Project Procurement Management 2022

Project Procurement Management 2022

Professional Development

20 Qs

quiz-placeholder

Similar activities

PMIS Training

PMIS Training

Professional Development

15 Qs

PMP Questions 6th Edition Quiz 2

PMP Questions 6th Edition Quiz 2

Professional Development

20 Qs

November W III - 1

November W III - 1

Professional Development

15 Qs

Project Procurement Management

Project Procurement Management

Professional Development

20 Qs

PMP Procurement Exercise

PMP Procurement Exercise

Professional Development

20 Qs

POST TEST Pelatihan E-Procurement

POST TEST Pelatihan E-Procurement

Professional Development

20 Qs

Quiziz Week 3 Day 2

Quiziz Week 3 Day 2

Professional Development

20 Qs

Alestra Diagnóstico

Alestra Diagnóstico

Professional Development

15 Qs

Project Procurement Management 2022

Project Procurement Management 2022

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Gigih Suhartanto

Used 42+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

Once signed, a contract i slegally binding unless:

One party is unable to perform.

One party is unable to finance its part of the work.

It is in violation of applicable law.

It is declared null and void by either party's legal councel.

2.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

You are advising another project manager who is starting his first agile project. In addition to the development tea, he would like to use subcontractors for some parts of the work, but he isn't sure how to define the acceptance criteria. Which statement would you advise him to include in the contract?

"The completed deliverables must be fit for business purpose."

"The delivery date may vary as long as all required scope is completed."

"The completed deliverables must match the original specification."

"The quality of the completed deliverable must pass UI Testing."

3.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

Your organization is transitioning to an agile approach. You have been asked to review the company's existing standard procurement contracts and revise them as needed to reflect the new project approach. What is one of the key adjustments you want to make?

Reduce the time allowance for meeting and planning activities with the team.

Add more flexibility for adjusting the iterative delivery deadlines.

Increase the customer's involvement in prioritising and reviewing the deliverables.

Improve the standards for providing clear, detailed specification.

4.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

A project manager for the seller is told by her management that the project team should do whatever possible to be awarded incentive money. The primary objective of incentive clause in a contract is to:

Reduce cost for the buyer.

Help the seller control costs.

Synchronize objectives.

Reduce risk for for the seller by shifting risk to the buyer.

5.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

All the following statements about change control are incorrect except:

A fixed-price contract will minimize the need for change control.

Changes seldom provide real benefits to the project.

Contract should include procedures to accomodate changes.

More detailed specifications eliminate the cause of changes.

6.

MULTIPLE CHOICE QUESTION

5 mins • 5 pts

A seller is working on a cost-reimbursable (CR) contract when the buyer decides he would like to expand the scope of services and change to a fixed-price (FP) contract. All the following are the seller's options except:

Completing the original work on a cost-reimbursable basis and then negotiating a fixed-price for the additional work.

Completing the original work and rejecting the additional work.

Negotiating a fixed-price contract that includes all the work.

Starting over with a new contract.

7.

MULTIPLE CHOICE QUESTION

3 mins • 5 pts

Which of the following best describes the project manager's role in the procurement process?

The project manager has only minor involvement.

The project manager should be the negotiator.

The project manager should provide an understanding of the risks of the project.

The project manager should tell the contract manager how the contracting process should behandled.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?