1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

New : An organization has recently started practicing Scrum. The Sprint Planning meetings have been taking a long time because the Scrum team members and stakeholders do not have the knowledge about the content or priority of the Product backlog items being considered. Whose responsibility is it prepare the Sprint Planning attendees to help with better discussions?

The Scrum Team.

Developers.

Scrum Master.

Product Owner.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The three pillars of Scrum are:

Planning, Inspection, Adaptation.

Watch, Learn and Develop.

Inspection, Transparency, Adaptation.

Planning, Develop, Test.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

New : The Sprint Retrospective occurs:

Is optional, flexible and can be scheduled based on the Scrum teams need.

After the Daily Scrum and before the next Sprint Review.

Before the Sprint Review and after the Sprint Planning.

After the Sprint Review and prior to the next Sprint Planning.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

At the Sprint Review, only the Developers should explain which Product Backlog items have been completed and what has not been “Done” to the key stakeholders as they have been working on these items.

False

True

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

New : Which activities does the accountability "functional manager" perform in Scrum?

Scrum has no such accountability as functional manager.

Lend their team members to the Scrum Team Leads as needed.

Monitor and manage the Developers in the Scrum Team.

Monitor everyone’s productivity.

6.

MULTIPLE SELECT QUESTION

1 min • 1 pt

New : Scrum Team A and Scrum Team B are working on the same Product. Team A has decided that their Sprint Length is going to be 4 weeks long. Team B has decided that their Sprint length is going to be 2 weeks long. Team A and Team B can: (Choose all that apply)

Have different Product Owner.

Have different Product Backlog.

Have different Sprint Lengths.

Have different Scrum Masters

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

New : The maximum length of a monthly Sprint Retrospective is:

8 hours for biweekly sprint. For shorter Sprints it is usually shorter.

3 hours.

4 hours for biweekly sprints.

4.5 hours.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?