Practice Exam 2 Part 2

Quiz
•
Professional Development
•
Professional Development
•
Hard
Michael Myers
Used 3+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Large organizations typically manage a wide range of projects; from small projects to large initiatives requiring long-term commitments. Which of the following factors can be used in scaling such projects:
Team size, geographical distribution, regulatory compliance, organizational complexity, technical complexity, and funds availability.
Team size, geographical distribution, regulatory compliance and organizational complexity.
Team size, geographical distribution and regulatory compliance.
Team size, geographical distribution, regulatory compliance, organizational complexity and technical complexity.
Answer explanation
In large organizations, there may be a mixture of small projects and large initiatives requiring long-term commitments to manage these programs using scaling factors such as team size, geographical distribution, regulatory compliance, organizational complexity, and technical complexity. Funds availability is a constraint applicable to all projects.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a part of the data gathering tools used in Control Quality process?
Checklists
Control Chart
Check sheets
Statistical Sampling
Answer explanation
Control chart is a monitoring tool, while the rest of the choices are valid data gathering tools used during Control Quality process.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Measuring the quality of items in a sample on a pass/fail basis is:
Biased sampling
Variable sampling
Stratified sampling
Attribute sampling
Answer explanation
Attribute sampling measures the quality of items in a sample on a pass/fail basis; variable sampling measures the quality on a continuous scale.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
George is managing a telecommunication network deployment project. Most of the key project stakeholders are happy with the project so far. However, George has some potential concerns that might become issues in the near future. The next project status update meeting with the key stakeholders is the next day. What should George do?
Wait until the concerns become issues
Discuss these concerns with the key stakeholders
Do not report the concerns in the next meeting but try to mitigate these concerns
Briefly discuss these concerns in the next meeting but do not make them look significant
Answer explanation
Effective stakeholder management requires addressing potential concerns that have not yet become issues and anticipating future problems that may be raised by stakeholders. Such concerns need to be identified and discussed as soon as possible to assess associated project risks.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
On-demand scheduling is one of the techniques used in agile projects. This type of scheduling relies on:
A schedule that was developed previously for the development of the project increments.
Discretionary dependencies that cannot be changed by the project team.
Skills of the project manager rather than the skills of the team.
A backlog or intermediate queue of work to be done.
Answer explanation
On-demand scheduling does not rely on a schedule that was developed previously for the development of the product or product increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately as resources become available.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Midway through a project, a project manager determined the project was running far behind schedule. If the project manager needs to shorten the project schedule without changing the project scope, which of the following schedule compression techniques could he use?
Crashing
Reserve Analysis
Forecasting
Last Tracking
Answer explanation
Crashing is a technique that can be applied to compress the project schedule without changing the project scope. Another option is fast tracking.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
At the end of a project, what will your schedule variance be equal to?
Zero
Equal to the total PV
One
Equal to the total EV
Answer explanation
The schedule variance is the earned value minus the planned value. At the end of the project, all of the planned values should be earned, and the difference should be zero.
Create a free account and access millions of resources
Similar Resources on Wayground
5 questions
SV, CV, SPI, CPI - Assignment

Quiz
•
Professional Development
10 questions
Communication 10 soal (Chapter 10)

Quiz
•
Professional Development
10 questions
SG20_Test_S9_CH8&11 Quality & Risk

Quiz
•
Professional Development
15 questions
Introduction to Project Management for MT Nestle

Quiz
•
Professional Development
10 questions
Project Closure

Quiz
•
Professional Development
10 questions
Quiziz Week 2 Day 1

Quiz
•
Professional Development
12 questions
Agile Mindset Quiz

Quiz
•
Professional Development
10 questions
Project Management Master Class 1

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade