wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Day 48-worksheet-PWD-Construction management topics

Total questions: 15

Worksheet time: 10mins

Name
Class
Date
1.

In construction planning, the procurement phase mainly includes —

a)

Detailed design and WBS preparation

b)

Bidding and tendering processes

c)

Site mobilization and resource allocation

d)

Dispute settlement and contract execution

2.

Which dispute-settlement method involves two technical persons and one chairperson?

a)

Adjudication

b)

Dispute Review Board

c)

Conciliation

d)

Arbitration

3.

The injury frequency rate is defined as —

a)

Days lost per 1000 man-hours

b)

Fatalities per year

c)

Disabling injuries per lakh man-hours worked

d)

Injuries due to physiological causes

4.

In material management, FIFO ensures —

a)

New stock is used first

b)

Reduced quality

c)

Older stock is used first

d)

Increased storage cost

5.

Conciliation is similar to mediation but the conciliator meets both parties separately.

a)

True

b)

False

6.

Selective tendering results in lower prices than open tendering due to greater competition.

a)

True

b)

False

7.

Assertion (A): Nomination (single tendering) often leads to lower contract prices. Reason (R): Because competition is eliminated and only one preferred contractor is invited. Choose the correct option.

a)

A and R are true, and R is the correct explanation

b)

A and R are true, but R is not the explanation

c)

A is true, R is false

d)

A is false, R is true

8.

The construction phase comes after the (a)   phase.

9.

(a)   float is defined as the time through which an activity can be delayed without affecting the succeeding and preceding activities.

10.

EOQ depends on annual consumption (A), ordering cost (S), and _____ cost (I).

a)

carrying

b)

scrap

c)

depreciation

d)

transport

11.

Arrange the following phases of a construction project in correct order

1) Procurement Phase 2) Close-out Phase 3) Pre-construction Phase 4) Construction Phase

(a)  

12.

Identify the odd one out.

a)

Mediation

b)

Conciliation

c)

Arbitration

d)

Activity-on-Node method

13.

In PERT analysis, a critical activity has—————-float

(a)  

14.

Consider the statements: S1: Selective tendering ensures only capable firms submit tenders. S2: Selective tendering always gives the lowest tender cost. Choose the correct option.

a)

Both correct

b)

Both incorrect

c)

S1 correct, S2 incorrect

d)

S1 incorrect, S2 correct

15.

The amount of time by which an activity can be delayed without affecting project completion time is:

(a)