Quiz 8: Communications Management Questions
Presentation
•
Other
•
Professional Development
•
Practice Problem
•
Hard
JMartin Gtz
FREE Resource
15 Slides • 15 Questions
1
Multiple Choice
One of the main goals of communications management is to…?
Prevent misunderstandings and miscommunications
Selections of the communications method
Determine which message to send
Collect the stakeholders requirements
2
Project communications management is about preventing misunderstandings and miscommunications. This is done through the careful selection of methods and the messages that are being sent by the project manager.
3
Multiple Choice
The project manager has decided that he will send the project status reports to the stakeholders using emails and memos. The stakeholders will not have to request any of the information; the project manager will just send it to them. What communication method does this illustrate?
Interactive Communications
Push Communication
Pull Communication
Give Communication
4
Push communication is when information is sent directly to the recipient. Interactive communication is a multidirectional exchange between the sender and receiver.
Pull communication is when the sender acquires the information at his or her own time using things such as a web portal.
5
Multiple Choice
During project communications the receiver is having difficulty understanding the message. Which of the following can cause a message not to be understood by the receiver?
Encoding
Decoding
Noise
Feedback
6
Noise generally interferes with the receiver’s ability to understand the message. Noise generally does not keep the sender from sending the message.
7
Multiple Choice
When selecting the correct communication technology, what should the project manager not be looking for?
Ease of use
Sensitivity of the information
Urgency for Information
Age of the Technology
8
Whether technology is new or old, as long as it meets the project’s needs, it will be sufficient.
9
Multiple Choice
The project manager has reviewed the stakeholder register and has concluded that there are 17 stakeholders on the project. After speaking with a few of them, he added four more stakeholders. How many communication channels are there currently on the project?
200
420
210
21
10
To get the answer correct, you will need to use the communications formula, which is N(N-1)/2. Replacing N with 21 stakeholders currently will give you 21(21-1)/2 = 210.
11
Multiple Choice
The project manager has completed the communications management plan. Which of the following choices would not be part of the communications management plan?
Who should receive project communications
What communications should be sent
A glossary of common terminology
The requirements for the project's scope
12
The requirements for the project’s scope are generally kept in the project scope statement, not the communication management plan.
13
Multiple Choice
The project manager is working on a multinational project and has met with the company’s senior management during a private meeting to discuss the project’s performance. They have indicated that they are very happy with the progress and would like the meetings to be shorter next time. What process best describes this scenario?
Plan Communications Management
Manage Communications
Control Communications
Monitor Communications
14
Manage communications is the process to ensure the timely and appropriate collection, creation, management, and disposition of project information. The project manager is currently updating the stakeholders on the progress of the project.
15
Multiple Choice
What is it called when a project manager builds a consensus and overcomes obstacles when managing a group?
Active Listening
Facilitation
Selective Listening
Meeting Management
16
Facilitation is building consensus and overcoming obstacles. This will lead to better group dynamics and maintaining interest among a group of people.
17
Multiple Choice
The project manager would like the team to actively listen during project meetings. How would the project manager know if active listening is taking place?
Acknowledging, clarifying, and confirming
Using eye contact and body language
Wheter someone is actively listening cannot be determined
Only using eye contact
18
Active listening generally involves acknowledging, clarifying and confirming information that is given.
19
Multiple Choice
When conducting the process of manage communication what does the project manager circulate to the stakeholders throughout the process?
Work Performance Data
work Performance Information
Work Performance Reports
Communication Management Plan
20
During the process of manage communications, the project manager will circulate the work performance report as specified in the communication management plan. Work performance reports are sometimes known as status reports or progress reports.
21
Multiple Choice
The project manager is giving a presentation to a large group of senior stakeholders. The project manager knows that his communication skills make a big difference during the presentation. What type of communication skills are gestures, tone of voice, and facial expressions?
Body Language
Presentation Skills
Body Skills
Nonverbal
22
Nonverbal communications include the appropriate body language used for transmitting meaningful information, generally through tone of voice, gestures, and facial expressions.
23
Multiple Choice
The project manager has collected many of the work performance data and has created the work performance report. The project manager distributes this status report according to the communication management plan. What tool best describes this?
Project Information Distribution
Project Report Distribution
Project Reporting
Project Data Distribution
24
Project reporting is a tool that is used to manage communication to collect and distribute project information. All other choices are not valid tools.
25
Multiple Choice
What does interacting with others to exchange information and develop contacts mean?
Meeting Management
Networking
Political Awareness
Cultural Awareness
26
Networking is a part of interpersonal and team skills in which you interact with others to exchange information and develop contacts.
27
Multiple Choice
The project manager is currently in the process of manage communications. During this process, what does the project manager do?
Conduct Project Communications
Gathering Communication Requirements
Changing the Communication Management Plan
Change in the Stakeholder Engagement Plan
28
The output of the process manage communications process is project communications, which include updating the stakeholders on the performance of the project.
Gathering communication requirements is done during the plan communications management process.
Manage communications does not have an output of changing requests, so changes in the communications and stakeholders’ management plan cannot be done in this process.
29
Multiple Choice
While conducting communication management on a project, the project manager has determined that the communication management plan is not adequate for the project, and many stakeholders have complained about the lack of communication. What should the project manager do next?
Create a change request
Hold a meeting
Do more networking
Speak with the project team
30
If a project manager determines that the communication management plan is inadequate for the project, the next step is to create a change request to change the plan to better match the communication needs of the project.
One of the main goals of communications management is to…?
Prevent misunderstandings and miscommunications
Selections of the communications method
Determine which message to send
Collect the stakeholders requirements
Show answer
Auto Play
Slide 1 / 30
MULTIPLE CHOICE
Similar Resources on Wayground
23 questions
Geology: Semester Recap 3°C
Presentation
•
Professional Development
23 questions
Understanding the function of Management- Leading & Controlling
Presentation
•
Professional Development
23 questions
Introduction Spurling's Hidden Treasures Riding Academy- SHTRA
Presentation
•
Professional Development
24 questions
Mentoring and Coaching
Presentation
•
Professional Development
24 questions
Coaching Skills
Presentation
•
Professional Development
24 questions
24.25 LPN Orientation Day 2
Presentation
•
Professional Development
21 questions
PE 3 M1
Presentation
•
Professional Development
23 questions
LDKS PRETEST 2020
Presentation
•
Professional Development
Popular Resources on Wayground
16 questions
Grade 3 Simulation Assessment 2
Quiz
•
3rd Grade
19 questions
HCS Grade 5 Simulation Assessment_1 2526sy
Quiz
•
5th Grade
10 questions
Cinco de Mayo Trivia Questions
Interactive video
•
3rd - 5th Grade
17 questions
HCS Grade 4 Simulation Assessment_2 2526sy
Quiz
•
4th Grade
24 questions
HCS Grade 5 Simulation Assessment_2 2526sy
Quiz
•
5th Grade
13 questions
Cinco de mayo
Interactive video
•
6th - 8th Grade
20 questions
Math Review
Quiz
•
3rd Grade
30 questions
GVMS House Trivia 2026
Quiz
•
6th - 8th Grade