wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Extracted Worksheet Questions

Total questions: 51

Worksheet time: 26mins

Name
Class
Date
1.

Which of the following is not an element of EEF that can influence the Manage Project Knowledge process? Select one.

a)

Customer Culture

b)

Organizational knowledge expert

c)

Knowledge sharing rule of thumb

d)

Legal / regulatory requirements

2.

Which of the following is not true about the concern of monitoring and controlling project work process? Select one.

a)

Decreasing the number of change request in order to increase the efficiency of the project

b)

Monitoring implementation of approved changes as they occur

c)

Comparing actual project performance against the project management plan

d)

Providing forecasts to update current cost and current schedule information

3.

Which of the following best describes what occurs in a generic life cycle? Select one.

a)

Costs of changes are at the peak at the start then decrease while risk and uncertainty are low at the start but then increase as you proceed through the project.

b)

Risks and uncertainty are at the peak at the start then decrease; while costs of changes are low at the start but then increase as you proceed through the project.

c)

Both costs and risks are lowest at the beginning of the project and increase as you proceed through the project.

d)

Both costs and risks are at its peak at the beginning of the project and decrease as you proceed through the project.

4.

Your company authorizes a project of online training in order to increase the efficiency of staff training cost, what is the reason that your company use to initiate that project? Select one.

a)

Market demand

b)

Organizational Needs

c)

Customer Requests

d)

Social needs

5.

Which of the following is a true statement about process groups? Select one.

a)

All process groups cannot be contained in the same phase.

b)

Process groups cannot be repeated in another phase.

c)

Process groups are the same as project life cycle phases.

d)

Process groups are highly interactive.

6.

Which of the following is the best source of expert judgment in developing the project charter? Select one.

a)

Benchmark data

b)

Focus groups

c)

Expert systems

d)

Stakeholders

7.

What is the level of authority of a project manager in a functional organization? Select one.

a)

Moderate

b)

Little or None

c)

Low

d)

High to Almost Total

8.

Which of the following factors is not a valid influence for the development of the project management plan? Select one.

a)

Project management information system

b)

Project management body of knowledge for vertical market

c)

Industry standards

d)

Baselines

9.

Which of the following is not example of Internal EEF? Select one.

a)

Geographic distribution of facilities and resources

b)

Resource availability

c)

Financial considerations

d)

Employee capability

10.

Which of these is not a component of the Project Management Plan? Select one.

a)

Development approach

b)

Project life cycle description

c)

Requirements Documentation

d)

Cost baseline

11.

_____ = BAC/CPIBAC/CPI

a)

ETC

b)

SPI

c)

EAC

d)

AC

12.

How much is estimated cost if total activities cost for Pessimistic 150.000 USD, Most likely 100.000 USD and Optimistic 80.000 USD using Three point estimated technique?

a)

100.000 USD

b)

105.000 USD

c)

115.000 USD

d)

110.000 USD

13.

Cost Baseline is an output which process?

a)

Determine Budget

b)

Control Cost

c)

Estimate Cost

d)

Plan Cost Management

14.

AC=100AC=100 and PV=200PV=200 and EV=150EV=150 then CV=CV= ?

a)

1,5

b)

-50

c)

0,75

d)

50

15.

What is the main goal of project cost management?

a)

to complete a project for as little cost as possible

b)

to provide truthful and accurate cost information on projects

c)

to complete a project within an approved budget

16.

AC=100AC=100 and PV=200PV=200 and EV=150EV=150 then SV=SV= ?

a)

50

b)

1,5

c)

-50

d)

0,75

17.

SPI=0.90SPI=0.90 and AC=145000AC=145000 and PV=100000PV=100000 then CPI=CPI= ?

a)

0.62

b)

1.402

c)

1.305

d)

0,90

18.

If CPI=0.58CPI=0.58 it means the project is?

a)

Ahead Schedule

b)

Behind Schedule

c)

Under Budget

d)

Over Budget

19.

Below are processes in cost management except

a)

Control Cost

b)

Determine Budget

c)

Plan Cost Management

d)

Determine Cost

20.

Project is over budget if? Select one.

a)

SPI1SPI \ge 1

b)

SPI<1SPI < 1

c)

CPI1CPI \ge 1

d)

CPI<1CPI < 1

21.

Work Performance Data is an input which process?

a)

Plan Cost Management

b)

Determine Budget

c)

Control Cost

d)

Estimate Cost

22.

AC=100 and PV= 200 and EV=150 then SV=?

a)

-50

b)

50

c)

0,75

d)

1,5

23.

_____ = BAC/CPI

a)

ETC

b)

SPI

c)

EAC

d)

AC

24.

Correct Formula for SPI is ...

a)

SPI=EVACSPI = EV - AC

b)

SPI=EVPVSPI = EV - PV

c)

SPI=EV/PVSPI = EV / PV

d)

SPI=EV/ACSPI = EV / AC

25.

if SPI 1.95 it means the project is ?

a)

Over Budget

b)

Behind Schedule

c)

Under Budget

d)

Ahead Schedule

26.

Project is behind schedule if?

a)

CPI<1CPI < 1

b)

SPI<1SPI < 1

c)

SPI1SPI \ge 1

d)

CPI1CPI \ge 1

27.

________________ is a project performance measurement technique that integrates scope, time, and cost data.

a)

Reserve analysis

b)

Earned value management

c)

Project cost budgeting

d)

Life cycle costing

28.

Which of the following is not an output of the project cost management process called Estimate Cost?

a)

project documents updates

b)

a cost baseline

c)

basis of estimates

d)

activity cost estimates

29.

Project is over budget if?

a)

SPI<1SPI < 1

b)

CPI1CPI \ge 1

c)

SPI1SPI \ge 1

d)

CPI<1CPI < 1

30.

WPI (Work Performance Information) is an output in which process?

a)

Determine Budget

b)

Control Cost

c)

Estimate Cost

d)

Plan Cost Management

31.

If SPI=1.95SPI = 1.95 it means the project is? Select one:

a)

Behind Schedule

b)

Under Budget

c)

Ahead Schedule

d)

Over Budget

32.

__________________ is a project performance measurement technique that integrates scope, time, and cost data. Select one:

a)

Reserve analysis

b)

Life cycle costing

c)

Earned value management

d)

Project cost budgeting

33.

Cost Baseline is an output which process? Select one:

a)

Estimate Cost

b)

Control Cost

c)

Determine Budget

d)

Plan Cost Management

34.

_____ = BAC/CPIBAC/CPI Select one:

a)

EAC

b)

SPI

c)

ETC

d)

AC

35.

Correct Formula for SPI is ... Select one:

a)

SPI=EVPVSPI = EV - PV

b)

SPI=EVACSPI = EV - AC

c)

SPI=EV/ACSPI = EV/AC

d)

SPI=EV/PVSPI = EV/PV

36.

Given AC=1000AC=1000 , SPI=1.6SPI=1.6 , and CPI=0.8CPI=0.8 , find PVPV . Select one.

a)

2000

b)

1280

c)

500

d)

800

37.

What is the main goal of project cost management? Select one.

a)

to complete a project within an approved budget

b)

to provide truthful and accurate cost information on projects

c)

to complete a project for as little cost as possible

38.

Correct formula for CPI is ... Select one.

a)

CPI=EVACCPI = EV - AC

b)

CPI=EV/ACCPI = EV/AC

c)

CPI=EVPVCPI = EV - PV

d)

CPI=EV/PVCPI = EV/PV

39.

Select one. SPI=0.90 and AC=145000 and PV=100000 then CPI=?

a)

0.62

b)

1.402

c)

1.305

d)

0,90

40.

Select one. AC=100 and PV= 200 and EV=150 then CV=?

a)

50

b)

-50

c)

0,75

d)

1,5

41.

Work performance reports is an input in which process?

a)

Manage Team

b)

Develop team

c)

Plan resource management

d)

Acquire resource

42.

Which theory believes that workers need to be involved with the management process?

a)

Herzberg's theory of motivation

b)

Ouchi's theory Z

c)

Expectancy theory

d)

McGregor's theory of X and Y

43.

Which problem-solving technique is the best for most project management situations?

a)

Confronting

b)

avoiding

c)

Compromising

d)

Forcing

44.

You are a project manager for E-learning Project. Your project requires two instructional designer. This is an example of which of the following?

a)

Organizational interfaces

b)

Planning Requirements

c)

Staffing Requirements

d)

Resource Constraints

45.

What are the process group that contains project resource management knowledge area?

a)

planning and closing

b)

planning,executing, monitoring & controlling

c)

initiating and planning

d)

planning and monitoring controling

46.

You are the project manager of Knowledge Management System Project. This project requires to tailor the way Project Resource Management processes are applied. Regarding to this, what is one of factor that need to consider?

a)

Life cycle approaches.

b)

Project's politic

c)

Emotional Intelligence

d)

Team Perseverance

47.

The following are list of project documents that will be used as an input in activity estimate process, Except?

a)

Resource Requirements

b)

Activity attributes

c)

Assumption log

d)

Activity list

48.

Which of the following describes Maslows Hierarchy of Needs?

a)

The companys needs are most important, then the boss, then the employees.

b)

You need to feel safe and accepted to want to be good at your job.

c)

You can not be good at your job if you do not have a nice office.

d)

Your boss needs are more important than yours.

49.

What are the five stages in Tuckman model of team development, in chronological order?

a)

norming, forming, storming, performing, and adjourning

b)

forming, storming, norming, performing, and adjourning

c)

storming, forming, norming, performing, and adjourning

d)

forming, storming, performing, norming, and adjourning

50.

Everybody does what Yoga says because he and the president of the company are golfing buddies. What kind of power does he hold over the team?

a)

Reward

b)

Referent

c)

Legitimate

d)

Punishment

51.

Stakeholder engagement assessment matrix is a technique in which process?

a)

Monitor Stakeholder Engagement

b)

Manage Stakeholder Engagement

c)

Identify Stakeholders

d)

Plan Stakeholder Management