
2-2 Project Work Planning
Quiz
•
Architecture
•
University
•
Practice Problem
•
Hard
Centari Rodriguez
Used 1+ times
FREE Resource
Enhance your content in a minute
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is creating the workplan and schedule for a 3,200-square-foot tenant infill project. The project will have a documentation phase and a construction phase. The architect's fee is $20,000 and the project must be ready for permit in six weeks.
Critical path method
Milestone chart
Fast-track schedule
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Early in the construction document phase of a building renovation project, a mechanical engineer alerts the project manager that the architect has improperly classified the use of the space. The architect will need to revise the use of the space so that the mechanical engineer can correctly size a large portion of the HVAC system and revise the distribution duct layout.
What should the architect do first to address the improper classification?
Submit a request for additional services.
Take corrective actions to modify the project work plan.
Identify the impact on the previous construction cost estimate.
Advise the owner of the design conditions and their impact on the schedule.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Refer to the exhibit.
An architect planned $350,000 in labor costs and 2,800 hours for the construction documents phase of a project. The project is now at 25% construction documents.
How should the architect keep the project within budget?
Continue to work at the current pace for the remainder of the phase.
Use more experienced staff to reduce labor hours for the remainder of the phase.
Reduce the time planned for documentation quality control to meet the project deadline.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Early in the construction documents phase of a project, a fire protection engineer alerts the architect that the architect improperly classified the materials planned to be stored in a warehouse space. The architect will need to revise the analysis of the materials so that the fire protection engineer can correctly plan sprinkler coverage and fire pump sizing.
What should the architect do first to respond to the lack of coordination?
Develop and submit a request for additional services.
Identify and take corrective actions to modify the project work plan.
Advise the owner of the design conditions and any impact on the schedule.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is contracted with an owner using an AIA B101 agreement. During construction, the owner informs the architect in writing to change the configuration of the restrooms. The architect responds that this work will require a $2,000 fee and one week will be required to make changes to the drawings. The owner agrees to the fee and timeline, noting an urgency to complete the work. What should the architect do next?
Invoice the owner for the added service and confirm receipt of the payment before starting the work.
Begin the work immediately and issue an add service proposal to formalize the change in scope.
Provide an add service proposal for the owner's signature prior to starting the work.
6.
FILL IN THE BLANK QUESTION
1 min • 1 pt
An owner asks the architect to reduce the production portion of each project phase with a client review and approval activity by one week. In addition, the owner requests the client review and approval time at each phase be extended by three weeks. Project phases follow: Programming: 8 weeks Schematic Design: 8 weeks Design Development: 12 weeks Construction Documents: 16 weeks Bidding/Negotiation: 6 weeks Construction Contract Administration: 56 weeks By how many weeks should the architect extend the overall schedule?
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Refer to the exhibit.
An architect develops a proposed schedule prior to the beginning of design. After the schedule is developed, the following changes occur: One week is added to Owner review and approval of the DD package. Develop Construction Documents is extended by two weeks. Finalize Specifications is extended by one week. When will construction start?
Week 25
Week 26
Week 28
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
Building Laws Quiz 2- PD 1096
Quiz
•
KG - Professional Dev...
15 questions
Islamic Geometric Patterns and Symmetry
Quiz
•
University
14 questions
Mimari qad aldunia quiz
Quiz
•
University
10 questions
ARCHITECTURE TRIVIA
Quiz
•
University
10 questions
Professional Practice Quiz#2
Quiz
•
University
15 questions
BIM 2 QZ-01
Quiz
•
University
12 questions
Design of Steel Beam Quiz 7
Quiz
•
University
15 questions
CHAPTER 2: TRAPS AND DRAINAGE ABOVE & BELOW GROUND SYSTEM
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Architecture
7 questions
How James Brown Invented Funk
Interactive video
•
10th Grade - University
5 questions
Helping Build the Internet: Valerie Thomas | Great Minds
Interactive video
•
11th Grade - University
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
19 questions
Review2-TEACHER
Quiz
•
University
15 questions
Pre2_STUDENT
Quiz
•
University
20 questions
Ch. 7 Quadrilateral Quiz Review
Quiz
•
KG - University
