Project objectives are.....
HVAC project preplanning

Quiz
•
Professional Development
•
University
•
Hard
nisya ghani
Used 1+ times
FREE Resource
9 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A critical element of a project
management
An element to measure or evaluate
project
An outline for what happening in
project once it successful
An outline for what happening in
project once it successful
2.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Project goals are.....
A critical element of a project
management
An element to measure or evaluate
project
An outline for what happening in
project once it successful
An outline for what happening in
project once it successful
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
there is two type of cost
direct field cost
overview cost
direct cost
indirect field cost
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many stages in value engineering
6
5
9
3
5.
FILL IN THE BLANK QUESTION
1 min • 1 pt
‘Project planning’ is all about ................. and.................
effective policies and methodologies to attain project
objectives. preparing a project for investment by
developing it determines the duties or activities necessary
to complete the project's goals
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
long lead times equipment is referring to ...................., ..................... and ....................... that are recognized early in a project to have a delivery time long enough to
directly influence the entire lead time of a project.
equipments
machine
systems
goods
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
the right order in creating critical path method (CPM)
list task, identify task sequence, network diagram, identify CPM, estimate task duration, and calculate float
list task, network diagram, estimate task duration, identify CPM and calculate float
list task, identify task sequence, network diagram, estimate task duration, identify CPM and calculate float
list task, identify task sequence, network diagram, estimate task duration and identify CPM
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
how many stages in project planning
5
7
6
8
9.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
There are only two (2) types of task dependencies in the Predecessor field.
true
false
Similar Resources on Wayground
10 questions
untitled

Quiz
•
University
10 questions
PMP- Scope (Basics)-Green Book

Quiz
•
University
12 questions
Product Based Planning (PBP) Quiz

Quiz
•
12th Grade - University
10 questions
Student Induction - Rules & Regulations

Quiz
•
University
13 questions
Time Management by Gabika and Simon

Quiz
•
University
12 questions
STRATEGIC INNOVATION

Quiz
•
University
10 questions
DPAABM – CFHP BM 2024 – Exercício 1

Quiz
•
2nd Grade - University
10 questions
Basic BPMN concepts

Quiz
•
University
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade