Q&As ADDITIONAL PRACTICE QUESTIONS MIXED 1/2

Q&As ADDITIONAL PRACTICE QUESTIONS MIXED 1/2

Professional Development

25 Qs

quiz-placeholder

Similar activities

Deaf Awareness/BSL

Deaf Awareness/BSL

5th Grade - Professional Development

20 Qs

Post Test Pendampingan Guru Kreator

Post Test Pendampingan Guru Kreator

Professional Development

20 Qs

Cloud Conference 2019 - Advanced

Cloud Conference 2019 - Advanced

Professional Development

20 Qs

SUMMATIVE W4 WAVE19

SUMMATIVE W4 WAVE19

Professional Development

20 Qs

Ultimate office trivia quiz

Ultimate office trivia quiz

KG - Professional Development

25 Qs

KESELAMATAN DAN KESEHATAN KERJA (K3)

KESELAMATAN DAN KESEHATAN KERJA (K3)

Professional Development

20 Qs

Project Procurement Management

Project Procurement Management

Professional Development

20 Qs

DOCUMENT-INFORMATION SECURITY

DOCUMENT-INFORMATION SECURITY

Professional Development

20 Qs

Q&As ADDITIONAL PRACTICE QUESTIONS MIXED 1/2

Q&As ADDITIONAL PRACTICE QUESTIONS MIXED 1/2

Assessment

Quiz

Professional Development

Professional Development

Easy

Used 1+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

227. The project life cycle is best defined as:

The continuum of a project life cycle.

The phases that a product or service passes through from its start to its completion.

The series of phases that a project passes through from its start to completion.

The various ways requirements and plans are brought from a project charter to completion.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

228. Projects following more of the adaptive side of the project life cycle most closely follow the pattern of:

Sequential, iteration-based phases and continuous overlapping phases.

Sequential, iteration-based phases and sequential nonoverlapping phases.

Continuous overlapping phases and agile-based phases.

Agile-based phases and sequential, iteration-based phases.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

229. All of the following are Process Groups in adaptive environments EXCEPT:

Planning Process Group.

Monitoring and Controlling Process Group.

Scope Management Process Group.

Closing Process Group.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

230. Iterative, agile, and adaptive approaches track, review, and regulate progress and performance by maintaining:

A detailed to-do list

A backlog

A work breakdown structure

Work packages

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

231. _______________ life cycles develop a set of high-level plans for the initial requirements and progressively elaborate requirements to an appropriate level of detail for the planning cycle.

Predictive

Adaptive

Plan-driven

Program

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

232. Project Integration Management includes all of the following EXCEPT:

Prevention is preferred over inspection. It is better to design quality into deliverables, rather than to find quality issues during inspection. The cost of preventing mistakes is generally much less than the cost of correcting mistakes when they are found by inspection or during usage.

Projects and project management are integrative by nature, with most tasks involving more than one Knowledge Area.

The relationships of processes within and between the Project Management Process Groups are iterative.

Managing project performance and changes to the project activities.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

233. Project Scope Management includes all of the following EXCEPT:

Scope can refer to product scope (the features and functions that characterize a product, service, or result), or to project scope (the work performed to deliver a product, service, or result with the specified features and functions).

Projects and project management are integrative by nature, with most tasks involving more than one Knowledge Area

Project life cycles range along a continuum from predictive to adaptive or agile. In a life cycle that uses a predictive approach, the project deliverables are defined at the beginning of the project and any changes to the scope are progressively managed. In an adaptive or agile approach, the deliverables are developed over multiple iterations where a detailed scope is defined and approved for each iteration when it begins.

Completion of the project scope is measured against the project management plan. Completion of the product scope is measured against the product requirements.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?