Which of the following is not an element of EEF that can influence the Manage Project Knowledge process? Select one.
Customer Culture
Organizational knowledge expert
Knowledge sharing rule of thumb
Legal / regulatory requirements
Which of the following is not true about the concern of monitoring and controlling project work process? Select one.
Decreasing the number of change request in order to increase the efficiency of the project
Monitoring implementation of approved changes as they occur
Comparing actual project performance against the project management plan
Providing forecasts to update current cost and current schedule information
Which of the following best describes what occurs in a generic life cycle? Select one.
Costs of changes are at the peak at the start then decrease while risk and uncertainty are low at the start but then increase as you proceed through the project.
Risks and uncertainty are at the peak at the start then decrease; while costs of changes are low at the start but then increase as you proceed through the project.
Both costs and risks are lowest at the beginning of the project and increase as you proceed through the project.
Both costs and risks are at its peak at the beginning of the project and decrease as you proceed through the project.
Your company authorizes a project of online training in order to increase the efficiency of staff training cost, what is the reason that your company use to initiate that project? Select one.
Market demand
Organizational Needs
Customer Requests
Social needs
Which of the following is a true statement about process groups? Select one.
All process groups cannot be contained in the same phase.
Process groups cannot be repeated in another phase.
Process groups are the same as project life cycle phases.
Process groups are highly interactive.
Which of the following is the best source of expert judgment in developing the project charter? Select one.
Benchmark data
Focus groups
Expert systems
Stakeholders
What is the level of authority of a project manager in a functional organization? Select one.
Moderate
Little or None
Low
High to Almost Total
Which of the following factors is not a valid influence for the development of the project management plan? Select one.
Project management information system
Project management body of knowledge for vertical market
Industry standards
Baselines
Which of the following is not example of Internal EEF? Select one.
Geographic distribution of facilities and resources
Resource availability
Financial considerations
Employee capability
Which of these is not a component of the Project Management Plan? Select one.
Development approach
Project life cycle description
Requirements Documentation
Cost baseline
_____ = BAC/CPI
ETC
SPI
EAC
AC
How much is estimated cost if total activities cost for Pessimistic 150.000 USD, Most likely 100.000 USD and Optimistic 80.000 USD using Three point estimated technique?
100.000 USD
105.000 USD
115.000 USD
110.000 USD
Cost Baseline is an output which process?
Determine Budget
Control Cost
Estimate Cost
Plan Cost Management
AC=100 and PV=200 and EV=150 then CV= ?
1,5
-50
0,75
50
What is the main goal of project cost management?
to complete a project for as little cost as possible
to provide truthful and accurate cost information on projects
to complete a project within an approved budget
AC=100 and PV=200 and EV=150 then SV= ?
50
1,5
-50
0,75
SPI=0.90 and AC=145000 and PV=100000 then CPI= ?
0.62
1.402
1.305
0,90
If CPI=0.58 it means the project is?
Ahead Schedule
Behind Schedule
Under Budget
Over Budget
Below are processes in cost management except
Control Cost
Determine Budget
Plan Cost Management
Determine Cost
Project is over budget if? Select one.
SPI≥1
SPI<1
CPI≥1
CPI<1
Work Performance Data is an input which process?
Plan Cost Management
Determine Budget
Control Cost
Estimate Cost
AC=100 and PV= 200 and EV=150 then SV=?
-50
50
0,75
1,5
_____ = BAC/CPI
ETC
SPI
EAC
AC
Correct Formula for SPI is ...
SPI=EV−AC
SPI=EV−PV
SPI=EV/PV
SPI=EV/AC
if SPI 1.95 it means the project is ?
Over Budget
Behind Schedule
Under Budget
Ahead Schedule
Project is behind schedule if?
CPI<1
SPI<1
SPI≥1
CPI≥1
________________ is a project performance measurement technique that integrates scope, time, and cost data.
Reserve analysis
Earned value management
Project cost budgeting
Life cycle costing
Which of the following is not an output of the project cost management process called Estimate Cost?
project documents updates
a cost baseline
basis of estimates
activity cost estimates
Project is over budget if?
SPI<1
CPI≥1
SPI≥1
CPI<1
WPI (Work Performance Information) is an output in which process?
Determine Budget
Control Cost
Estimate Cost
Plan Cost Management
If SPI=1.95 it means the project is? Select one:
Behind Schedule
Under Budget
Ahead Schedule
Over Budget
__________________ is a project performance measurement technique that integrates scope, time, and cost data. Select one:
Reserve analysis
Life cycle costing
Earned value management
Project cost budgeting
Cost Baseline is an output which process? Select one:
Estimate Cost
Control Cost
Determine Budget
Plan Cost Management
_____ = BAC/CPI Select one:
EAC
SPI
ETC
AC
Correct Formula for SPI is ... Select one:
SPI=EV−PV
SPI=EV−AC
SPI=EV/AC
SPI=EV/PV
Given AC=1000 , SPI=1.6 , and CPI=0.8 , find PV . Select one.
2000
1280
500
800
What is the main goal of project cost management? Select one.
to complete a project within an approved budget
to provide truthful and accurate cost information on projects
to complete a project for as little cost as possible
Correct formula for CPI is ... Select one.
CPI=EV−AC
CPI=EV/AC
CPI=EV−PV
CPI=EV/PV
Select one. SPI=0.90 and AC=145000 and PV=100000 then CPI=?
0.62
1.402
1.305
0,90
Select one. AC=100 and PV= 200 and EV=150 then CV=?
50
-50
0,75
1,5
Work performance reports is an input in which process?
Manage Team
Develop team
Plan resource management
Acquire resource
Which theory believes that workers need to be involved with the management process?
Herzberg's theory of motivation
Ouchi's theory Z
Expectancy theory
McGregor's theory of X and Y
Which problem-solving technique is the best for most project management situations?
Confronting
avoiding
Compromising
Forcing
You are a project manager for E-learning Project. Your project requires two instructional designer. This is an example of which of the following?
Organizational interfaces
Planning Requirements
Staffing Requirements
Resource Constraints
What are the process group that contains project resource management knowledge area?
planning and closing
planning,executing, monitoring & controlling
initiating and planning
planning and monitoring controling
You are the project manager of Knowledge Management System Project. This project requires to tailor the way Project Resource Management processes are applied. Regarding to this, what is one of factor that need to consider?
Life cycle approaches.
Project's politic
Emotional Intelligence
Team Perseverance
The following are list of project documents that will be used as an input in activity estimate process, Except?
Resource Requirements
Activity attributes
Assumption log
Activity list
Which of the following describes Maslows Hierarchy of Needs?
The companys needs are most important, then the boss, then the employees.
You need to feel safe and accepted to want to be good at your job.
You can not be good at your job if you do not have a nice office.
Your boss needs are more important than yours.
What are the five stages in Tuckman model of team development, in chronological order?
norming, forming, storming, performing, and adjourning
forming, storming, norming, performing, and adjourning
storming, forming, norming, performing, and adjourning
forming, storming, performing, norming, and adjourning
Everybody does what Yoga says because he and the president of the company are golfing buddies. What kind of power does he hold over the team?
Reward
Referent
Legitimate
Punishment
Stakeholder engagement assessment matrix is a technique in which process?
Monitor Stakeholder Engagement
Manage Stakeholder Engagement
Identify Stakeholders
Plan Stakeholder Management