
Quiz 9: Risk Management Quiz
Presentation
•
Other
•
Professional Development
•
Practice Problem
•
Hard
JMartin Gtz
FREE Resource
20 Slides • 20 Questions
1
Multiple Choice
A project manager has just started the risk management process on a project. Which of the following statements accurately describes the objectives of risk management on a project?
Risk management is done to increase the probability and/or impact of positive risks
Risk management is done to decrease the probability and/or impact of negative risks
Risk management is done to minimize all risks
Risk management is done to increase the probability and/or impact of positive risks and decrease the probability and/or impact of negative risks
2
The objectives of project risk management include increasing the probability and/or impact of positive risks and decreasing the probability and/or impact of negative risks.
3
Multiple Choice
While discussing risk management with a team member, what should the project manager say about the different risk levels?
There are two levels: individual project risks and overall project risks
There is only one level of risk: individual project risks
There is only one level of risk: overall project risks
There are two levels: project risks and operations risks
4
The risk management process in the PMBOK lists two levels of project risks: individual and overall project risks.
5
Multiple Choice
A team member stops the project manager during the meeting to ask about positive risks. Which of the following statements about positive risks is false?
Positive risks can lead to a shortened schedule
positive risks can lead to a longer schedule
Positive risks can lead to a smaller budget
Project risks lead to more customer satisfaction
6
Positive risks are also known as opportunities and will impact the project positively. This can include shortening the schedule budget and increasing customer satisfaction.
7
Multiple Choice
Which of the following statements is false in regard to how risk will affect the project?
Risk will continue to emerge during the lifetime of the project
Risks should be monitored and managed as the project progresses
Risk identification should only be done at the beginning of the project
Risk identification is done throughout the project
8
Risk identification is done throughout the project. As the project progresses, new risks will emerge and will have to be assessed by the project team.
9
Multiple Choice
What kind of risk is about uncertainties that exist regarding what might happen in the future and cannot be predicted currently, such as regulatory frameworks or the future development of technology?
Ambiguity Risks
Variability Risks
Project Resilience
Positive Risks
10
Ambiguity risks describe the uncertainty that exists about what might happen in the future and are very difficult to predict, such as future regulations or changes in technology.
11
Multiple Choice
The project manager knows that managing risks is an important part of a project. One of the most important aspects is documenting the stakeholders’ risk appetite. Where would the project manager document the stakeholders’ risk appetite?
In the stakeholder's engagement plan
In the scope management plan
In the risk management plan
In the risk register
12
The stakeholders’ risk appetite is documented and stored in the risk management plan. The stakeholders’ risk appetite is an important component of the plan, since it will help determine what risks will be acceptable.
13
Multiple Choice
Senior management within the organization has requested a brief overview of how the project conducts risk management. They would like to see the different categories of risk that can affect the project. What should the project manager show them?
the risk breakdown structure
The work breakdown structure
The resource breadown structure
The risk register
14
The risk breakdown structure is part of the risk management plan, and it shows the different categories of risk on a project.
15
Multiple Choice
During the process of Identify risks, the project manager has determined that the project team should be included as stakeholders who identifies risks for the project. Which of the following statement is true about this approach?
It will lead to a more thprpugh risk register
It is incorrect and the project manager should have all stakeholders identify risks
It would be easier to come up with the risk responses
It would be easier to implement the risk responses
16
During the process of identify risks, all project stakeholders should be encouraged to help identify individual project risks. This will lead to a more thorough risk register and include perspectives from all people affected by the project.
17
Multiple Choice
The project team is currently doing data analysis to help identify which risks can affect the project. What data analysis technique can they use to help determine if there are certain risks in the procurement agreement that can affect the project?
Root cause analysis
Assumption and constrain analysis
SWOT analysis
Document analysis
18
Document analysis is a structured review of the different project documents that could include contracts, agreements, and different parts of the project plan.
19
Multiple Choice
The project team has started to identify risks on the project. What method can they best use to identify both positive and negative risks while analyzing how the strength may offset threats and vice versa?
Root cause analysis
Assumption and constrain analysis
SWOT analysis
Document analysis
20
The SWOT analysis is done to identify the strengths, weaknesses, opportunities, and threats of a project. This strengths and opportunities are positive risks, and the weaknesses and threats are the negative risks. By putting this into a quadrant diagram, the project team can see how strengths may offset threats, and vice versa.
21
Multiple Choice
The project team members have finished identifying risks up to this point in the project. They have created the risk register, which lists all of the individual project risks. What should the team create next?
The risk management plan
The risk response plan
The risk report
The risk implementation plan
22
The risk report is generally created with the risk register or after the risk register. It includes information on the sources of overall project risks and a summary of information on the identified individual project risks.
23
Multiple Choice
The project manager has met with the legal department within the organization to be informed of a new regulation that was recently passed that may impact the project. The project manager has added this risk to the risk register. What process should the project manager do next?
Plan risk management
Perform quantitative risk analysis
Plan risk response
Monitor risks
24
Once a risk has been identified, the next step is to determine how the risks will impact the project. This can be done by either doing a qualitative and/or a quantitative analysis. Sometimes, these two analyses are done sequentially, in which case a qualitative analysis is done followed by a quantitative analysis, or they can be done in parallel. Do not respond to a risk if you do not understand how the risk will impact the project.
25
Multiple Choice
The project team members are reviewing the risk in the risk register to determine which risks will have the greatest impact on a project. One risk in particular has a very high impact but the team has determined that this risk should be ranked very low on the project. What statement best describes why this risk is ranked so low?
The probability of the risk occurring is low
The project team is not familiar with the risk
The risks will take place in the far future of the project
They're using the wrong methods to assess the risks
26
It is very likely that some risks may have a high impact and a low probability, which will lead to the risk being ranked very low. An example is an earthquake in New York City. The impact may be high, but the probability of it occurring may be very low, which leads to the risk being ranked lower.
27
Multiple Choice
The project team members are currently doing the process of perform qualitative risk analysis. They would like to use a tool that could not only display the probability of the risks or impact but the overall likelihood of the risks. What tool can be used to display the three parameters?
Probability and impact matrix
Probability and impact assessment
Bubble chart
Ishikawa diagram
28
A bubble chart is part of the tool data representation. It is used to display three dimensions of data.
All other choices may only displays two dimensions.
29
Multiple Choice
While conducting a brainstorming session with the team in order to rank the risks, the project manager is worried about the data the team is using to rank the risks. The project manager feels that some team members may only be speculating about what the probability of a risks would be. What tool can best help the project manager in this scenario?
Risk probability and impact assessment
Risk data quality assessment
Probability and impact matrix
Hierarchical charts
30
Risk data quality assessment evaluates the degree to which the data about the individual risks are accurate and reliable. If these data are not accurate then the entire assessment may be compromise and will not truly reflect the risk ranking on a project.
31
Multiple Choice
The project manager and team has determined that if a flood were to take place during the building renovation project, it would delay the project by 2 weeks and cost approximately $50,000 in damages. What process did the project manager and team complete to collect these data?
Perform qualitative risk analysis
Perform quantitative risk analysis
Identify risks
Plan risk response
32
Quantitative risk analysis is a numerical analysis of how the risk will impact the project. This is in contrast to a qualitative analysis, which would just rank the risks from the most important to the least important. The project team did not come up with a response to the flood risks in this scenario, so the choice cannot be to plan a risk response. Identify risk is used to create the risk register, and a risk report does not evaluate the risks.
33
Multiple Choice
The project team has identified, ranked, and determined how the risks will impact the project. One risk in particular is a new regulation that may pass and can have a severe effect on the project and on the entire organization. What risk response strategy would be best for the team to take?
Avoid
Tranfer
Mitigate
Escalate
34
Since this is a risk that will not just affect the project but the entire organization, the project team should escalate the risk toward a portfolio or the organization level. Let the organization’s legal department communicate with the project manager and determine how to respond.
35
Multiple Choice
The project team members are coming up with ways to respond to an opportunity that they feel will not likely happen. The opportunity is that the permit for the building renovation project comes earlier than its supposed six-week wait. Since the permit office is so backed up, the project team members have decided that if the permit does come earlier than 6 weeks, they will still start the work in 6 weeks. What risk response strategy does this illustrate?
Escalate
Exploit
Enhance
Accept
36
Acceptance of an opportunity is to take no proactive action before it happens. In this scenario, the team is making no proactive response. If the permit comes earlier, the team will still start the work in the 6 weeks that it would take for the permit to come normally.
37
Multiple Choice
While working on a 60-story skyscraper project, one supplier has informed the project manager that due to dangerous weather at the warehouse, the materials will be anywhere 1 to 2 months late. The project manager has already accounted for this risk and has decided to go with another supplier to get the materials. What process best illustrates this scenario?
Plan risk response
Monitor risks
Implement risk responses
Identify risks
38
In this scenario, the project manager is implementing the risk response. The project manager is not trying to identify risks or plan a response.
39
Multiple Choice
During the process of monitor risks, the project manager works with the organization to determine the effectiveness of the risk management processes. They have determined that the risk processes for the project are adequate and that no changes should be made. What tool best describes this?
Audits
Data Analysis
Meetings
Data Representation
40
Audits are done by the organization to determine the effectiveness of the risk management processes for a project.
A project manager has just started the risk management process on a project. Which of the following statements accurately describes the objectives of risk management on a project?
Risk management is done to increase the probability and/or impact of positive risks
Risk management is done to decrease the probability and/or impact of negative risks
Risk management is done to minimize all risks
Risk management is done to increase the probability and/or impact of positive risks and decrease the probability and/or impact of negative risks
Show answer
Auto Play
Slide 1 / 40
MULTIPLE CHOICE
Similar Resources on Wayground
33 questions
Have vs Have got
Presentation
•
Professional Development
33 questions
Chapter 2 Business Basics
Presentation
•
Professional Development
33 questions
Care Team Refresher Course
Presentation
•
KG
32 questions
Talking about Jobs and Business Environment
Presentation
•
Professional Development
35 questions
Greg's Birthday Quiz
Presentation
•
Professional Development
32 questions
CFA Trainer Authority
Presentation
•
Professional Development
36 questions
Critical Thinking for Professional Success
Presentation
•
Professional Development
32 questions
Routines and Creativity
Presentation
•
University
Popular Resources on Wayground
16 questions
Grade 3 Simulation Assessment 2
Quiz
•
3rd Grade
19 questions
HCS Grade 5 Simulation Assessment_1 2526sy
Quiz
•
5th Grade
10 questions
Cinco de Mayo Trivia Questions
Interactive video
•
3rd - 5th Grade
17 questions
HCS Grade 4 Simulation Assessment_2 2526sy
Quiz
•
4th Grade
24 questions
HCS Grade 5 Simulation Assessment_2 2526sy
Quiz
•
5th Grade
13 questions
Cinco de mayo
Interactive video
•
6th - 8th Grade
20 questions
Math Review
Quiz
•
3rd Grade
30 questions
GVMS House Trivia 2026
Quiz
•
6th - 8th Grade