PMP Question 100
Quiz
•
Other
•
Professional Development
•
Practice Problem
•
Medium
Edi Giyanto
Used 61+ times
FREE Resource
Enhance your content in a minute
100 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a routine analysis of the project's reserves, the project manager realizes that some project costs have been saved due to the project taking advantage of an unexpected opportunity to outsource several activities.
What should the project manager do with these saved costs?
A Record them as actual costs (AC)
B Add them to the contingency reserves
C Reduce them from the budget at completion
D Credit them to the procurement department
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are leading a software development project for an important client. For this project, you have elected to use a change-driven life cycle. Currently, you are about to lead an iteration planning meeting with the product owner and the development team.
What should you first accomplish at the start of the iteration?
A With the project scope determined during initial project planning, the scope must be controlled to prevent scope creep
B Disregard the fixed requirements and focus on those elements that are still evolving to determine the scope of the iteration
C Define and approve the detailed scope of the iteration
D Review and record lessons learned to correct processes and improve the performance of the upcoming iteration
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have replaced a project manager midway through project execution. You discover that although financial project reports that include CPI and SPI are prepared weekly, the financial database repository has never been updated.
Which tailoring consideration did your predecessor most likely miss earlier in the project?
A Project complexity
B Knowledge management
C Cost management plan
D Earned value management
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project execution, scheduling challenges have been experienced due to inclement weather that has resulted in multiple schedule variances. The project manager has noticed that a particular vendor is very flexible in scheduling their work. The project manager has found that the flexibility to adjust leads and lags is a particularly effective method for controlling the project schedule.
What should be done with this information?
A Updated in the lessons learned repository
B Noted in the schedule variance management plan
C Documented in the lessons learned register
D Included in the schedule baseline
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During product testing, a project team has discovered that some components did not meet government regulations established for the industry. Following the approved change request to repair the defects, the components have been fixed, and the team is ready to test the product again.
What documents should the team refer to while re-testing the product?
A Verified deliverables
B Resource requirements
C Approved change requests
D Quality improvement methods
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is having difficulty getting project team members to meet their weekly performance targets. The project manager has provided team training and team-building activities, but so far these and other efforts have been unsuccessful. The project manager would like to use a reward system to incentivize team members to meet their performance goals.
Which of the following strategies would be best?
A Give all team members a raise to help motivate them
B Give rewards to team members who meet their performance goals at the end of the project
C Hold a contest where team members can compete for prizes
D Consult the resource management plan
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are leading a project to design a car with new self-driving technology. During project planning, existing government regulations regarding the new technology were virtually non-existent. You identified this ambiguity risk during project planning and developed a risk response. Now, with the car ready for production, new regulations have been enacted. The new regulations are so complicated that you have trouble understanding them and their implications for the project.
What should you do next?
A Seek the opinion of a recognized expert to validate or modify the risk response
B Terminate the project since the new technology does not meet the new regulations
C Submit a change request to alter the scope baseline to accommodate the new regulations
D Proceed with the project and implemented the risk response as originally planned
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
100 questions
Brainrot Lyric Finish
Quiz
•
Professional Development
100 questions
KFRC ACAK#12
Quiz
•
Professional Development
100 questions
EMS103 CHAP 26-31
Quiz
•
Professional Development
100 questions
LPBank 100/8
Quiz
•
Professional Development
102 questions
Vocabulary and Grammar Quiz - MEGATHIL
Quiz
•
Professional Development
100 questions
0015: Roles of Local and State Health Agencies in Public Health
Quiz
•
Professional Development
98 questions
Revisão HTML CSS
Quiz
•
Professional Development
100 questions
TEACHER'S ASSESSMENT
Quiz
•
Professional Development
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Other
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
25 questions
Christmas Movies
Quiz
•
Professional Development
20 questions
Christmas Trivia
Quiz
•
Professional Development
15 questions
Fun Holiday Trivia
Quiz
•
Professional Development
25 questions
Name That Tune - Christmas
Quiz
•
Professional Development
29 questions
Christmas Song Emoji Pictionary
Quiz
•
Professional Development
9 questions
Holiday Movie Trivia
Lesson
•
Professional Development
34 questions
Winter Trivia
Quiz
•
Professional Development
