MTL2 Central Heating Learner Outcome 9

Total questions: 18

Worksheet time: 9mins

Name
Class
Date
1.

What is the best way to minimise heating downtime for customers?

a)

Drain the system early

b)

Work without informing the customer

c)

Carry out as much preparation work as possible before isolation

d)

Increase boiler temperature

2.

Why should final connections be made last when extending a system?

a)

To reduce pipe length

b)

To improve circulation

c)

To minimise the time the system is isolated

d)

To avoid flushing

3.

Why is customer communication important during decommissioning?

a)

It reduces paperwork

b)

It avoids regulations

c)

It allows customers to prepare for loss of heating

d)

It increases efficiency

4.

What should customers be told before heating is isolated?

a)

Radiator sizes

b)

Pipe material

c)

How long the system will be unavailable

d)

Boiler efficiency

5.

Why should customers be advised to collect water beforehand?

a)

To test water pressure

b)

To allow essential use during isolation

c)

To reduce draining time

d)

To protect the boiler

6.

What safety information should be provided before work begins?

a)

Programmer settings

b)

Radiator locations

c)

Which parts of the system will be worked on

d)

Pipe sizes

7.

What must be isolated first before draining a heating system?

a)

Water supply

b)

Gas supply

c)

Electrical supply

d)

Radiators

8.

Why should warning notices be placed at isolation points?

a)

To meet warranty rules

b)

To improve communication

c)

To prevent accidental system operation

d)

To protect pipework

9.

Which component is opened to allow air in during draining?

a)

Expansion vessel

b)

Filling loop

c)

Radiator air release valve

d)

Pump

10.

What should be done after permanently removing heating pipework?

a)

Leave pipes open

b)

Paint pipe ends

c)

Cap pipes at the nearest live connection

d)

Increase pressure

11.

Why must pipework be capped after removal?

a)

To improve flow

b)

To prevent stagnation and contamination

c)

To reduce heat loss

d)

To improve efficiency

12.

What should be done to flue openings after boiler removal?

a)

Leave open

b)

Cover with tape

c)

Make good the building fabric

d)

Insulate only

13.

Central heating water may be discharged to:

a)

Surface water drains

b)

Rainwater gullies

c)

Foul water drains

d)

Soakaways

14.

Why must heating water not be discharged into surface water drains?

a)

It is too hot

b)

It causes blockages

c)

It may cause environmental pollution

d)

It reduces pressure

15.

Which substance must NOT be present in water being discharged?

a)

Inhibitors

b)

Flux residue

c)

Glycol

d)

Sludge

16.

How can accidental operation of a system be prevented?

a)

Closing radiator valves

b)

Removing radiators

c)

Isolating and locking off supplies

d)

Increasing pressure

17.

Why should fuses be removed during decommissioning?

a)

To save energy

b)

To meet regulations

c)

To prevent electrical operation

d)

To improve safety labeling

18.

What should accompany system isolation points?

a)

Programmer

b)

Expansion vessel

c)

Warning notice

d)

Pressure gauge