Project Controls PC 12 Rev 02

Project Controls PC 12 Rev 02

1st Grade

10 Qs

quiz-placeholder

Similar activities

WAZE ADS

WAZE ADS

1st - 3rd Grade

10 Qs

RMP - 6. MONITOR & CLOSE RISK

RMP - 6. MONITOR & CLOSE RISK

1st Grade

14 Qs

CO

CO

1st Grade

10 Qs

PMI-SH Plan and Manage Quality of Products/deliverables

PMI-SH Plan and Manage Quality of Products/deliverables

1st Grade

13 Qs

WISE Budgeting Vocabulary (Porzio)

WISE Budgeting Vocabulary (Porzio)

KG - University

14 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

21-04-20

21-04-20

KG - Professional Development

7 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

Project Controls PC 12 Rev 02

Project Controls PC 12 Rev 02

Assessment

Quiz

Professional Development

1st Grade

Easy

Created by

Gary Carr

Used 11+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which analysis reviews the differences (or variables) between planned and actual performance.

Monte Carlo Analysis

Change Analysis

Variance Analysis

All options

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Variance is a quantifiable deviation, departure, or divergence away from a known baseline or expected value?

True

False

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion is known as ?

Budget at Completion

Schedule Performance Index

Variance at Completion

Cost Performance Index

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In respect of Monitoring & Controlling the Health of a Project Inefficient buying & Untimely buying are both causes of what?

Budget and schedule variance

Bill of Materials

H&S Analysis

Formal Change Process

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The best way to manage variances is to have monthly reports and regular meetings to discuss these discrepancies with management and department heads.

This also allows you to hold specific managers accountable for minimizing budget variance. Request a copy of the most recent budget.

True

False

Only on complex projects

Only during a Safety Audit

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

(Actual price - Standard price) x Actual quantity = ?

Key Performance Indicator

Bill of Materials

Purchase price variance

None of the Options Listed

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Linear Lists showing Month to Month or Year to Year cost Analysis to define trends is also known as ?

Horizontal Analysis

Vertical Analysis

Scatter Diagram

Fishbone Diagram

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?