1.

You are transitioning to drug development phases in a small pharmaceutical company. The drug development aspect of the project is characterized by a high degree of uncertainty, complexity, and risk. As the work related to the governmental approval process can be more stable, it is highly structured and well defined. What project management approach would you recommend for this project?

a)

Agile for the drug development phases and predictive for the governmental approval process

b)

Predictive for drug development phases and agile for the governmental approval process

c)

Kanban to manage WIP for drug development phases and predictive for the governmental approval process

d)

Only select either Kanban or both the drug development phase and the governmental approval process

2.

You are facilitating a meeting attended by key stakeholders to review the recently completed project management plan. The goal of the meeting is to obtain consensus and approval for the plan. As the project manager, which of the following interpersonal and team skills is the most beneficial to use to achieve the meeting's goal?

a)

Conflict management

b)

Facilitation

c)

Meeting management

d)

Team building

3.

In finalizing the plan, your sponsor can only get half the resources you requested to support the project. The team must wait until the current project stage is finished before the resources will be available. Which action, consistent with best project management practices, should be taken when resources have been allocated in this manner?

a)

Agree with the stakeholders and find a means to deliver less work with the new limitations

b)

Explain that it is not realistic to develop prior releases as top stakeholders may be unavailable

c)

Request stakeholders for more time so the work can continue to be completed when the planned work is not supported

d)

Re-plan the schedule and work with the sponsor to determine when the resources will be available and to support the project schedule

4.

You are leading an agile project management project. As is often the case in agile frameworks, you are leading the project as a servant leader. When reflecting on the project so far, it appears that the project team completes the project increment that has been due during the iteration in order to demonstrate the product increment to the product owner. The product owner gives a review of the product increment, and retrospective and sprint planning meetings are held at the end of every iteration. You have also observed that the team does not use the lessons learned from previous iterations. Your boss, not so experienced in agile frameworks, has observed the same and asks for your advice. What is the best way to address this point?

a)

Perform a sprint review

b)

Schedule a sprint planning meeting

c)

Conduct lessons learned and retrospective sessions

d)

Coach lessons learned introduction into agile projects

5.

You are managing a large IT rollout as a project plan. You try to coordinate the team and have issued various design concepts. Your most experienced engineer is not responding to ideas nor willing to give feedback. Which of the following should you evaluate first to deal with the knowledge gap the team is facing?

a)

The project management plan

b)

The next report

c)

The final assessment

d)

The communications management plan