Management is the art of getting work done through:
Machines
Money
People
Materials
Which is the first function of management?
Staffing
Planning
Directing
Controlling
CPM focuses mainly on:
Cost
Quality
Critical activities
Materials
Which organization structure follows unity of command strictly?
Functional
Line
Line & Staff
Matrix
PERT was developed by:
DuPont
US Navy
Ford
Taylor
Resource leveling aims to:
Reduce cost
Increase duration
Balance resources
Increase profit
Which project is publicly funded?
Private
Industrial
State
Residential
Theory X assumes workers are:
Self-motivated
Lazy
Innovative
Creative
Bar chart is also known as:
Network chart
Gantt chart
CPM chart
Flow chart
Materials are issued only on:
Invoice
Bin card
Indent
Voucher
Which function of management ensures work is performed as per plan?
Planning
Organizing
Directing
Controlling
Staffing mainly deals with:
Machines
Money
Manpower
Materials
The main objective of controlling is to:
Punish workers
Increase profit
Ensure performance as per standards
Reduce labour
Functional organization was proposed by:
Henry Fayol
F.W. Taylor
Mintzberg
Koontz
Which role of manager involves decision making?
Informational
Interpersonal
Decisional
Supervisory
In CPM, the critical path is the path with:
Maximum float
Minimum activities
Longest duration
Highest cost
Float time is associated with:
Critical activities
Non-critical activities
All activities
Final activity
PERT uses which time estimates?
Single
Two
Three
Four
Which construction project is funded by central government?
Private
State
Federal
Industrial
Resource leveling is done mainly to:
Reduce project duration
Reduce cost
Balance resource usage
Increase profit
Which planning is done before tender submission?
Contract planning
Site execution planning
Pre-tender planning
Post-construction planning
The document authorizing issue of materials from stores is:
Invoice
Bin card
Indent
Voucher
Bin card is maintained at:
Site office
Divisional office
Store room
Head office
Bar charts are also called:
CPM charts
PERT charts
Gantt charts
Network charts
Which scheduling method clearly shows inter-dependency of activities?
Bar chart
Histogram
CPM
Pie chart
Construction planning mainly aims at:
Increasing wages
Minimizing cost and time
Reducing labour
Maximizing paperwork
Resource aggregation generally results in:
Straight line
Bell-shaped curve
Zigzag curve
Random curve
Which resource planning technique shifts non-critical activities?
Resource loading
Resource leveling
Resource allocation
Resource analysis
Measurement Book (M-Book) is used for:
Store records
Labour attendance
Recording measurements
Financial audit
CPM was developed by:
Henry Fayol
F.W. Taylor
Morgan Walker & James Kelley
Mintzberg
Which contract has fixed total cost?
Item rate
Percentage rate
Lump sum
Cost plus
Tender is:
Agreement
Contractor’s written offer
Payment bill
Measurement record
Muster Roll is used for payment to:
Contractors
Suppliers
Casual labour
Engineers
Casual labour is generally paid on:
Monthly basis
Weekly basis
Daily basis
Annual basis
Regular establishment employees are paid:
Daily wages
Piece rate
Monthly salary
Contract basis
Which Act ensures minimum wages?
Contract Labour Act
Workmen Compensation Act
Minimum Wages Act, 1948
Factory Act
Real wage includes:
Only cash payment
Bonus and benefits
Overtime only
Allowances only
Which accident cause is due to poor lighting?
Human cause
Mechanical cause
Environmental cause
Administrative cause
Workmen Compensation Act applies in case of:
Illness only
Accident during employment
Voluntary injury
Alcohol consumption
Contract Labour Act applies when workers exceed:
10
15
20
50
Scheduling mainly helps in:
Wage fixation
Resource optimization
Labour law compliance
Tender evaluation
Which chart does NOT show progress clearly?
CPM
Network diagram
Bar chart
Resource histogram
Which activity delay delays entire project?
Non-critical
Dummy
Critical
Float
Which is NOT a management function?
Planning
Organizing
Directing
Accounting
Construction management aims at:
Maximum cost
Minimum production
Maximum output at least cost
Maximum manpower
Stores should not be issued in bulk to contractors to avoid:
Delay
Pilferage
Quality issues
Documentation
Which planning is done after tender acceptance?
Pre-tender
Contract planning
Strategic planning
Financial planning
Which scheduling method is simplest?
CPM
PERT
Bar chart
Line of balance
CPM is best suited for:
Highly uncertain projects
Probabilistic analysis
Deterministic projects
Small projects only
The longest path in network determines:
Cost
Float
Duration
Quality
Which management function is called the “life spark” of organization?
Planning
Staffing
Directing
Controlling
In CPM, activities with zero float are called:
Dummy
Free
Critical
Independent
PERT is most suitable for projects which are:
Repetitive
Small
Uncertain in time
Low cost
Line organization strictly follows:
Unity of direction
Unity of command
Division of work
Centralization
Resource leveling is applied when:
Cost is fixed
Duration is flexible
Duration is fixed
Labour is unlimited
Which document forms the basis of contractor payment?
Bin card
Indent
Measurement book
Invoice
Lump sum contract is suitable when:
Quantities are uncertain
Design is incomplete
Scope is well defined
Rates fluctuate
Casual labour wages are recorded in:
Cash book
Ledger
Muster roll
Bill register
The critical path always has:
Maximum cost
Minimum activities
Zero float
Minimum duration
Which Act regulates employment of contract labour?
Minimum Wages Act
Contract Labour Act, 1970
Factory Act
Compensation Act
Explain the functions of management in construction projects.
Planning, organizing, staffing, directing and controlling
Planning, budgeting, tendering and accounting
Organizing, scheduling, contracting and financing
Directing, supervising, purchasing and auditing
Describe CPM and its importance in construction management.
A bar-chart method that focuses on aesthetics of reporting
A probabilistic model used mainly for cost estimation
A network-based scheduling technique that identifies critical activities, controls delays and improves timely completion
A manpower forecasting tool for non-critical tasks only
Explain resource leveling and its advantages.
Shifting non-critical activities within float time to balance resource demand, avoid over-utilization and ensure smooth workflow without extending project duration
Accelerating critical activities by adding overtime to shorten project duration
Reducing project cost by cutting resource quantities below planned levels
Reassigning all activities to critical path to maximize productivity
Explain types of construction projects. Construction projects are classified into private, state and federal projects. Which are the types classified here? Select all that apply.
Private projects
State projects
Federal projects
International projects
Explain the importance of construction planning. Construction planning minimizes cost, reduces delays, optimizes resources, prevents conflicts and improves coordination. Which outcomes are ensured by effective construction planning? Select all that apply.
Minimizes cost
Reduces delays
Optimizes resources
Prevents conflicts and improves coordination
Increases random variability in schedules
CASE–1: Delay in Housing Project. A private housing project was scheduled for completion in 18 months. Due to improper planning, shortage of skilled labour and frequent material delays, the project got delayed by 5 months. The project manager failed to revise the schedule and did not monitor critical activities. Which management functions were mainly lacking in this project? Select all that apply.
Controlling
Planning
Organizing
Staffing
CASE–1: Delay in Housing Project. A private housing project was scheduled for completion in 18 months. Due to improper planning, shortage of skilled labour and frequent material delays, the project got delayed by 5 months. The project manager failed to revise the schedule and did not monitor critical activities. Name the scheduling technique that could have identified delay‑causing activities.
CPM
PERT
Gantt chart
Line of Balance
CASE–1: Delay in Housing Project. A private housing project was scheduled for completion in 18 months. Due to improper planning, shortage of skilled labour and frequent material delays, the project got delayed by 5 months. The project manager failed to revise the schedule and did not monitor critical activities. Which activities must be closely monitored to avoid such delay?
Non‑critical activities
Critical activities
Dummy activities
Optional activities
CASE–1: Delay in Housing Project. A private housing project was scheduled for completion in 18 months. Due to improper planning, shortage of skilled labour and frequent material delays, the project got delayed by 5 months. The project manager failed to revise the schedule and did not monitor critical activities. Which corrective measures would help prevent future delays? Select all that apply.
Proper scheduling
Resource planning
Regular monitoring
Reduce project scope without approval
CASE–2: Resource Imbalance at Construction Site. In a bridge construction project, the contractor deployed a large number of workers during initial stages, while later activities suffered from labour shortage. This caused idle time in early stages and overtime wages in later stages. Identify the construction management problem in this case.
Improper resource allocation
Poor quality control
Insufficient safety measures
Inaccurate surveying
CASE–2: Resource Imbalance at Construction Site. In a bridge construction project, the contractor deployed a large number of workers during initial stages, while later activities suffered from labour shortage. This caused idle time in early stages and overtime wages in later stages. Which resource management technique should have been used?
Resource leveling
Just‑in‑time purchasing
Cost–benefit analysis
Benchmarking
CASE–2: Resource Imbalance at Construction Site. In a bridge construction project, the contractor deployed a large number of workers during initial stages, while later activities suffered from labour shortage. This caused idle time in early stages and overtime wages in later stages. What is the main objective of the recommended technique?
Balanced utilization of resources
Minimizing contract disputes
Enhancing architectural aesthetics
Maximizing profit through change orders
CASE–2: Resource Imbalance at Construction Site. In a bridge construction project, the contractor deployed a large number of workers during initial stages, while later activities suffered from labour shortage. This caused idle time in early stages and overtime wages in later stages. Which drawbacks are likely if this technique is not applied? Select all that apply.
Idle time
Increased cost
Improved schedule adherence
Lower overtime wages
CASE–3: Accident at Construction Site. A worker fell from scaffolding due to absence of safety railings and poor lighting. Investigation revealed that no safety inspection was conducted and workers were not trained properly. Identify the type of accident cause involved.
Environmental and administrative cause
Mechanical failure
Natural calamity
Intentional misconduct
CASE–3: Accident at Construction Site. A worker fell from scaffolding due to absence of safety railings and poor lighting. Investigation revealed that no safety inspection was conducted and workers were not trained properly. Which management responsibilities were neglected? Select all that apply.
Directing
Controlling
Planning
Marketing
CASE–3: Accident at Construction Site. A worker fell from scaffolding due to absence of safety railings and poor lighting. Investigation revealed that no safety inspection was conducted and workers were not trained properly. Name the Act applicable in this situation.
Workmen Compensation Act
Factories Act
Environmental Protection Act
Minimum Wages Act
CASE–3: Accident at Construction Site. A worker fell from scaffolding due to absence of safety railings and poor lighting. Investigation revealed that no safety inspection was conducted and workers were not trained properly. Which safety measures should be implemented to avoid such accidents? Select all that apply.
Safety training
Proper lighting
Safety rails
Ignore minor hazards
CASE–4: Poor Stores Management. At a construction site, materials were frequently unavailable despite sufficient stock in store records. On inspection, bin cards were not updated regularly and materials were issued without proper authorization. Which management area is weak in this case?
Stores management
Financial auditing
Design management
Site surveying
CASE–4: Poor Stores Management. At a construction site, materials were frequently unavailable despite sufficient stock in store records. On inspection, bin cards were not updated regularly and materials were issued without proper authorization. Name the document used for authorization of material issue.
Indent
Invoice
Purchase order
Gate pass
CASE–4: Poor Stores Management. At a construction site, materials were frequently unavailable despite sufficient stock in store records. On inspection, bin cards were not updated regularly and materials were issued without proper authorization. Where should bin cards be maintained?
Store room
Site office
Accounts department
Design studio
CASE–4: Poor Stores Management. At a construction site, materials were frequently unavailable despite sufficient stock in store records. On inspection, bin cards were not updated regularly and materials were issued without proper authorization. Which improvements would strengthen stores management? Select all that apply.
Regular updating of records
Proper record keeping
Issue materials without authorization
Maintain accurate bin cards
CASE–5: Tender and Contract Issue. A contractor quoted a very low rate to secure a government project. Later, he faced heavy losses due to underestimated quantities and increased material costs. Identify the mistake made by the contractor.
Improper pre‑tender planning
Choosing a high‑risk site
Excess staff recruitment
Ignoring safety compliance
CASE–5: Tender and Contract Issue. A contractor quoted a very low rate to secure a government project. Later, he faced heavy losses due to underestimated quantities and increased material costs. Which type of contract would be risky in this situation?
Lump sum contract
Cost‑plus contract
Unit rate contract
Time and materials contract
CASE–5: Tender and Contract Issue. A contractor quoted a very low rate to secure a government project. Later, he faced heavy losses due to underestimated quantities and increased material costs. Which planning stage was ignored by the contractor?
Pre‑tender planning
Execution planning
Post‑contract review
Commissioning planning
CASE–5: Tender and Contract Issue. A contractor quoted a very low rate to secure a government project. Later, he faced heavy losses due to underestimated quantities and increased material costs. Which precaution should be taken while bidding?
Detailed cost analysis
Promise unrealistic completion time
Reduce contingency to zero
Avoid site visits
CASE–6: Ineffective Supervision. In a road construction project, workers were often absent, quality of work was poor and progress was slow. The site engineer rarely visited the site and instructions were unclear. Which management function is poorly performed?
Directing
Planning
Organizing
Staffing
CASE–6: Ineffective Supervision. In a road construction project, workers were often absent, quality of work was poor and progress was slow. The site engineer rarely visited the site and instructions were unclear. Name two elements of directing involved here. Select all that apply.
Supervision
Communication
Procurement
Budgeting
CASE–6: Ineffective Supervision. In a road construction project, workers were often absent, quality of work was poor and progress was slow. The site engineer rarely visited the site and instructions were unclear. What is the impact of poor supervision?
Low productivity and poor quality
High morale and faster progress
Improved safety and training
Accurate resource leveling
CASE–6: Ineffective Supervision. In a road construction project, workers were often absent, quality of work was poor and progress was slow. The site engineer rarely visited the site and instructions were unclear. Which corrective action is appropriate?
Regular supervision with clear instructions
Reduce inspections to save time
Delegate supervision entirely to workers
Focus only on paperwork
CASE–7: CPM Application. A project has two paths: Path A = 20 days; Path B = 26 days. Identify the critical path.
Path A
Path B
Both paths
Neither path
CASE–7: CPM Application. A project has two paths: Path A = 20 days; Path B = 26 days. What is the project duration?
20 days
26 days
46 days
Depends on resource leveling
CASE–7: CPM Application. A project has two paths: Path A = 20 days; Path B = 26 days. What happens if Path B is delayed by 3 days?
Project completion will be delayed
Only non‑critical tasks are affected
No change due to total float
Path A becomes critical and duration unchanged
CASE–7: CPM Application. A project has two paths: Path A = 20 days; Path B = 26 days. Can Path A be delayed without affecting project completion?
Yes, if float is available
No, any delay affects completion
Only with overtime on Path B
Only after commissioning
CASE–8: Labour Payment Issue. Casual labour at a site complained about delayed wages. The site clerk failed to maintain proper attendance records. Which document is used for recording casual labour attendance?
Muster roll
Pay slip
Work order
Time and motion sheet
CASE–8: Labour Payment Issue. Casual labour at a site complained about delayed wages. The site clerk failed to maintain proper attendance records. Which management function is weak?
Controlling
Planning
Organizing
Marketing
CASE–8: Labour Payment Issue. Casual labour at a site complained about delayed wages. The site clerk failed to maintain proper attendance records. Which effect of delayed wages on productivity is likely?
Low morale and absenteeism
Higher motivation
Improved productivity
Reduced turnover
CASE–8: Labour Payment Issue. Casual labour at a site complained about delayed wages. The site clerk failed to maintain proper attendance records. Which corrective step is appropriate?
Timely wage payment
Ignore attendance records
Reduce wages to control costs
Delay payment to align with cash flow