Practice Exam 2 Part 2

Practice Exam 2 Part 2

Professional Development

10 Qs

quiz-placeholder

Similar activities

November W-2 III

November W-2 III

Professional Development

15 Qs

Drilling Quiz W-2/II

Drilling Quiz W-2/II

Professional Development

10 Qs

General Mindset 2

General Mindset 2

Professional Development

13 Qs

SCRUM quiz

SCRUM quiz

University - Professional Development

10 Qs

November W III - II

November W III - II

Professional Development

15 Qs

TIAPMP

TIAPMP

Professional Development

10 Qs

Project Closure

Project Closure

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Practice Exam 2 Part 2

Practice Exam 2 Part 2

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Michael Myers

Used 3+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Large organizations typically manage a wide range of projects; from small projects to large initiatives requiring long-term commitments. Which of the following factors can be used in scaling such projects:

Team size, geographical distribution, regulatory compliance, organizational complexity, technical complexity, and funds availability.

Team size, geographical distribution, regulatory compliance and organizational complexity.

Team size, geographical distribution and regulatory compliance.

Team size, geographical distribution, regulatory compliance, organizational complexity and technical complexity.

Answer explanation

In large organizations, there may be a mixture of small projects and large initiatives requiring long-term commitments to manage these programs using scaling factors such as team size, geographical distribution, regulatory compliance, organizational complexity, and technical complexity. Funds availability is a constraint applicable to all projects.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a part of the data gathering tools used in Control Quality process?

Checklists

Control Chart

Check sheets

Statistical Sampling

Answer explanation

Control chart is a monitoring tool, while the rest of the choices are valid data gathering tools used during Control Quality process.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Measuring the quality of items in a sample on a pass/fail basis is:

Biased sampling

Variable sampling

Stratified sampling

Attribute sampling

Answer explanation

Attribute sampling measures the quality of items in a sample on a pass/fail basis; variable sampling measures the quality on a continuous scale.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

George is managing a telecommunication network deployment project. Most of the key project stakeholders are happy with the project so far. However, George has some potential concerns that might become issues in the near future. The next project status update meeting with the key stakeholders is the next day. What should George do?

Wait until the concerns become issues

Discuss these concerns with the key stakeholders

Do not report the concerns in the next meeting but try to mitigate these concerns

Briefly discuss these concerns in the next meeting but do not make them look significant

Answer explanation

Effective stakeholder management requires addressing potential concerns that have not yet become issues and anticipating future problems that may be raised by stakeholders. Such concerns need to be identified and discussed as soon as possible to assess associated project risks.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

On-demand scheduling is one of the techniques used in agile projects. This type of scheduling relies on:

A schedule that was developed previously for the development of the project increments.

Discretionary dependencies that cannot be changed by the project team.

Skills of the project manager rather than the skills of the team.

A backlog or intermediate queue of work to be done.

Answer explanation

On-demand scheduling does not rely on a schedule that was developed previously for the development of the product or product increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately as resources become available.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Midway through a project, a project manager determined the project was running far behind schedule. If the project manager needs to shorten the project schedule without changing the project scope, which of the following schedule compression techniques could he use?

Crashing

Reserve Analysis

Forecasting

Last Tracking

Answer explanation

Crashing is a technique that can be applied to compress the project schedule without changing the project scope. Another option is fast tracking.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At the end of a project, what will your schedule variance be equal to?

Zero

Equal to the total PV

One

Equal to the total EV

Answer explanation

The schedule variance is the earned value minus the planned value. At the end of the project, all of the planned values should be earned, and the difference should be zero.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?