1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. Project team member Boy has learned a new method to program the financial application by reading a book about functions in applications. What kind of knowledge is this?

A. Explicit
B. Tacit
C. Common
D. Programming

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

2. While executing a project, the project manager has learned that a vendor will delay the delivery of the server needed to implement the phone system. This problem will need to be resolved soon. What should the PM do first?

A. Update the project management plan

B. Update the issue log

C. Update the sponsor

D. Find the new vendor

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. A company has plans to improve one their products. They have started to work with Mary to get this project authorized by the board of directors. What is the output of this process?

A. Project Management Plan
B. Project Charter
C. Stakeholder register
D. Business Documents

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. When creating a project management plan what component will address how to approve changes on a project?

A. Change Approval Management Plan
B. Change Management Plan
C. Change Control Board Plan
D. Change Plans

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. A project team has just completed a major module in a new application. They were able to complete it in about half the time that was approved for them using a new method from a recent programmers’ publication. What should the project manager do first with this new programming method?

A. Update Project Management Plan
B. Update project sponsor about the work
C. Close the project or phase
D. Update learson learned register

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. While executing a large project for building a bridge, the PM has received a request that would affect the structure of the bridge and may need it to be completely redesigned. The change came from the local transportation department. What should the PM do next?

A, Stop all the work on the bridge
B. Review the change and how it will impact the overall project
C. Nothing to do
D. Inform the departement that work already started and they cannot stop

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. A phase of a long software development project has been completed. The phase was considered very successful: the team was able to complete the deliverables in about half the time and under budget. The deliverables were successfully transferred to the next phase of the project. What should the project manager do next for this phase?

A. Create final report
B. Close phase immediately
C. Update Project Management Plan
D. Iniate the next phase of the project

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?