Project Management Cumulative Quiz One
Authored by Miranda File
Life Skills
10th Grade
Used 20+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
An employee has been asked to evaluate a project that is experiencing some performance challenges. She asked the project manager to call a meeting with the project sponsor. The project manager replies that he does not know who the project sponsor is. The employee decides to review the initial project document. Which document should she request?
business case
project baseline document
project charter
project plan
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which tool or technique would be useful when developing the project charter?
customer survey
expert judgement
PERT method
planning guide
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A customer calls the project manager and informs her of a minor change to a requirement on the project. What is the first thing that the project manager should do?
analyze the request and its costs on the project
ask the customer to provide a formal change request
instruct her team to implement the minor change
note the change in her weekly notes for review
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project manager is implementing a variety of approved changes to a project. Which would least likely be a type of approved change?
corrective action
defect repair
lessons learned
preventive action
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project manager has discovered that a project is outside the original scope. The project manager has requested a change to bring expected future performance of the project work back in line with the project management plan. What type of change implementation has the project manager requested?
corrective action
defect repair
lessons learned
preventive action
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Heather is working on a project to create a new running shoe. She is working with her stakeholders to decide the color combination for the shoe. Heather decides that they will vote, and everyone has to agree on the color combination. Heather is using which tool or technique to collect requirements?
dictatorship
majority
plurality
unanimity
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Steve is in charge of building a house, and he is currently working on the project scope statement. Steve has a budget of $250,000 and six months to finish building the house. These components would be listed under what section in the project scope statement?
project appearance criteria
project constraints
project deliverables
project exclusions
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?