An architect is creating the workplan and schedule for a 3,200-square-foot tenant infill project. The project will have a documentation phase and a construction phase. The architect's fee is $20,000 and the project must be ready for permit in six weeks.

2-2 Project Work Planning

Quiz
•
Architecture
•
University
•
Hard

Centari Rodriguez
Used 1+ times
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Critical path method
Milestone chart
Fast-track schedule
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Early in the construction document phase of a building renovation project, a mechanical engineer alerts the project manager that the architect has improperly classified the use of the space. The architect will need to revise the use of the space so that the mechanical engineer can correctly size a large portion of the HVAC system and revise the distribution duct layout.
What should the architect do first to address the improper classification?
Submit a request for additional services.
Take corrective actions to modify the project work plan.
Identify the impact on the previous construction cost estimate.
Advise the owner of the design conditions and their impact on the schedule.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Refer to the exhibit.
An architect planned $350,000 in labor costs and 2,800 hours for the construction documents phase of a project. The project is now at 25% construction documents.
How should the architect keep the project within budget?
Continue to work at the current pace for the remainder of the phase.
Use more experienced staff to reduce labor hours for the remainder of the phase.
Reduce the time planned for documentation quality control to meet the project deadline.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Early in the construction documents phase of a project, a fire protection engineer alerts the architect that the architect improperly classified the materials planned to be stored in a warehouse space. The architect will need to revise the analysis of the materials so that the fire protection engineer can correctly plan sprinkler coverage and fire pump sizing.
What should the architect do first to respond to the lack of coordination?
Develop and submit a request for additional services.
Identify and take corrective actions to modify the project work plan.
Advise the owner of the design conditions and any impact on the schedule.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is contracted with an owner using an AIA B101 agreement. During construction, the owner informs the architect in writing to change the configuration of the restrooms. The architect responds that this work will require a $2,000 fee and one week will be required to make changes to the drawings. The owner agrees to the fee and timeline, noting an urgency to complete the work. What should the architect do next?
Invoice the owner for the added service and confirm receipt of the payment before starting the work.
Begin the work immediately and issue an add service proposal to formalize the change in scope.
Provide an add service proposal for the owner's signature prior to starting the work.
6.
FILL IN THE BLANK QUESTION
1 min • 1 pt
An owner asks the architect to reduce the production portion of each project phase with a client review and approval activity by one week. In addition, the owner requests the client review and approval time at each phase be extended by three weeks. Project phases follow: Programming: 8 weeks Schematic Design: 8 weeks Design Development: 12 weeks Construction Documents: 16 weeks Bidding/Negotiation: 6 weeks Construction Contract Administration: 56 weeks By how many weeks should the architect extend the overall schedule?
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Refer to the exhibit.
An architect develops a proposed schedule prior to the beginning of design. After the schedule is developed, the following changes occur: One week is added to Owner review and approval of the DD package. Develop Construction Documents is extended by two weeks. Finalize Specifications is extended by one week. When will construction start?
Week 25
Week 26
Week 28
Create a free account and access millions of resources
Similar Resources on Quizizz
11 questions
3-2 Construction Observation

Quiz
•
University
14 questions
Building Information Modelling Quiz

Quiz
•
University
9 questions
2-1 Resource Management

Quiz
•
University
10 questions
Quiz on Quantity Surveying

Quiz
•
University
10 questions
SPP 200 - Code of Ethics (RA 9266)

Quiz
•
University
11 questions
S4.1 Return Brief & Fee Proposal

Quiz
•
University
15 questions
S26 Service

Quiz
•
University
10 questions
Construction management : Finances

Quiz
•
University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade