WorksheetsIT Project Management and Feasibility Worksheet
Total questions: 50
Worksheet time: 25mins
What is the main purpose of IT Project Management?
To focus on programming and system development
To ensure IT projects meet goals on time, within budget, and within scope
To reduce the cost of developing IT systems
To increase the number of project stakeholders
Which of the following best describes the Triple Constraint?
People, process, product
Scope, time, cost
Planning, execution, control
Budget, quality, documentation
Which scenario best represents scope in IT project management?
Deadline is moved earlier due to client request
Total cost of hosting increases
Specific features such as login system, dashboard, and reports
The project must be completed in six months
Which phase involves developing schedules, WBS, and Gantt charts?
Initiation
Planning
Execution
Closing
In which project phase does coding, system setup, and integration occur?
Planning
Execution
Initiation
Monitoring & Controlling
Who ensures that all project activities stay within the planned timeline and budget?
Developer
Stakeholder
Project Manager
Quality Assurance Tester
Which tool is best suited for version control during the Execution phase?
SurveyMonkey
GitHub
Google Docs
Trello Boards
The phase where the project output is evaluated and lessons learned are documented is:
Monitoring & Controlling
Execution
Initiation
Closing
A Business Analyst is primarily responsible for:
Writing and testing the system code
Managing budgets and schedules
Gathering requirements and converting them into technical details
Deploying and maintaining servers
A failed government IT system due to poor project monitoring highlights the importance of:
Setting strict penalties for developers
Increasing project cost
Following proper IT project management practices
Removing stakeholders from decision-making
Which question is most relevant to technical feasibility?
Will the new system fit into current workflows?
Can the required technology be implemented with available infrastructure?
Will the project increase the company’s revenue?
Are users willing to adopt the system?
What does operational feasibility primarily assess?
Availability of programming languages
Financial benefits and cost savings
The organization’s ability to adopt and sustain the system
Compatibility of hardware and software
Economic feasibility answers which of the following?
Is the technology available in the market?
Does the project deliver benefits greater than its cost?
Do users need training to operate the system?
Can the project team handle the development tasks?
A company wants to build a CRM. Evaluating employee readiness and process integration belongs to:
Technical feasibility
Operational feasibility
Cost-benefit analysis
Project scheduling
Which of the following is not part of technical feasibility?
Checking if the team has required skills
Assessing whether the infrastructure can support the project
Analyzing future revenue from system usage
Determining if required software tools exist
ROI, payback period, and cost-benefit analysis are most relevant to:
Technical feasibility
Operational feasibility
Economic feasibility
Resource feasibility
What is the main purpose of conducting a feasibility study before starting an IT project?
To guarantee the project will succeed
To determine if the project is viable across technical, operational, and economic dimensions
To start building system prototypes
To speed up the development timeline
In the example of the fitness mobile app, which factor made the project technically feasible?
High revenue projections for Year 1
Team skills in React Native, APIs, and cloud hosting
Availability of customer support staff
Subscription model for premium users
When evaluating whether the project fits the organization’s goals and capacity, the process is known as:
Project execution
Project selection
Cost estimation
System deployment
Which is an example of operational feasibility for a mobile app project?
Choosing between MySQL and MongoDB
Estimating the payback period for the development cost
Determining if users can integrate the app with fitness trackers
Ensuring the UI/UX design is completed on time
What is the primary purpose of a Project Charter?
To create the project’s technical architecture
To formally authorize the project and define its objectives
To assign tasks to developers
To estimate software development costs
Which component is typically included in a Project Charter?
Detailed UI mockups
Network diagrams
Assumptions and constraints
Code repository links
SMART objectives must be:
Specific, Measurable, Achievable, Relevant, Time-bound
Simple, Modern, Accurate, Realistic, Timed
Strategic, Marketable, Accurate, Reliable, Timed
Short, Manageable, Achievable, Realistic, Technical
What does the Scope Statement primarily define?
The budget for each software module
What is included and excluded in the project
The roles of each project member
The project's marketing approach
Which of the following is an example of an Out-of-Scope item?
Core features included in the MVP
Tasks scheduled for the next project phase
Which section of the Project Charter identifies individuals with interest or influence in the project?
Assumptions
Stakeholders
Deliverables
Boundaries
What is the benefit of creating SMART objectives?
It guarantees that the project will finish on time
It makes objectives less strict and more flexible
It provides measurable and clearly defined project goals
It eliminates the need for project planning
Scope creep occurs when:
The team creates a detailed timeline
Unapproved features or tasks are added to the project
Project objectives follow the SMART format
The budget is allocated to system testing
Which of the following is typically listed under “Project Deliverables”?
Budget assumptions
Software prototypes or final system outputs
Team responsibilities
Stakeholder communication plans
Why is defining “Out-of-Scope” items important?
To identify who will manage the project
To limit unnecessary tasks and prevent expectation problems
To assign the project budget accurately
To ensure all features are included in the first release
What is the main purpose of a Work Breakdown Structure (WBS)?
To create a budget for the project
To decompose a project into smaller, manageable tasks
To assign roles to team members
To estimate project revenue
In a WBS, what does Level 1 represent?
The first task in the sequence
The main deliverable or final project output
The smallest work package
The project manager’s assigned tasks
Which of the following BEST describes a “work package”?
A final project deliverable
The smallest unit of work that can be managed and assigned
A list of all project risks
A tool used to track team attendance
Which dependency type means one task must finish before another can start?
Start-to-Start (SS)
Finish-to-Start (FS)
Finish-to-Finish (FF)
Start-to-Finish (SF)
“Testing cannot finish until development is complete.” This describes which dependency?
FS
SS
FF
SF
Which of the following is an example of a Start-to-Start (SS) dependency?
Coding must finish before testing can start
Testing must finish before deployment
Backend coding and database setup can start at the same time
Deployment can only finish after reviews begin
What tool MOST appropriate for visually creating a WBS?
Google Docs
Draw.io (diagrams.net)
Slack
SurveyMonkey
Why are task dependencies important in a WBS?
They help in identifying the budget requirements
They determine which tasks require more team members
They show the correct order in which tasks must occur
They reduce the number of project deliverables
Which of the following is part of the WBS creation process?
Conducting market research
Breaking down the project into smaller components
Designing the system architecture
Writing test scripts
In the WBS example for a mobile fitness app, which task should occur before testing?
UI design
App deployment
Backend API development
User training
What is the primary purpose of project scheduling in IT project management?
To increase project cost
To allocate resources, assign tasks, and track progress
To remove task dependencies
To shorten the organizational structure
A Gantt chart primarily shows which of the following?
Stakeholder roles and responsibilities
Visual timeline of tasks, durations, and dependencies
Project risks and impacts
Server performance metrics
In the Critical Path Method (CPM), which tasks determine the project’s minimum completion time?
Non-critical tasks
Tasks with float
Critical path tasks
Optional tasks
Which dependency type is the most common in scheduling?
Start-to-Start (SS)
Start-to-Finish (SF)
Finish-to-Finish (FF)
Finish-to-Start (FS)
A milestone on a Gantt chart is represented by which symbol?
Square
Circle
Which of the following BEST describes a non-critical task?
A task that must never be delayed
A task with float or flexibility
A task that belongs to the project manager
A task that has no dependencies
If “Testing” depends on the completion of “Backend Development,” this reflects which dependency?
SS
FF
FS
SF
Which step comes first when creating a Gantt chart?
Exporting the Gantt chart as a PDF
Listing all tasks
Assigning color codes
Adding milestones
Which tool is specifically recommended in this chapter for generating a detailed Gantt chart?
Microsoft Word
Canva
GanttProject
Slack
In CPM, what happens if a critical task is delayed by 3 days?
The project end date remains unchanged
Only non-critical tasks are affected
The entire project is delayed by 3 days
Dependencies are removed automatically