U1 PM1 Unit 1 Review
Authored by Bobbie Jones
Business
9th - 12th Grade
Used 27+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
21 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After the prom, the student planning committee meets to discuss what activities went well and what activities would need to be changed next time. What project management process stage is the committee in?
initiating
executing
monitoring and controlling
closing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?
initiating
executing
monitoring and controlling
closing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Joe holds a team meeting to discuss lessons learned. He is in which process stage?
planning
executing
monitoring and controlling
closing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The organizational structure in which the project manager has the greatest amount of authority is a:
composite organization.
functional organization.
matrix organization.
projectized organization.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sierra is visiting and calling venues to see who is available to host her parents' anniversary party. What process stage is she in?
planning
executing
monitoring and controlling
closing
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After a wedding, Christina meets with the newlyweds to deliver the photographs she took and get the customer's signature and payment for the work done. Which process stage is Christina in?
planning
executing
monitoring and controlling
closing
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Jeff is a science teacher and Celeste is a computer programming teacher at a high school. The school they work in allows them to co-teach lessons based on their area of expertise. Their students are creating a program to anticipate the temperature based on measurements taken for an ecosystem prediction project. Jeff and Celeste work in which type of an organizational structure?
composite organization
functional organization
matrix organization
projectized organization
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?