21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After the prom, the student planning committee meets to discuss what activities went well and what activities would need to be changed next time. What project management process stage is the committee in?

initiating

executing

monitoring and controlling

closing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?

initiating

executing

monitoring and controlling

closing

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Joe holds a team meeting to discuss lessons learned. He is in which process stage?

planning

executing

monitoring and controlling

closing

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The organizational structure in which the project manager has the greatest amount of authority is a:

composite organization.

functional organization.

matrix organization.

projectized organization.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Sierra is visiting and calling venues to see who is available to host her parents' anniversary party. What process stage is she in?

planning

executing

monitoring and controlling

closing

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After a wedding, Christina meets with the newlyweds to deliver the photographs she took and get the customer's signature and payment for the work done. Which process stage is Christina in?

planning

executing

monitoring and controlling

closing

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Jeff is a science teacher and Celeste is a computer programming teacher at a high school. The school they work in allows them to co-teach lessons based on their area of expertise. Their students are creating a program to anticipate the temperature based on measurements taken for an ecosystem prediction project. Jeff and Celeste work in which type of an organizational structure?

composite organization

functional organization

matrix organization

projectized organization

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?