SCRUM Simulation test 1

Authored by Beatriz Fonseca

Professional Development

Professional Development

Used 13+ times

SCRUM Simulation test 1
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

1. When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?

(Choose the best answer)

Whenever a team member can accommodate more work

At the Sprint Planning Event

Never. The entire Scrum Team is accountable for creating value every Sprint

During the Daily Scrum

2.

MULTIPLE SELECT QUESTION

3 mins • 1 pt

Who is on the Scrum Team

A. The Product Owner

A. The Scrum Master

A. Developers

A. Project Manager

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The CEO asks the Developers to add a “very important” item to a Sprint that is in progress. What should the Developers do?

(Choose the best answer)

A. Inform the other members of the Scrum Team so the team can decide what to do

A. Add the item to the next Sprint

A. Add the item to the current Sprint and drop an item of equal size

A. Add the item to the current Sprint without any adjustments

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The three pillars of empiricism are:

(Choose the best answer)

A. Respect for people, Kaizen, Eliminating Waste

A. Planning, Inspection, Adaptation

A. Planning, Demonstration, Retrospective

A. Inspection, Transparency, Adaptation

A. Transparency, Eliminating Waste, Kaizen

5.

MULTIPLE SELECT QUESTION

3 mins • 1 pt

Which Scrum events are timeboxed?

(Choose the best three answers)

A. Release Testing

A. Sprint Retrospective

A. Refinement

A. Sprint Planning

A. Sprint Review

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

When does a Developer become the sole owner of a Sprint Backlog item?

(Choose the best answer)

A. At the Sprint Planning event

A. During the Daily Scrum

A. Never. All Sprint Backlog items are “owned” by the developers on the Scrum Team even though each item may be implemented by an individual Developer

A. Whenever a team member can accommodate more work

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The length of a Sprint should be:

(Choose the best answer)

A. Short enough to keep the business risk acceptable to the Product Owner

A. Short enough to be able to synchronize the development work with other business events

A. One month or less

A. All of the above

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development