POST TEST

POST TEST

Professional Development

15 Qs

quiz-placeholder

Similar activities

SI Units

SI Units

Professional Development

10 Qs

Perform Online Collaboration A

Perform Online Collaboration A

Professional Development

12 Qs

8D=PACE-Induction-Session-2

8D=PACE-Induction-Session-2

Professional Development

12 Qs

Marketing and Advertising

Marketing and Advertising

Professional Development

15 Qs

Plans & Maxis Device Contract

Plans & Maxis Device Contract

Professional Development

16 Qs

V20 Performance

V20 Performance

Professional Development

16 Qs

Workplace Inspection

Workplace Inspection

Professional Development

20 Qs

SBILD Kochi T20

SBILD Kochi T20

Professional Development

20 Qs

POST TEST

POST TEST

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Hard

Created by

Achmad Fuad

Used 25+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Dallas is a junior project manager for an IT consulting company. He has just started working on the budget for his software development project. But, he is not sure to include indirect costs such as legal expenses, maintenance expenses and other administrative costs in the project budget. Upon consulting an organizational expert, he learns that the indirect costs were never a part of the project budget in his organization before. However, he is required to document the assumptions in regard to exclusion of indirect expenses in the project budget. In order to document why the indirect costs are not part of the budget, Dallas must use:

Scope baseline
Cost performance baseline
Basis of estimates
Activity cost estimates

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Simulation, probabilistic, and ensemble are methods used in

Manage Project Team
Develop Project Team
Identify Stakeholders
Forecasting

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Brian is a junior project manager who has started planning for a rather complex project for the first time. He is trying to understand the details of work that will be performed by various people in the project. In order to avoid confusion, he would like to break the work progressively into smaller pieces in a logical way to manage the work more efficiently. This effort is known as:

Progressive elaboration
Decomposition
WBS definition
Division

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The process of identifying and documenting relationships among the project activities is called

Monte Carlo Analysis
Sequence Activities
Critical Path Analysis
Earned Value Analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager must learn to apply knowledge, tools, and techniques in a project. In addition to those tools, an effective project manager must possess which of the following characteristics:

All of the above
Performance
Knowledge
Personal effectiveness

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT an output of the Create WBS process?

Functional & Non-functional requirements
Code of account identifier & Description of work
Product scope description & Product acceptance criteria
Work breakdown structure (WBS)

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are running a Locomotive design project. Since you planned the manufacturing in two different locations, you would like to reduce the sensitivity of locomotive performance to sources of variation caused by manufacturing differences. You classify various factors like engine design, suspension, weight and change factors all at a time to determine the impact on the quality and use that information to design the best quality locomotive. The most appropriate tool to perform this analysis is known as:

Design of experiments
Benchmarking
Flow charts
Statistical sampling

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development