Quarry operational plan

Authored by soheil mehr

Professional Development

1st - 3rd Grade

Used 1+ times

Quarry operational plan
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the name of the Quarry operational plan?

QOP

Albion park Quarry extension

Albion park Bypass

Nowra Bridge

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where is the location of the Quarry?

Port kembla office

Home

sand Quarry

East west link road

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What stages of the quarry does the document refer to?

3&4

2&3

4

1

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

what is the PROJECT NOISE EMISSION LIMITS for stage 3&4 on the The Hill” residence (Dunster premises)?

40

38

45

30

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Operating Hours for weekdays?

6am-4pm

7am-5.30pm

7.30am-5.30pm

6.30am-4.30pm

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Within how many days of detecting an exceedance of a noise limit,

the exceedance is to be reported to EPA, the Secretary of the DPE and the

owner of the property?

7days

5days

4days

3days

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the event of any exceedance of relevant criteria, the matter will immediately be brought to attention of who?

Safety officer

blasting subcontractor

Your mate

the attention of the Quarry Production Manager

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?