
Quiz 5 - Cost Management Quiz
Presentation
•
Other
•
Professional Development
•
Practice Problem
•
Hard
JMartin Gtz
FREE Resource
20 Slides • 20 Questions
1
Multiple Choice
When developing the cost management plan, what tool or technique includes reviewing the different funding options that can be used to fund the project?
Meetings
Data Analysis
Expert Judgment
External Funding
2
3
Multiple Choice
While working on a multinational project, the project manager has decided to represent the project budget in American dollars, even though the project will span nine different countries. This will make the budget uniform and easier for the stakeholders to understand. Where will the project manager document the units of measurement for the budget?
Cost Management Plan
Funding Management Plan
Units of Measurement Plan
Currency Format Plan
4
5
Multiple Choice
Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more. What kind of estimate is this?
Definitive Estimate
Rough Order of Magnitude Estimate
Wide Estimate
Plan Estimate
6
7
Multiple Choice
Cost estimates for activities generally include the cost for labor, materials, equipment, services, and facilities. Which of the following statements is false regarding costs estimates?
Cost estimates are progressively elaborated
Cost estimates are best done by the project team
Cost estimates also includes the operational cost of the product
Cost estimates also include the contingency cost
8
9
Multiple Choice
While working on a game design project, the project sponsor has asked the project manager that to ensure that his estimates are very precise. What estimating technique should the project manager use?
Analogous Estimating
Bottom-up Estimating
Three-Point Estimating
Accuracy Estimating
10
11
Multiple Choice
The project manager and the project team determined that the budget for the project will be $60,000. That includes the cost for all the activities and all uncertainties that may have taken place during the project. The project cost baseline is $60,000. The sponsor has determined that if there is a need for additional funds, he will add an additional $5,000. The additional $5,000 represents what?
Contingency Reserves
Risk Reserves
Management Reserves
Sponsor Reserves
12
13
Multiple Choice
The project manager has worked with an expert project team to estimate the project’s cost. The project manager is very confident that the project will end at that budget. Where should the project manager document his or her confidence level of the cost estimate?
Cost Baseline
Cost Management Plan
Risk Register
Basis of Estimates
14
15
Multiple Choice
When determining the budget for a project, what tool should the project manager use to sum the cost of each work package to form the entire project budget?
Data Analysis
Decision Making
Cost Aggregation
WBS Aggregation
16
17
Multiple Choice
The project manager has just been told by the project sponsor that, due to a current recession in the stock market, the company will not be able to allocate all of the funds that the project will need for completion. What should the project manager do with this funding limit?
Implemented Change Requests
Reschedule the Project Work
Close the Project
Seek External Funding
18
19
Multiple Choice
The project manager has completed the process of determining budget. He has created the cost baseline, which will be added to the project management plan. The project manager is also aware of the project budget. What is the difference between the project budget and cost baseline?
The cost baseline includes the contingency and management reserves
The cost baseline only includes the management reserves
The cost baseline includes the contingency reserves and the project budget includes the management reserves
The cost baseline includes the management reserves and the project budget includes the contingency reserves
20
21
Multiple Choice
In the process of control costs, the project manager compares the project management plan with what other information?
Work Performance Data
Project Funding Requirements
Project Documents
Work Performance Reports
22
23
Multiple Choice
The project manager is currently evaluating how well the project is meeting the project budget. What earned value formula will be needed to determine if a project is on or over budget?
PV
AC
SV
SPI
24
25
Multiple Choice
The budget manager has completed the earned value analysis for the project. He has concluded that the CPI of the project is .9. Which of the following statements best describes this project?
Over Budget by 10%
Over Budget by 90%
On the Budget by 10%
Under Budget by 90%
26
27
Multiple Choice
The project manager has calculated the EV of the project to be $14,000 and the PV to be $16,000. The BAC is currently at $22,000. Which statement best describes this project?
The project is ahead of schedule
The project is on budget
The project is over budget
The project is behind schedule
28
29
Multiple Choice
While working on a multinational project with a budget of $90,000, the team has completed the design aspect of the project. You have calculated that the AC is $30,000 and the EV is $32,000. What is the EAC of this project?
$89,000
$92,804
$89,807
$84,906
30
31
Multiple Choice
When creating the cost baseline, the project manager uses an S-curve graph to represent the baseline. Which of the following statements is true about the S-curve?
It is a time phase view of the cost baseline
It is a time phase view of the project schedule
It is a time phase view of the project scope
It is used to create the project schedule
32
33
Multiple Choice
Which one of the following is FALSE about TCPI?
TCPI calculates the performance that must be achieved in order to meet financial or schedule goals
TCPI usually determines the status on the remaining work with respect to the funds remaining
If the cumulative CPI falls below the baseline plan, all future work must be performed at the TCPI to achieve the planned BAC
If the cumulative CPI falls below the baseline plan, all future work must be performed below the TCPI to achieve the planned BAC
34
35
Multiple Choice
Earned Value Management (EVM) would NOT be very beneficial in which situation?
To measure a project's progress against the project scope, cost, and schedule baselines
To forecast future performance and the project's completion date and final cost
To provide schedule and budget variances during the project
To develop the project cost baseline
36
37
Multiple Choice
While developing complex software, the project manager decided to bill the company by how many lines of codes it will take to write the software. What type of estimate best describes this scenario?
Bottom-up estimating
Analogous estimating
Parametric estimating
Three-point estimating
38
39
Multiple Choice
Which of the following statements would be considered false about a project that has an SPI of 1.2 and the CPI of .7?
The project is being crashed to be completed faster
The project is being fast track to completed faster
The project is ahead of schedule and over budget
A change request may be needed to correct the budget
40
When developing the cost management plan, what tool or technique includes reviewing the different funding options that can be used to fund the project?
Meetings
Data Analysis
Expert Judgment
External Funding
Show answer
Auto Play
Slide 1 / 40
MULTIPLE CHOICE
Similar Resources on Wayground
32 questions
Routines and Creativity
Presentation
•
University
33 questions
Have vs Have got
Presentation
•
Professional Development
33 questions
Chapter 2 Business Basics
Presentation
•
Professional Development
37 questions
Fractions to Decimals and Decimals to Fractions
Presentation
•
Professional Development
37 questions
Fraction Decimal
Presentation
•
Professional Development
35 questions
Greg's Birthday Quiz
Presentation
•
Professional Development
36 questions
DOL Wiring Standards Oct 1 -9
Presentation
•
KG - University
36 questions
Critical Thinking for Professional Success
Presentation
•
Professional Development
Popular Resources on Wayground
10 questions
Safety Day 2026 – Student Review
Quiz
•
9th Grade
21 questions
Continents and Oceans
Quiz
•
6th Grade
20 questions
Parts of Speech
Quiz
•
5th Grade
16 questions
Subject & Predicate
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
12 questions
Map Skills
Quiz
•
3rd Grade
22 questions
Continents and Oceans
Quiz
•
5th Grade
15 questions
Rounding Decimals
Quiz
•
5th Grade