Length of the current collector shoe is 500 mm.
False
True
While moving RRCS, the audible alarm sound will be activated.
False
True
What is the function of the Transition Bar in ROCS?
To support the cantilever
To connect ROCS with FOCS
To reduce voltage drop
To clamp insulators
The contact wire in ROCS is tensioned mechanically.
False
True
Mid-point anchor is used to control expansion and contraction forces.
True
False
RRCS can be operated only when the system is
Energized
De-energized
Under load
Grounded
From the track center to the third rail, the horizontal distance is ______
3000mm
1350mm
1480mm
1840mm
Height of the contact wire in a 2x25 kV system high-rise OHE (DFCC) is
8.94 m
5.80 m
7.57 m
7.54 m
3 Span overlap is adopted in
EDFC Project
DFCC Project
EPC Project
Nowhere
Out of run (OOR) should be avoided at
Curved Track
Level Crossing
All the above
Tangent Track
At obligatory locations, track separation should be between
150mm to 700mm
650mm to 720mm
620mm to 700mm
150mm to 720mm
The minimum setting distance of a mast located on the platform is 4.75 m.
False
True
Maximum span adopted in high-speed rail is
72 m
63 m
54 m
50 m
Full form of RRCS is
Retractable Rigid Catenary System
Raised Rigid Catenary System
Retractable Rigid Continuity System
Rigid and Raised Catenary System
Maximum design speed for High-Speed OHE system is
160 km/h
200 km/h
250 km/h
320 km/h
Output voltage of a Scott-connected transformer is
66 KV
110 KV
132 KV
50 KV
Generally, the sub-sector is between ____ & ____
AFP & SP
Gantry & Isolator
FP & SSP
SSP & Isolator
Parallel interrupters are provided for extending the UP & DN line power supply.
True
False
Protection of the transformer in TSS is by
Transformer CB
Feeder CB
Interrupters
Auto Transformer
Voltage system used for Bullet Train OHE is
25 kV AC
2 x 25 kV AC
1500 V DC
750 V DC
First aid boxes and shock treatment charts are provided at switching stations.
False
True
M-15 ratio of concrete mix is
1:3:9
1:3:6
1:2:4
1:2:6
The foundation center is measured from the track center to the face of the mast.
False
True
The embedded length of a high-speed foundation is
750mm
500mm
800mm
600mm
Clear span of ‘O’ type portal is
None of the above
20.05 m – 30.45 m
9.91 m – 20.31 m
30.50 m – 36.00 m
Reverse deflection of the TTC structure is 60 mm.
False
True
Which colour of GRP cover fasteners is used for tunnel sections?
Blue
White
Black
Pink
DFCC catenary wire cross-sectional area is 129 sq. mm
False
True
What is the cross-sectional area of the contact and catenary wires in High-speed OHE?
120 sq.mm
150 sq.mm
170 sq.mm
200 sq.mm
Which component joins two conductor rails together in ROCS?
Anchor Bar
Interlocking Joint
Swivel Head
Drop Tube
In the Third Rail System, the conductor rail is made of
Pure copper
Aluminium with stainless steel
Mild steel
Aluminium and zinc
Isolators are supported above a mast with
Bracket insulator
Tie rod insulator
Pedestal / support insulator
Stay insulator
Creepage distance of insulators in highly polluted zone area at the DFCC project
1050 mm
850 mm
1612 mm
1650 mm
Maximum stagger of contact wire in curvature in metro is
500 mm
150 mm
450 mm
300 mm
Which type of cantilever?
Push off
Pull off
Size of Al. Bracket tube in modular cantilever is
40 mm
49 mm
55 mm
70 mm
Take OFF / take ON point on Pantograph is
650 to 720 mm
150 to 750 mm
100 to 700 mm
200 to 500 mm
Expansion joints are not required in a third rail traction system.
TRUE
FALSE
Insulated overlap is required for
OHE sectioning purpose
To keep OHE in current collection
To maintain the height of OHE conductors
All of the above
At the obligatory location, the turnout contact wire is kept ___ mm above the main line contact wire.
100 mm
50 mm
20 mm
5 mm
Advantage of Spring ATD is
Easy to Measure X & Y Values
Lower Initial Cost
None of the above
Lower Maintenance
Power block limit boards are to be provided at
X-Over
UIOL
Turnouts
IOL
Size of the MS flat used in DFCC TSS is
40 x 6 mm
50 x 6 mm
100 x 8 mm
75 x 8 mm
Long time clearance is
200 mm
250 cm
250 mm
200 cm
Before running passenger trains, the section will be inspected by
CRS
PMC
Sr. DEE
CEO
The FRP Insulator Cover is provided for
Reducing weight
Insulation and safety from electric contact
Thermal expansion
Alignment
Which safety feature is included in RRCS operation?
Voltage detection interlock
Manual switch operation
Separate supply feeder
Counterweight tensioner
Isolator clearance between Phase and Earth is
450-500 mm
490-520 mm
500-550 mm
550-600 mm
'BDV' of transformer oil should be
30 KV / minute
40 KV / minute
60 KV / minute
100 KV / minute
PTFE neutral section is suitable for a speed of
70 km/hr
90 km/hr
100 km/hr
130 km/hr