PMP Exam Preparation - Ch 9 and 12 -Resource and Procurement

PMP Exam Preparation - Ch 9 and 12 -Resource and Procurement

KG

10 Qs

quiz-placeholder

Similar activities

PMP Exam Preparation Mentoring Ch 4 Integration

PMP Exam Preparation Mentoring Ch 4 Integration

KG

10 Qs

Diplomado Intec - Ágil

Diplomado Intec - Ágil

Professional Development

15 Qs

PMP Exam - Study Group Ch Quality and Resources

PMP Exam - Study Group Ch Quality and Resources

KG

10 Qs

PMP Exam Mentoring Ch 8 Project Quality Management

PMP Exam Mentoring Ch 8 Project Quality Management

KG

10 Qs

Study Group PMP Exam Preparation Chapter 1, 2 and 3

Study Group PMP Exam Preparation Chapter 1, 2 and 3

KG

10 Qs

Study Group PMP Chapter 4  Project Integration Management

Study Group PMP Chapter 4 Project Integration Management

KG

10 Qs

Reviewer

Reviewer

University

10 Qs

PMP Exam Preparation Mentoring Chapter 1, 2, 3

PMP Exam Preparation Mentoring Chapter 1, 2, 3

KG

10 Qs

PMP Exam Preparation - Ch 9 and 12 -Resource and Procurement

PMP Exam Preparation - Ch 9 and 12 -Resource and Procurement

Assessment

Quiz

Education

KG

Medium

Created by

quiz eNetwoQ

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1. The project manager has met with the team, and they are currently deciding whether they should develop internal software to meet the needs of the project sponsor or purchase external commercial software. What process are they currently engaged in?
A. Plan Procurement Management
B. Conduct Procurement
C. Control Procurement
D. Make or Buy Analysis

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2. The project manager has negotiated a fixed-price contract with a steel supplier. The contract is for 4 years. The seller has requested that the cost be increased by 4% every year due to inflation and fuel costs. What type of contract should the project manager use?
A. Firm Fixed Price
B. Fixed Price Incentive
C. Fixed Price Economic Price Adjustment
D. Cost Plus Fixed Fee

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3. As the project manager is getting ready to send out the request for proposals for the project, he contacts the PMO for a list of properly vetted sellers. What is the name of this list?
A. Qualified Seller List
B. Pre-qualified Seller list
C. Pre-approved selelr list
D. Approved seller list

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4. The project manager and the team have come up with a few different criteria they will use when selecting a seller. The criteria include costs, qualifications, licenses, and financial stability of the seller. What best describes these criteria?

A. Procurement Documents

B. Agreement

C. Request for Proposal

D. Source Selection Criteria

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. While working on the office renovation project, the project manager has received multiple bids from different vendors. What the project manager thought would be a cost-effective contract turned out to be very expensive. The project manager then hires a professional estimator to determine what the contract should cost. What is the project manager looking for?

A. Outside estimate

B. Building Cost estimate

C. Independent Cost Estimate

D. PMO

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. Two project team members have had frequent clashes, which have at times resulted in shouting matches during teammeetings. The project manager has intervened, asked them to resolve their differences, and even facilitated a meetingbetween them, but things have gotten worse. The project manager is concerned that the situation is negatively affecting teamcohesion and is placing the successful completion of the project at risk.

What should the project manager do next?

A. Use formal procedures including disciplinary actions

B. Allow the team members to resolve their differences on their own

C. Facilitate another meeting between the two team members

D. Request that the other project team members intercede as a form of peer pressure

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. Late in a project, a key team member leaves the company. The project manager realizes that he does not have enough teammembers to meet the hard deadline. At a weekly status meeting, the project manager discusses several options with hisproject team, including authorizing additional overtime, hiring subcontractors, or bringing in additional resources from anotherproject team within the company.

Which resource management technique does the project manager use?

A. Cost-benefit analysis

B. Alternatives analysis

C. Problem solving

D. Interpersonal skills

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?