Search Header Logo

PMP Exam Preparation Mocktest With Formula

Authored by Gigih Suhartanto

Professional Development

Professional Development

Used 23+ times

PMP Exam Preparation Mocktest With Formula
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?

55.70 percent

68.26 percent

95.46 percent

99.73 percent

2.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the expected duration of the work package?

45 weeks

70 weeks

90 weeks

140 weeks

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Media Image

What is the float for Activity G?

-2

0

1

4

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Media Image

If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?

–1

0

2

Cannot be determined

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:


PV = $2,200

EV = $2,000

AC = $2,500

BAC = $10,000


According to earned value analysis, the SV and status of the project described above is—

–$300; the project is ahead of schedule

+$8,000; the project is on schedule

+$200; the project is ahead of schedule

–$200; the project is behind schedule

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:


PV = $2,200

EV = $2,000

AC = $2,500

BAC = $10,000


What is the EAC for this project, and what does it represent?

$12,500; the revised estimate for total project cost (based on performance thus far)

$10,000; the revised estimate for total project cost (based on performance thus far)

$12,500; the original project budget

$10,000; the original project budget

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is—

$150

–$150

–$350

–$500

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?