PMP Exam Preparation Mocktest With Formula

Quiz
•
Professional Development
•
Professional Development
•
Hard
Gigih Suhartanto
Used 22+ times
FREE Resource
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?
55.70 percent
68.26 percent
95.46 percent
99.73 percent
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the expected duration of the work package?
45 weeks
70 weeks
90 weeks
140 weeks
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
What is the float for Activity G?
-2
0
1
4
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
–1
0
2
Cannot be determined
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
According to earned value analysis, the SV and status of the project described above is—
–$300; the project is ahead of schedule
+$8,000; the project is on schedule
+$200; the project is ahead of schedule
–$200; the project is behind schedule
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?
$12,500; the revised estimate for total project cost (based on performance thus far)
$10,000; the revised estimate for total project cost (based on performance thus far)
$12,500; the original project budget
$10,000; the original project budget
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is—
$150
–$150
–$350
–$500
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Project Management Fundamentals - Module 5

Quiz
•
Professional Development
10 questions
Project Closure

Quiz
•
Professional Development
11 questions
AUG 2022

Quiz
•
Professional Development
17 questions
ENGLISH CLASS EVALUATION

Quiz
•
Professional Development
15 questions
Scope Management Plan

Quiz
•
Professional Development
10 questions
10 soal campuran (June)

Quiz
•
Professional Development
11 questions
Basics of Project management

Quiz
•
Professional Development
10 questions
Just about Trains

Quiz
•
3rd Grade - Professio...
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade