)

To set energy tariffs

c)

To review energy data, set targets, and create action plans

d)

To record electricity bills only

25.

Which system is NOT a focus in MS 1525:2014?

a)

Lighting system

b)

Plumbing design

c)

Air-conditioning and mechanical ventilation

d)

Electrical power distribution

26.

What does MS 1525:2014 promote in building design?

a)

Air-tightness

b)

Minimalist design

c)

Energy efficiency and renewable energy use

d)

High energy consumption

27.

What clause in MS 1525:2014 addresses air-conditioning system design?

a)

Clause 5

b)

Clause 6

c)

Clause 8

d)

Clause 10

28.

Which of the following is NOT listed under energy-efficient appliances in MS 2680:2017?

a)

Water heaters

b)

Electric irons

c)

Printers

d)

Televisions

29.

What is the primary goal of MS 2680:2017?

a)

Increase home taxes

b)

Guide efficient energy use and promote renewable energy in homes

c)

Promote smart homes only

d)

Encourage construction of bigger houses

30.

What does MS 2680:2017 encourage regarding appliance use?

a)

Buying the cheapest available

b)

Regular servicing of all units

c)

Selection based on energy efficiency

d)

Avoiding all electronics