Practice Exam 2 Part 2
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Hard
Michael Myers
Used 3+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Large organizations typically manage a wide range of projects; from small projects to large initiatives requiring long-term commitments. Which of the following factors can be used in scaling such projects:
Team size, geographical distribution, regulatory compliance, organizational complexity, technical complexity, and funds availability.
Team size, geographical distribution, regulatory compliance and organizational complexity.
Team size, geographical distribution and regulatory compliance.
Team size, geographical distribution, regulatory compliance, organizational complexity and technical complexity.
Answer explanation
In large organizations, there may be a mixture of small projects and large initiatives requiring long-term commitments to manage these programs using scaling factors such as team size, geographical distribution, regulatory compliance, organizational complexity, and technical complexity. Funds availability is a constraint applicable to all projects.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a part of the data gathering tools used in Control Quality process?
Checklists
Control Chart
Check sheets
Statistical Sampling
Answer explanation
Control chart is a monitoring tool, while the rest of the choices are valid data gathering tools used during Control Quality process.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Measuring the quality of items in a sample on a pass/fail basis is:
Biased sampling
Variable sampling
Stratified sampling
Attribute sampling
Answer explanation
Attribute sampling measures the quality of items in a sample on a pass/fail basis; variable sampling measures the quality on a continuous scale.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
George is managing a telecommunication network deployment project. Most of the key project stakeholders are happy with the project so far. However, George has some potential concerns that might become issues in the near future. The next project status update meeting with the key stakeholders is the next day. What should George do?
Wait until the concerns become issues
Discuss these concerns with the key stakeholders
Do not report the concerns in the next meeting but try to mitigate these concerns
Briefly discuss these concerns in the next meeting but do not make them look significant
Answer explanation
Effective stakeholder management requires addressing potential concerns that have not yet become issues and anticipating future problems that may be raised by stakeholders. Such concerns need to be identified and discussed as soon as possible to assess associated project risks.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
On-demand scheduling is one of the techniques used in agile projects. This type of scheduling relies on:
A schedule that was developed previously for the development of the project increments.
Discretionary dependencies that cannot be changed by the project team.
Skills of the project manager rather than the skills of the team.
A backlog or intermediate queue of work to be done.
Answer explanation
On-demand scheduling does not rely on a schedule that was developed previously for the development of the product or product increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately as resources become available.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Midway through a project, a project manager determined the project was running far behind schedule. If the project manager needs to shorten the project schedule without changing the project scope, which of the following schedule compression techniques could he use?
Crashing
Reserve Analysis
Forecasting
Last Tracking
Answer explanation
Crashing is a technique that can be applied to compress the project schedule without changing the project scope. Another option is fast tracking.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
At the end of a project, what will your schedule variance be equal to?
Zero
Equal to the total PV
One
Equal to the total EV
Answer explanation
The schedule variance is the earned value minus the planned value. At the end of the project, all of the planned values should be earned, and the difference should be zero.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
Accepting Change Quiz
Quiz
•
Professional Development
15 questions
Breakthrough Performance
Quiz
•
Professional Development
10 questions
UTS Part 2
Quiz
•
Professional Development
10 questions
Health and safety revision.
Quiz
•
Professional Development
15 questions
Supervisory Management Development
Quiz
•
Professional Development
12 questions
AZURE WALKTHROUGH QUIZ 2
Quiz
•
Professional Development
15 questions
Agile
Quiz
•
Professional Development
12 questions
Gala Quizz-2
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade
