PMP Exam Preparation Mocktest With Formula
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Hard
Gigih Suhartanto
Used 23+ times
FREE Resource
Enhance your content in a minute
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?
55.70 percent
68.26 percent
95.46 percent
99.73 percent
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the expected duration of the work package?
45 weeks
70 weeks
90 weeks
140 weeks
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
What is the float for Activity G?
-2
0
1
4
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
–1
0
2
Cannot be determined
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
According to earned value analysis, the SV and status of the project described above is—
–$300; the project is ahead of schedule
+$8,000; the project is on schedule
+$200; the project is ahead of schedule
–$200; the project is behind schedule
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?
$12,500; the revised estimate for total project cost (based on performance thus far)
$10,000; the revised estimate for total project cost (based on performance thus far)
$12,500; the original project budget
$10,000; the original project budget
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is—
$150
–$150
–$350
–$500
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Complete Recovery EQ DAY 2
Quiz
•
Professional Development
10 questions
INTELLIGENCE
Quiz
•
Professional Development
10 questions
ISQPC
Quiz
•
Professional Development
10 questions
Gujarat State
Quiz
•
KG - Professional Dev...
12 questions
Week 16 - Primary Survey Recap
Quiz
•
University - Professi...
12 questions
Recap Quiz 1
Quiz
•
Professional Development
16 questions
Noom | Day 3 - Enrollment
Quiz
•
Professional Development
13 questions
Anime 99
Quiz
•
9th Grade - Professio...
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
